Chapter 7, Problem 19QP
Summary Introduction
To identify: The project NPV.
Present Value:
It refers to the value of an amount today after considering the
Capital Budgeting:
The decision-related to the investment for long run is called capital budgeting. Capital budgeting includes the investment in the heavy machinery and information technology.
The net present value is a differential amount of the net
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Wayne Company is considering a long-term investment project called ZIP. ZIP will require an investment of $125,600. It will have a useful life of 4 years and no salvage value. Annual cash inflows would increase by $80,500, and annual cash outflows would increase by $42,000. The company’s required rate of return is 8%. Click here to view PV table.Calculate the net present value on this project. (If the net present value is negative, use either a negative sign preceding the number eg -45 or parentheses eg (45). Round present value answer to 0 decimal places, e.g. 125. For calculation purposes, use 5 decimal places as displayed in the factor table provided.)
Net present value
________?
Whether this project should be accepted?
The project should be ACCEPTED OR DECLINED???? .
You are examining a new project. You expect to sell 7,000 units per year at €60 net cash flow apiece for the next 10 years. The relevant discount rate is 16 per cent, and the initial investment required is €1,800,000.
a. What is the base-case NPV?
b. After the first year, the project can be dismantled and sold for €1,400,000. If expected sales are revised based on the first year’s performance, when would it make sense to abandon the investment? In other words, at what level of expected sales would it make sense to abandon the project?
c. Explain how the €1,400,000 abandonment value can be viewed as the opportunity cost of keeping the project in one year
You are examining a new project. You expect to sell 7,000 units per year at €60 net cash flow apiece for the next 10 years. The relevant discount rate is 16 per cent, and the initial investment required is €1,800,000.
a. After the first year, the project can be dismantled and sold for €1,400,000. If expected sales are revised based on the first year’s performance, when would it make sense to abandon the investment? In other words, at what level of expected sales would it make sense to abandon the project?
b. Explain how the €1,400,000 abandonment value can be viewed as the opportunity cost of keeping the project in one year
Chapter 7 Solutions
CONNECT 1 SEMESTER ACCESS CARD FOR CORPORATE FINANCE
Ch. 7 - Forecasting Risk What is forecasting risk? In...Ch. 7 - Sensitivity Analysis and Scenario Analysis What is...Ch. 7 - Prob. 3CQCh. 7 - Break-Even Point As a shareholder of a firm that...Ch. 7 - Prob. 5CQCh. 7 - Real Options Why does traditional NPV analysis...Ch. 7 - Real Options The Mango Republic has just...Ch. 7 - Prob. 8CQCh. 7 - Prob. 9CQCh. 7 - Project Analysis You are discussing a project...
Ch. 7 - Sensitivity Analysis and Break-Even Point We are...Ch. 7 - Prob. 2QPCh. 7 - Prob. 3QPCh. 7 - Prob. 4QPCh. 7 - Prob. 5QPCh. 7 - Decision Trees Ang Electronics. Inc., has...Ch. 7 - Decision Trees The manager for a growing firm is...Ch. 7 - Prob. 8QPCh. 7 - Prob. 9QPCh. 7 - Financial Break-Even Niko has purchased a brand...Ch. 7 - Prob. 11QPCh. 7 - Prob. 12QPCh. 7 - Project Analysis You are considering a new product...Ch. 7 - Project Analysis McGilla Golf has decided to sell...Ch. 7 - Prob. 17QPCh. 7 - Prob. 18QPCh. 7 - Prob. 19QPCh. 7 - Prob. 20QPCh. 7 - Prob. 21QPCh. 7 - Option to Wait Hickock Mining is evaluating when...Ch. 7 - Abandonment Decisions Allied Products, Inc., is...Ch. 7 - Prob. 24QPCh. 7 - Scenario Analysis You are the financial analyst...Ch. 7 - Scenario Analysis Consider a project to supply...Ch. 7 - Sensitivity Analysis In Problem 26, suppose youre...Ch. 7 - Prob. 28QPCh. 7 - Prob. 29QPCh. 7 - Financial Break-Even The Cornchopper Company is...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.Similar questions
