CORPORATE FIN.(LL)-W/ACCESS >CUSTOM<
CORPORATE FIN.(LL)-W/ACCESS >CUSTOM<
11th Edition
ISBN: 9781260269901
Author: Ross
Publisher: MCG CUSTOM
bartleby

Videos

Textbook Question
Book Icon
Chapter 7, Problem 26QP

Scenario Analysis Consider a project to supply Detroit with 25,000 tons of machine screws annually for automobile production. You will need an initial $2,700,000 investment in threading equipment to get the project started; the project will last for five years. The accounting department estimates that annual fixed costs will be $275,000 and that variable costs should be $265 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over !he five-year project life. It also estimates a salvage value of $250,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $345 per ton. The engineering department estimates you will need an initial net working capital investment of $400,000. You require a 13 percent return and face a marginal tax rate of 38 percent on this project.

  1. a. What is the estimated OCF for this project? The NPV? Should you pursue this project?
  2. b. Suppose you believe that the accounting department’s initial cost and salvage value projections are accurate only to within ±15 percent; the marketing department’s price estimate is accurate only to within ±10 percent; and the engineering department’s net working capital estimate is accurate only to within ±5 percent. What is your worst-case scenario for this project? Your best-case scenario? Do you still want to pursue the project?

a)

Expert Solution
Check Mark
Summary Introduction

To determine: The operating cash flow and net present value.

Introduction:

Net present value (NPV) refers to the discounted value of the future cash flows at present. The company should accept the project, if the net present value is positive or greater than zero and vice-versa. If there are two mutually exclusive projects, then the company has to select the project that has higher net present value.

Answer to Problem 26QP

Solution: The operating cash flow is $1,274,700 and the net present value is $1,684,650.59.

Explanation of Solution

Given information:

The annual fixed costs are $275,000, variable cost per unit is $265 per ton, number of quantity supplied is 25,000, marginal tax rate is 38%, initial investment on the equipment is $2,700,000, and life of the project is five years. The net initial working capital investment is $400,000 and required rate of return is 13%. The salvage value is $250,000. The selling price is $345 per ton. The marginal tax rate at 38%

The formula to calculate the operating cash flow:

Operating cash flow=([(Unit sold×[Selling priceVariable price])Fixed cost]×(1Tax rate)+(Depreciation×Tax rate))

The formula to calculate the net present value:

NPV =([(Initial investmentInitial working capital investment)+(Estimated Operating cash flow(Present value of an annuity of $1 period for R% of N period))]+[Net initial working capital investment+Salvage value(1Marginal tax rate)(1+Required rate of return)n])

Where,

n refers to the number of years.

Compute the operating cash flows:

Operating cash flow=([(Unit sold×[Selling priceVariable price])Fixed cost]×(1Tax rate)+(Depreciation×Tax rate))=([(25,000×[$345$265])$275,000]×(10.38)+($2,700,0005×0.38))=($1,069,500+$205,200)=$1,274,700

Hence, the operating cash flow is $1,274,700.

Compute the net present value:

Note: The increase in operating cash flow at present value of interest factor annuity at 13% for 5 years is 3.51723.

Calculate the net present value:

NPV =([(Initial investmentInitial working capital investment)+(Estimated operating cash flow(Present value of an annuity of $1 period for R% of N period))]+[Net initial working capital investment+Salvage value(1Marginal tax rate)(1+Required rate of return)n])=([($2,700,000$400,000)+($1,274,700(3.51723))]+[$400,000+$250,000(10.38)(1+0.13)5])=$1,383,413.081+[$400,000+$155,0001.8424]

=$1,383,413.081+$301,237.51=$1,684,650.59

Hence, the net present value is $1,684,650.59.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The worst-case scenario and best-case scenario of the project.

Introduction:

Scenario analysis is a process of analyzing the possible future events. This analysis helps to determine the effect of what-if questions towards the net present value estimates. At the time when the firm begins to look for an alternative, then they can be able to find the possible project, which would result in positive net present value (NPV).

Answer to Problem 26QP

Solution:

Worst-case scenario:

The operating cash flow of the worst-case scenario is $770,730 and the NPV of worst-case scenario is −$514,691.82.

Best-case scenario:

The operating cash flow of the best-case scenario is $1,778,670 and the NPV of best-case scenario is $3,883,992.99.

