Question
Chapter 7, Problem 10P
a)
Summary Introduction
To determine: The crossover point in units.
Introduction: The crossover point is the point at which revenue and expenses of the firm are equal. The company will experience neither loss nor profit at break-even point. Feasibility of the project can be determined using the crossover point.
b)
Summary Introduction
To determine: The monthly profit or loss for high speed shredder when selling 60,000 bags per month.
c)
Summary Introduction
To determine: The monthly profit or loss for Clunker when selling 60,000 bags per month.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
California Gardens, Inc., prewashes, shreds, and distributes a variety of salad mixes in 2-pound bags. Doug Voss, Operations VP, is considering a new Hi-Speed shredder to replacethe old machine, referred to in the shop as "Clunker." Hi-Speed will have a fixed cost of $85,000 per month and a variable cost of $1.25 per bag. Clunker has a fixed cost of only $44,000 per month, but a variable cost of$ 1.75. Selling price is $2.50 per bag.a) What is the crossover point in units (point of indifference) for the processes?b) What is the monthly profit or loss if the company changes to the Hi-Speed shredder and sells 60,000 bags per month? c) What is the monthly profit or loss if the company stays with Clunker and sells 60,000 bags per month?
California Gardens, Inc., prewashes, shreds, and distributes a variety of salad mixes in 2-pound bags. Doug Voss, Operations VP, is considering a new Hi-Speed shredder to replace the old machine, referred to in the shop as "Clunker." Hi-Speed will have a fixed cost of $87,000 per month and a variable cost of $1.20 per bag. Clunker has a fixed cost of only $31,000 per month, but a variable cost of $1.70. Selling price is $2.40 per bag.
Part 2
a) What is the crossover point in units (point of indifference) for the processes?
The crossover point is units. (Round your response to the nearest whole number.)
California Gardens, Inc., prewashes, shreds, and distributes a variety of salad mixes in 2-pound bags. Doug Voss, Operations VP, is considering a new Hi-Speed shredder to replace the old machine, referred to in the shop as "Clunker." Hi-Speed will have a fixed cost of $87,000 per month and a variable cost of $1.20 per bag. Clunker has a fixed cost of only $31,000 per month, but a variable cost of $1.70. Selling price is $2.40 per bag.
Part 2
a) What is the crossover point in units (point of indifference) for the processes?
The crossover point is
112000112000
units. (Round your response to the nearest whole number.)
Part 3
b) What is the monthly profit or loss if the company changes to the Hi-Speed shredder and sells
90,000
bags per month?
The monthly profit or loss if the company changes to the Hi-Speed shredder and sells
90,000
bags per month is
$enter your response here.
(Round your response to the nearest dollar and include a minus sign if necessary.)
Chapter 7 Solutions
OPERTATIONS MGMT:SUSTAINABILITY
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - Prob. 4DQCh. 7.S - Prob. 5DQCh. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Similar questions
- California Gardens, Inc., prewashes, shreds, and distributes a variety of salad mixes in 2-pound bags. Doug Voss, Operations VP, is considering a new Hi-Speed shredder to replace the old machine, referred to in the shop as "Clunker." Hi-Speed will have a fixed cost of $87,000 per month and a variable cost of $1.20 per bag. Clunker has a fixed cost of only $31,000 per month, but a variable cost of $1.70. Selling price is $2.40 per bag. a) What is the crossover point in units (point of indifference) for the processes? The crossover point isunits. (Round your response to the nearest whole number.)arrow_forwardGordon Miller's job shop has four work areas, A, B, C, and D. Distances in feet between centers of the work areas are: A B C D A − 4 10 8 B − − 5 9 C − − − 9 D − − − − Workpieces moved per week between work areas are: A B C D A − 900 700 600 B − − 400 300 C − − − 600 D − − − − It costs Gordon $3 to move 1 work piece 1 foot. The weekly total material handling cost of the layout =....... $nothing (enter your response as a whole number). The weekly total material handling cost of the layout =....... nothing dollars (enter your response as a whole number).arrow_forwardMatthew Bailey, as manager of Designs by Bailey,is upgrading his CAD software. The high-performance (HP)software rents for $3,000 per month per workstation. Thestandard-performance (SP) software rents for $2,000 per monthper workstation. The productivity figures that he has availablesuggest that the HP software is faster for his kind of design.Therefore, with the HP software he will need five engineers and with the SP software he will need six. This translates into a vari-able cost of $200 per drawing for the HP system and $240 per drawing for the SP system. At his projected volume of 80 draw-ings per month, which system should he rent?arrow_forward