- The J.R. Ryland Computer Company is considering a plant expansion to enable the company to begin production of a new computer product. The companys president must determine whether to make the expansion a medium- or large-scale project. Demand for the new product is uncertain, which for planning purposes may be low demand, medium demand, or high demand. The probability estimates for demand are 0.20, 0.50, and 0.30, respectively. Letting x and y indicate the annual profit in thousands of dollars, the firms planners developed the following profit forecasts for the medium-and large-scale expansion projects. a. Compute the expected value for the profit associated with the two expansion alternatives. Which decision is preferred for the objective of maximizing the expected profit? b. Compute the variance for the profit associated with the two expansion alternatives. Which decision is preferred for the objective of minimizing the risk or uncertainty?arrow_forwardHemmingway, Inc. is considering a $5 million research and development (R&D) project. Profit projections appear promising, but Hemmingway’s president is concerned because the probability that the R&D project will be successful is only 0.50. Furthermore, the president knows that even if the project is successful, it will require that the company build a new production facility at a cost of $20 million in order to manufacture the product. If the facility is built, uncertainty remains about the demand and thus uncertainty about the profit that will be realized. Another option is that if the R&D project is successful, the company could sell the rights to the product for an estimated $25 million. Under this option, the company would not build the $20 million production facility. The decision tree follows. The profit projection for each outcome is shown at the end of the branches. For example, the revenue projection for the high demand outcome is $59 million. However, the cost of the R&D project ($5 million) and the cost of the production facility ($20 million) show the profit of this outcome to be $59 – $5 – $20 = $34 million. Branch probabilities are also shown for the chance events. Analyze the decision tree to determine whether the company should undertake the R&D project. If it does, and if the R&D project is successful, what should the company do? What is the expected value of your strategy? What must the selling price be for the company to consider selling the rights to the product? Develop a risk profile for the optimal strategy.arrow_forwardRoberts Company is considering an investment in equipment that is capable of producing more efficiently than the current technology. The outlay required is 2,293,200. The equipment is expected to last five years and will have no salvage value. The expected cash flows associated with the project are as follows: Required: 1. Compute the projects payback period. 2. Compute the projects accounting rate of return. 3. Compute the projects net present value, assuming a required rate of return of 10 percent. 4. Compute the projects internal rate of return.arrow_forward
- Friedman Company is considering installing a new IT system. The cost of the new system is estimated to be 2,250,000, but it would produce after-tax savings of 450,000 per year in labor costs. The estimated life of the new system is 10 years, with no salvage value expected. Intrigued by the possibility of saving 450,000 per year and having a more reliable information system, the president of Friedman has asked for an analysis of the projects economic viability. All capital projects are required to earn at least the firms cost of capital, which is 12 percent. Required: 1. Calculate the projects internal rate of return. Should the company acquire the new IT system? 2. Suppose that savings are less than claimed. Calculate the minimum annual cash savings that must be realized for the project to earn a rate equal to the firms cost of capital. Comment on the safety margin that exists, if any. 3. Suppose that the life of the IT system is overestimated by two years. Repeat Requirements 1 and 2 under this assumption. Comment on the usefulness of this information.arrow_forwardThe Siler Construction Company is about to bid on a new industrial construction project. To formulate their bid, the company needs to estimate the time required for the project. Based on past experience, management expects that the project will require at least 24 months, and could take as long as 48 months if there are complications. The most likely scenario is that the project will require 30 months. a. Assume that the actual time for the project can be approximated using a triangular probability distribution. What is the probability that the project will take less than 30 months? b. What is the probability that the project will take between 28 and 32 months? c. To submit a competitive bid, the company believes that if the project takes more than 36 months, then the company will lose money on the project. Management does not want to bid on the project if there is greater than a 25% chance that they will lose money on this project. Should the company bid on this project?arrow_forwardMarkoff Products is considering two competing projects, but only one will be selected. Project A requires an initial investment of $42,000 and is expected to generate future cash flows of $6,000 for each of the next 50 years. Project B requires an initial investment of $210,000 and will generate $30,000 for each of the next 10 years. If Markoff requires a payback of 8 years or less, which project should it select based on payback periods?arrow_forward
