Interpretation:The network diagram is to be drawn.
Concept Introduction:Network diagram is a graphical representation of tasks in symbols and lines for easy understanding. The networking technique is a method for planning, programming and controlling of work in progress. It is helpful for effective management. It helps the management for decisions.
B
Interpretation:The critical path and duration of the project are to be determined.
Concept Introduction:Critical path is a technique which has various stages. It is used to calculate the optimum time is requiredto complete a task. It is the longest length of time for completion of the project.
C
Interpretation:The slack for each activity is to be determined.
Concept Introduction:Slack is the time evaluatedwhich causes the delay during any activity. For calculation, the earliest and the latest time of activity are required.
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Chapter 7 Solutions
MyLab Operations Management with Pearson eText -- Access Card -- for Operations Management: Processes and Supply Chains
- (Use the information below to solve Q11 - Q20) Given the following information regarding a project: Predecess ors None None a a b b Activity a b C d e CD f OC g h Duration 3 1 3 4 4 5 23 c, e f Which of the following is NOT a path in the network? O a-d O a-c-g b-c-g O b-e-g b-f-harrow_forwardEarned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: No Type Cumulative Budgeted Cost (CBC) 2 Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) 1 3 TOTAL RM i. ii. iii. iv. 64,000 68,000 54,000 100,000 Percentage 64.0 Cost performance Index (CPI) [hint: CEV/CAC] Cost variance (VC) [hint: CEV-CAC] 68.0 54.0 a) Based on question 2(a), calculate and elaborate the various of indicators of cost performance for this project based on the respective below: 100.0 Forecasted cost of completion (FCAC) with action taken [hint: TBC/CPI] Forecasted cost of completion (FCAC) without any action taken [hint: CAC + [TBC-CEV]arrow_forwardA project manager has compiled a list of major activities that will be required to install a new CCTV system in the office. The list includes estimated completion time for activities and precedence relationship. Determine the Critical Path Activities Compute for Total Project Duration Note: Use MS Excel QM Activity Immediate Predecessor Estimated Times (weeks) 2-4-6 A D A 6-8-10 E D 7-9-12 E 2-3-5 IF A 3-4-8 F 5-7-9 2-2-3 2-3-6 J 3-4-5 K 4-5-8 5-8-12 M 1-1-1 IN M 6-7-11 8-9-13 End |Н, G, К, Оarrow_forward
- The following information is known about a project toupgrade a point-of-sale system at Kids and Tots Apparel.Activity Activity Time (days) Immediate Predecessor(s)A 7 —B 2 A C 4 AD 4 B, CE 4 DF 3 EG 5 Ea. Draw the network diagram for this project.b. Determine the critical path and project duration.c. Calculate the slack for each activity.arrow_forwardHow can a business analyst communicate requirements (and associated models) for a project in project management.arrow_forwardReliable Garage is completing production of the J2000 kit car. The following data are available for the project:a. Draw the network diagram for the project. b. Determine the project’s critical path and duration. c. What is the slack for each activity?arrow_forward
- Ql: For the project listed below, find the following items: 1- Total project finishing time, 2- Critical path 3- Free float for each task. 4- If Activity B is delayed by 7 weeks. As a project manager explains how this will affect the total project critical path. Dependency or Predecessor Activity الفعالية Duration in Weeks المدة بالأسابيع Activities الاعتمادية او الفعاليات السابقة C 6. 4 3 A 7 С, В, Р U 4 T 2 A 3 A 6. Uarrow_forwardReliable Garage is completing production of the J2000 kit car. The following data are available for the project:a. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forwardCreate a Network Diagram and Critical Path using the Data. Determine the minimum project duration. The duration of each activity is in days.arrow_forward
- A project consisting of the following activities: Activities predece.Activities day TE M K J H G E C B G KJ G I,F D D E,C B,A| B,A A 1 3 4 6. 5 2 3 9 6 2 4 3 5 1- Draw the network diagram of the project 2- Calculate (Es) and (Lc) the project events 3- Select the critical path 4 - What is the minimum time required to complete the project?arrow_forward(please try to do math in handwritten) Use the following project data for problem 1 through 5 Activity name Predecessor Activity Activity Duration N 3 M 2 P M,N 4 3 P,Q R,S 2. 1. Prepare an AON Network Diagram 2. Identify all possible paths. Provide that information in a table. The heading of your table should as follow: Path Duration 3. Perform a forward pass and a backward pass. Display your result in an AON diagram.Usethe follow legend for your node(s) Activity ES EF Duration LS LF 4. Prepare a table summarizing the results of your Activity Schedule. The heading of your table should as follows: Activity name ES Slack EF LS LF 5. Identify the critical path. What is the project duration? 2. 4.arrow_forwardscenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a Website' : Activity Description Duration (days) Preceding Activities A Determine user needs 8 Review s/w and languages Purchase software 10 Design format and style 10 E Write programs A F Review outcome product with user 12 G Make revisions 4 C H Select server site E I Install on server 14 D, F Test G, H, I 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities) 7. what would happen if activity D revised to take 14 instead of 10 days?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)