Question
Book Icon
Chapter 7.S, Problem 15P

a)

Summary Introduction

To determine: The bottleneck operation.

Bottleneck time:

The bottleneck time of the system is the process in the system that takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

b)

Summary Introduction

To determine: The bottleneck time of the bottleneck operation.

Bottleneck time:

The bottleneck time of the system is the process in the system that takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

c)

Summary Introduction

To determine: The throughput time of the overall system.

Throughput time:

The throughput time of a system is the time taken for a product to pass from the raw materials stage to the finished goods stage. The higher the throughput time, the more efficient the system will be.

d)

Summary Introduction

To determine: The monthly capacity of the manufacturing process.

Bottleneck time:

The bottleneck time of the system is the process in the system that takes the most amount of time to complete its activity. The bottleneck time will reduce the overall efficiency of the system.

Monthly capacity:

The monthly capacity is the number of units the firm is able to produce in a month’s time. It will be calculated taking into consideration the resources and constraints present in the manufacturing process.

Blurred answer
Students have asked these similar questions
A computer factory in Tangerang plans to increase production line for new products and plan to produce as many as XX0 units per hour. Production process, production time and production process to continue the next production process are described in the table below: (1 day = 8 working hours) production process production time Production process that follows the next production according to the list below A 12 - B 15 A C 8 A D 5 B,C E 20 D a. What is the cycle time for the production of the new product? ( note : in second )b. What is the minimum number of workstations?c. Draw a diagram of the production process.d. Is it with the diagram that you have drawn, the production process can go according to plan? Describe the process from each workstation you've created!
7-383   A plant manager needs a design for an assembly line to assembly a new product that is being introduced. The time requirements and immediate predecessors for the work elements are as follows:   Work Element Time (sec) Immediate Predecessor A 12 – B 60 A C 36 – D 24 – E 38 C, D F 72 B, E G 14 – H 72 – I 35 G, H J 60 I K   12 F, J Total   = 435     1.If the desired output rate is 30 units per hour, what are the cycle time and theoretical minimum? 2.Suppose that we are fortunate enough to find a solution with just four stations. What is the idle time per unit, efficiency, and the balance delay for this solution?
A) Which step in this process is the bottleneck? =30 min for tan leather B) How many briefcases are processed at the bottleneck workstation per hour?=60/30=2 briefcases per hr C) What is the throughput time of the overall process?=30+15+10+10+10 Throughput = 75 minutes   given the above information please answer qestions 1-3 below.  If the manufacturing facility operates 8 hours per day, 250 days a year, what is the annual capacity of this manufacturing process.  Assume the company decides to hire additional workers in order to duplicate the bottleneck step identified in part a so that there are 3 of these workstations instead of 1. Redraw the diagram showing the flow of the revised process.  Answer parts a through d again based on the new process created in part e?

Chapter 7 Solutions

Operations Management 11/e (2 Colors) By Heizer (2015-12-25)

Ch. 7.S - Explain how net present value is an appropriate...Ch. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the past month, the plant in Problem S7.1,...Ch. 7.S - If a plant has an effective capacity of 6,500 and...Ch. 7.S - Prob. 4PCh. 7.S - Material delays have routinely limited production...Ch. 7.S - Prob. 6PCh. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Under ideal conditions, a service bay at a Fast...Ch. 7.S - A production line at V. J. Sugumarans machine shop...Ch. 7.S - A work cell at Chris Ellis Commercial Laundry has...Ch. 7.S - The three-station work cell Illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Klassen Toy Company, Inc., assembles two parts...Ch. 7.S - Prob. 15PCh. 7.S - Prob. 16PCh. 7.S - Markland Manufacturing intends to increase...Ch. 7.S - Using the data in Problem S7.17. a. What is the...Ch. 7.S - Given the data in Problem S7.17, at what volume...Ch. 7.S - Janelle Heinke, the owner of HaPeppas!, is...Ch. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - As a prospective owner of a club known as the Red...Ch. 7.S - Prob. 27PCh. 7.S - James Lawsons Bed and Breakfast, in a small...Ch. 7.S - Prob. 29PCh. 7.S - Prob. 30PCh. 7.S - Prob. 31PCh. 7.S - What is the present value of 5,600 when the...Ch. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Bolds Gym, a health club chain, is considering...Ch. 7.S - Prob. 1VCCh. 7.S - Prob. 2VCCh. 7.S - Prob. 3VCCh. 7 - What is process strategy?Ch. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - What is process redesign?Ch. 7 - Prob. 5DQCh. 7 - Name the tour quadrants of the service process...Ch. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Identify manufacturing firms that compete on each...Ch. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 11DQCh. 7 - Identify the competitive advantage of each of the...Ch. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Explain what a flexible manufacturing system (FMS)...Ch. 7 - Prob. 17DQCh. 7 - Prepare a flowchart tor one of the following: a....Ch. 7 - Prob. 2PCh. 7 - Prepare a time-function map for one of the...Ch. 7 - Prepare a service blueprint for one of the...Ch. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Ski Boards, Inc., wants to enter the market...Ch. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Using Figure 7.6 in the discussion of value-stream...Ch. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Rochester Manufacturings Process Decision...Ch. 7 - Prob. 2CSCh. 7 - Prepare the case for an optimistic sales manager...Ch. 7 - Prob. 1.1VCCh. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Prob. 2.1VCCh. 7 - Prob. 2.2VCCh. 7 - Process Strategy at Wheeled Coach Video Case Video...Ch. 7 - Prob. 2.4VC
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.