- Two manufacturing processes are being considered for making a new product. Process A is less capital intensive, with fixed costs of $60,000 per year and variable costs of $700 per unit. Process B has fixed costs of $400,000 annually, with variable costs of $300 per unit. What is the break-even quantity for the two processes? If annual sales are expected to be 700 units, which process should be selected? Operations and Engineering have found a way to reduce the cost of Process B, such that the fixed costs for this process decrease from $400,000 to $300,000 annually. All other costs remain the same. Does this change the process selection for the annual sales volume of 700 units?arrow_forwardMatthew Bailey, as manager of Designs by Bailey,is upgrading his CAD software. The high-performance (HP)software rents for $3,000 per month per workstation. Thestandard-performance (SP) software rents for $2,000 permonth per workstation. The productivity figures that he hasavailable suggest that the HP software is faster for his kind ofdesign. Therefore, with the HP software he will need five engineers and with the SP software he will need six. This translatesinto a variable cost of $200 per drawing for the HP system and$240 per drawing for the SP system. At his projected volumeof 80 drawings per month, which system should he rent?arrow_forwardCalifornia Gardens, Inc., prewashes, shreds, and dis-tributes a variety of salad mixes in 2-pound bags. Doug Voss, Operations VP, is considering a new Hi-Speed shredder to replacethe old machine, referred to in the shop as “Clunker.” Hi-Speedwill have a fixed cost of $85,000 per month and a variable costof $1.25 per bag. Clunker has a fixed cost of only $44,000 permonth, but a variable cost of $1.75. Selling price is $2.50 per bag.a) What is the crossover point in units (point of indifference) forEric Limon/ Shutterstock the processes? b) What is the monthly profit or loss if the company changes tothe Hi-Speed shredder and sells 60,000 bags per month?c ) What is the monthly profit or loss if the company stays withClunker and sells 60,000 bags per month?arrow_forward
- Draw a process fl ow diagram of your last doctor’s offi cevisit. Identify bottlenecks. Did any activities occur in parallel?arrow_forwardThere are four tasks performed in stations: mixing,, shaping, baking and packaging. Each cookie goes thru 1 of the 2 of shaping machines and 1 of the 3 baking ovens. Station 1 Mix 6.5 min/batch Station 2 shape 18 min/batch shape 10 min/batch Station 3 bake 17 min/batch bake 14 min/batch bake 35 min/batch Station 4 pack 9.8 min/batch 1. What is the Throughput time? 2. What is the Bottleneck time? 3. If factory operates 16 hours/day, 6 days/week, what is weekly capacity? 4. If upgrading some equipment to replace one of the existing operations. Which operation should be considered first?arrow_forwardExplain the importance of process selection in system design?arrow_forward
- A production process at Raider Red Manufacturing is shown below. There are five parallel Sawing operations, five parallel Sanding operations, two parallel Welding operations, and four parallel Assembly operations. Find the throughput of the overall system in minutes per unit.arrow_forwardHi, I need help with this Operations Mangement problem. Thank you!arrow_forwardAn assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are the tasks and their performance times: TASK PRECEDINGTASKS PERFORMANCE TIME (SECONDS) TASK PRECEDINGTASKS PERFORMANCETIME (SECONDS) a — 48 g d 43 b — 58 h e 38 c — 73 i f 23 d a 63 j g 33 e b 88 k h, i 53 f c 23 l j, k 67 A) What is the efficiency of your line balance? B) Suppose demand increases by 10 percent. How would you react to this? Assume that you can operate only 13 hours per day in regular time. (Round your answers to the nearest whole number.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.