Explanation of Solution

Given information:

The annual fixed costs are $275,000, variable cost per unit is $265 per ton, number of quantity supplied is 25,000, marginal tax rate is 38%, initial investment on the equipment is $2,700,000, and life of the project is five years. The net initial working capital investment is $400,000 and required rate of return is 13%. The salvage value is $250,000. The selling price is $345 per ton. The marginal tax rate at 38%

Formulae:

The formula to calculate the operating cash flow for best or worst-cases scenarios:

Operating cash flow of best or worst case scenario}=[(Pv)QFC]×(1Tax rate)+Tax rate×Depreciation

Where,

P refers to the price per unit of the project

v refers to the variable cost per unit

Q refers to the number of unit sold

FC refers to the fixed costs

The formula to calculate the NPV of best or worst-cases:

Net present value of best or worst-cases}=Initial investment+Best or worst-cases operating cash flow

Note: In the best-case scenario, both the price and sales indicates an increase in the value whereas the costs will indicate a decrease in the value. In the worst-case scenario, both the price and sales indicates a decrease in the value but the costs will specify an increase in the value.

Compute the operating cash flow for worst-case scenario:

Note: The tax shield approach is used to determine the operating cash flow of the worst-case scenario. In this given problem, the price and quantity is decreased by 10%. As a result, both price and quantity is multiplied by 10 percent decrease. However, the variable and fixed costs will indicate an increase by 15 percent.

Operating cash flow of worst-case scenario}=[(Pv)QFC]×(1Tax rate)+Tax rate×Depreciation=[($345(10.1)$265)25,000$275,000]×(10.38)+0.38×($2,700,000(1+0.15)5)=($1,137,500$275,000)×0.62+0.38×$621,000

=$534,750+$235,980=$770,730

Hence, the operating cash flow of the worst-case scenario is $770,730.

Compute the NPV of worst-case scenario:

Net present value =([(Initial investmentInitial working capital investment)+(Estimated Operating cash flow(Present value of an annuity of $1 period for R% of N period))]+[Net initial working capital investment+Salvage value(1Marginal tax rate)(1+Required rate of return)n])=([(($2,700,000(1+0.15)5)$400,000(1+0.05)+($770,730(3.51723))]+[$400,000(1+0.05)+$250,000(10.15)(10.38)(1+0.13)5])=$3,105,000$420,000+$2,710,834.67+[$420,000+$131,7501.8424]

=$814,165.33+$299,473.51=$514,691.82

Hence, the NPV of the worst-case scenario is −$514,691.82.

Compute the operating cash flow for best-case scenario:

Operating cash flow of best-case scenario}=[(Pv)QFC]×(1Tax rate)+Tax rate×Depreciation=[($345(1+0.10)265)25,000$275,000]×(10.38)+0.38×($2,700,000(10.15)5)=($2,862,500$275,000)×0.62+0.38×$459,000

=$1,604,250+$174,420=$1,778,670

Hence, the operating cash flow of the best-case scenario is $1,778,670.

Compute the net present value of best-case scenario:

Net present value =([(Initial investmentInitial working capital investment)+(Estimated operating cash flow(Present value of an annuity of $1 period for R% of N period))]+[Net initial working capital investment+Salvage value(1Marginal tax rate)(1+Required rate of return)n])=($2,700,000(10.15)5)$400,000(10.05)+$1,778,670×3.51723+$400,000(10.05)+$250,000(1+0.15)(10.38)(1+0.13)5=$2,295,000$380,000+$6,255,991.48+($380,000+$178,250(1+0.13)5)=$3,580,991.48+$558,2501.8424

=$3,580,991.48+$303,001.51=$3,883,992.99

Hence, the net present value of the best-case scenario is $3,883,992.99.

Expert Solution
Check Mark
Summary Introduction

To discuss: Whether the project is pursued or not based on the computation of NPV.

Explanation of Solution

The worst-case scenario indicates a negative NPV whereas the best-case indicates the positive NPV. Therefore, to proceed with the project would not be difficult.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
Recommended textbooks for you
Text book image
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Financial Management: Theory & Practice
Finance
ISBN:9781337909730
Author:Brigham
Publisher:Cengage
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Text book image
EBK CFIN
Finance
ISBN:9781337671743
Author:BESLEY
Publisher:CENGAGE LEARNING - CONSIGNMENT
Fixed Asset Replacement Decision 1235; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=LJRzn9K8Nwk;License: Standard Youtube License