- Waste Management Inc. is analyzing an average-risk project, and the following data have been developed. Unit sales will be constant, but the sales price will increase with inflation. Fixed costs will also be constant, but variable costs will rise with inflation. The project should last for 3 years, and there will be no salvage value. This is just one project for the firm, so any losses can be used to offset gains on other firm projects. What is the project's expected NPV? IRR? Would you accept this project? WACC 9.50% Net investment cost (depreciable basis) $100,000 Units sold 40,000 Average price per unit, Year 1 $25.00 Fixed op. cost excl. depr'n (constant) $150,000 Variable op. cost/unit, Year 1 $20.20 Annual depreciation rate 33.33% Expected inflation 5.00% Tax rate 40.0% Please show work.arrow_forwardLehigh Products Company is considering the purchase of nen automated equipment. The project has an expected set present value of $250,000 with a standard deviation of $100,000. Question: 1. What is the probability that the project will have a net present value less than $50,000, assuming that net present value is normally distributed?arrow_forwardThe plant manager of IHK is considering the purchase of a new robotic assemble plant. The new robotic line will cost $250,000. The manager believes that the new investment will result in direct labor savings of $62,500 per year for ten years.Requirements:a. What is the payback period for this projectb. What is the net present value or PV assuming a 10% rate of return?c. Should the plant manager accept or reject the project?d. What else should the manager consider in the analysis?arrow_forward
- 1 Downside scenarios Consider a proposal to produce and market a new tennis racquet. The most likely outcome scenario for the project incl. Expected sales of 30,000 units per year, Unit price of $200, Variable cost per racquet of $120, Fixed cost of $1,200,000. The project will last for 10 years and requires an initial investment of $4 million, which will be depreciated straight-line over the project life to a fnal value of zero. The firm´s tax rate is 30%, and the required rate of return is 12%. 1. What is the project NPV? However, you recognize that some of these estimates are subject to error. Sales could fall 20% below expectations for the life of the project and, if that happens, the unit price would probably be only $150. The good news is that Öxed costs could be as low as $800,000, and total Variable costs1 would decline in proportion to sales. 2. What is NPV in the worst-case scenario?3. How else could you consider the downside scenario in your NPV calculation? (Answer…arrow_forwardSuppose the MARR is 10% with probability 0.25, 12% with probability 0.50, and 15% with probability 0.25; what is the probability that Alternative A is the most economic alternative? Two investment alternatives are being considered. Alternative A requires an initial investment of $15,000 in equipment; annual operating and maintenance costs are anticipated to be normally distributed, with a mean of $5,000 and a standard deviation of $500; the terminal salvage value at the end of the 8-year planning horizon is anticipated to be normally distributed, with a mean of $2,000 and a standard deviation of $800. Alternative B requires endof-year annual expenditures over the planning horizon. The annual expenditure will be normally distributed, with a mean of $8,000 and a standard deviation of $750. Using a MARR of 15%, what is the probability that Alternative A is the most economic alternative?arrow_forwardA company is considering an investment that will require a cost outlay of $5,000 per year for the first five years and an extra $2000 at the beginning of Year 8. At the end of the project, the salvage value will be $15,000. The project will yield returns of $8500 at the end of each year from Year 4 to Year 10. There are no returns after Year 10. Providing a 21% rate of return, what is the NPV? If your answer is negative, be sure to place a (-) sign before the number.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTEssentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage Learning
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeIntermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License