a)
To determine: The unit cost for 20 units.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
a)
Answer to Problem 9P
Explanation of Solution
Given information:
Formula:
Calculation of unit cost for 20 units:
The time to compute the unit cost for 20 units is to compute the average cost for 20 units. It can be computed by finding labor cost, material cost, overhead cost and total cost. From the total cost, the average cost is computed.
Estimation of labor, material, overheads and total cost:
At 90% learning curve, the unit factor for 20 unit is 14.608 (using learning curve coefficient table)
The time for completing the 20 units is calculated by multiplying 5 with the unit factors 14.608 which yields 73.04 hours.
The labor cost is calculated by multiplying 73.045 hours with 8.50 which yields $620.84.
Material cost is calculated by multiplying 20 units with $20 per unit which yields $400.
The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $535.42
The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $620.84, $535.42 and $400.00 which yields $1,606.26.
The average cost per unit is calculated by dividing $1,606.26 with 20 which yields $80.31.
Hence, the unit cost for 20 units is $80.31.
b)
To determine: The minimum production quantity necessary to make the production cost less than the purchase cost.
Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.
b)
Answer to Problem 9P
Explanation of Solution
Given information:
Formula:
Calculation of minimum production quantity necessary to make the production cost less than the purchase cost:
The production cost per unit is $80.31 per unit for 20 units and it is less than the purchase cost which is $88.50 per unit. By trial and error approach the numbers which accounts to less than the purchase cost is computed which are 10 units.
Estimation of labor, material, overheads and total cost:
At 90% learning curve, the unit factor for 10 unit is 7.994 (using learning curve coefficient table)
The time for completing 10 units is calculated by multiplying 5 with the unit factors 7.994 which yields 39.97 hours.
The labor cost is calculated by multiplying 39.97 hours with 8.50 which yields $339.75.
Material cost is calculated by multiplying 10 units with $20 per unit which yields $200.
The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $294.88
The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $339.75, $294.88 and $200 which yields $884.63.
The average cost per unit is calculated by dividing $884.63 with 10 which yields $88.46 which is less than $88.50.
Hence, the minimum production quantity necessary to make the production cost less than the purchase cost is $88.46.
Want to see more full solutions like this?
Chapter 7 Solutions
Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
- National Company is planning to introduce a new product with an 90 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the total labor cost for the cumulative total time using the incremental unit-time learning curve to produce 2,000 units?arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 21 hours. The contractor estimates a 90 percent learning rate. Part 2 a. How long do you estimate the time required to install the second pool? enter your response here hours. (Enter your response rounded to two decimal places.) Part 3 b. How long do you estimate the time required to install the fourth pool? enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardYour company has received an order for 60 units of a product. The labor cost to produce the item is $22 per hour. The setup cost for the item is $1200 and material costs are $80 per unit. The learning rate is 80 percent. Overhead costs are charged at a rate of 60 percent of material cost. Determine the average production unit cost for the 60 units if the first unit takes 12 hours. The item is sold for $219.99 per unit. Should your company take this order? Why or why not? Determine the minimum number of units that need to be made before it makes sense to accept the order. Show breakdown of workarrow_forward
- You are asked to do a learning curve analysis as part of your internship project, but you discover that the data is pretty slim. Unfortunately you don't have time to do more field work and you have to come up with the best estimate based on the available data. Here's what you know: It took 98.71 minutes to complete the seventh unit and only 89.35 minutes to complete the twelfth unit. What is your best estimate of the Learning Rate for this process?arrow_forwardMass Balance Company is manufacturing a new digital scale for use by a large chemical company. The order is for 40 units. The first scale took 60 hours of direct labor. The second unit took 48 hours to complete.a. What is the learning rate?b. What is the estimated time for the 40th unit?c. What is the estimated total time for producing all 40 units?d. What is the average time per unit for producing the last 10 units (#31–#40)?arrow_forwardSuppose the 1st unit takes 15 hours to be produced and the learning rate is 82% , find time taken for 4th unit using incremental method ?arrow_forward
- You need to develop a labor time estimate for a customer order of 50 network installations. It is estimated that the first installation will require 75 labor hours and a learning curve of 85 percent is expected. a. How many labor hours are required for the 25th installation?b. How many labor hours are required to complete all 50 installations? c. If the average labor cost is $28 per hour, what is the total labor cost for installing all the networks?d. How many workers are needed to complete the job in a week? Assuming each worker works 8 hours per day 5 days per week. Show breakdown of workarrow_forwardIn your own words, describe self-paced, technology-based learning. Next, explain the benefits and drawbacks of this training method. Finally, describe 2 training topics that this teaching method would be best used for and explain why.arrow_forwardLearning Curves 1. Mass Balance Company is manufacturing a new digital scale for use by a large chemical company. The order is for 40 units. The first scale took 60 hours of direct labor. The second unit took 54 hours to complete. a) What is the learning rate? b) What is the estimated time for the 40th unit? c) What is the estimated total time for producing all 40 units? d) What is the average time per unit for producing the last 10 units (#30 - #40)?arrow_forward
- The time to asaemble the first unit on a production line is 19 hours. The learning rate is 0.85. Approximately how long will it take for the fifth unit to be assembled?arrow_forwardSuppose a manufacturer of copiers has concluded that a 70 percent learning curve applies to the time a beginning service technician takes to install copy machines. Use the Learning Curve Excel template to answer the following questions: If the time required to install the first copy machine is estimated to be five hours, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 it takes hours For x = 3 it takes hours If the learning rate changes to 65 or 95 percent, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 and a 65% LC, it takes hours For x = 3 and a 65% LC, it takes hours For x = 2 and a 95% LC, it takes hours For x = 3 and a 95% LC, it takes hoursarrow_forwardWhat is an example of the learning curve for a business operation where the average costs were reduced due to cumulative production experience?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.