ESSENTIALS OF CORPORATE FINANCE (LL)
ESSENTIALS OF CORPORATE FINANCE (LL)
9th Edition
ISBN: 9781260282191
Author: Ross
Publisher: MCG
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 8, Problem 11QP
Summary Introduction

To calculate: The rate of crossover for two projects and sketch the NPV profile.

Introduction:

The net present value is one of the capital budgeting techniques, which is used to identify the profitability in the proposed investment. The internal rate of return is a rate of discount, which makes the predictable investment’s NPV equals zero.

Expert Solution & Answer
Check Mark

Answer to Problem 11QP

The crossover rate for the two projects is 7.62%. The NPV profiles shows that both projects have a higher NPV for the rate of discount below 7.62% and have a lower NPV for the rate above 7.62%.

Explanation of Solution

Given information:

The details of two projects are provided. The cash flows of project X for year 1, year 2, and year 3, are $13,100, $9,480, and $7,890 respectively. The initial investment is $23,400. The project Y cash flows for 4 years are $9,200, $10,620, $11,180 respectively and the initial investment is $23,400.

Note:

  • NPV is the difference between the present values of the cash inflows and the present value of the cash outflows.
  • The IRR is the rate of interest, which makes the project’s NPV equals zero. Hence, using the available information, assume that NPV is equal to zero and form an equation to compute the IRR.

Equation of NPV to compute IRR assuming that NPV is equal to zero:

NPV=0=$23,400+$13,100(1+IRR)+$9,480(1+IRR)2+$7,890(1+IRR)30=$23,400+$13,100(1+IRR)+$9,480(1+IRR)2+$7,890(1+IRR)3

Compute IRR for project X using a spreadsheet:

Step 1:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  1

  • Type the equation of NPV in H6 in the spreadsheet and consider the IRR value as H7.

Step 2:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  2

  • Assume the IRR value as 10%.

Step 3:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  3

  • In the spreadsheet, go to data and select the What-if analysis
  • In What-if analysis, select Goal Seek.
  • In “Set cell”, select H6 (the formula).
  • The “To value” is considered as 0 (the assumption value for NPV).
  • The H7 cell is selected for “By changing cell”.

Step 4:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  4

  • Following the previous step, click OK in the Goal Seek Status. The Goal Seek Status appears with the IRR value.

Step 5:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  5

  • The value appears to be 15.980199204821%.

Hence, the IRRvalue is 15.98%.

Equation of NPV to compute IRR assuming that NPV is equal to zero:

NPV=0=$23,400+$9,200(1+IRR)+$10,620(1+IRR)2+$11,180(1+IRR)30=$23,400+$9,200(1+IRR)+$10,620(1+IRR)2+$11,180(1+IRR)3

Compute IRR for project Y using a spreadsheet:

Step 1:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  6

  • Type the equation of NPV in H6 in the spreadsheet and consider the IRR value as H7.

Step 2:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  7

  • Assume the IRR value as 10%.

Step 3:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  8

  • In the spreadsheet, go to data and select the What-if analysis.
  • In What-if analysis, select Goal Seek.
  • In “Set cell”, select H6 (the formula).
  • The “To value” is considered as 0 (the assumption value for NPV).
  • The H7 cell is selected for “By changing cell”.

Step 4:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  9

  • Following the previous step, click OK in the Goal Seek Status. The Goal Seek Status appears with the IRRvalue.

Step 5:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  10

  • The value appears to be 14.953339658603%.

Hence, the IRRvalue is 14.95%.

Formula to compute the crossover rate:

Crossover rate for each year=Cash flows from project XCash flows from project Y

Equation of crossover rate to compute R:

0=$3,900(1+R)$1,140(1+R)2$3,290(1+R)3

Where,

R denotes the crossover rate.

Compute R using a spreadsheet:

Step 1:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  11

  • Type the equation of NPV in H6 in the spreadsheet and consider the IRR value as H7.

Step 2:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  12

  • Assume the IRR value as 10%.

Step 3:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  13

  • In the spreadsheet, go to data and select the What-if analysis.
  • In What-if analysis, select Goal Seek.
  • In “Set cell”, select H6 (the formula).
  • The “To value” is considered as 0 (the assumption value for NPV).
  • The H7 cell is selected for “By changing cell”.

Step 4:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  14

  • Following the previous step, click OK in the Goal Seek Status. The Goal Seek Status appears with the IRRvalue.

Step 5:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  15

  • The value appears to be 7.61811282095653%.

Hence, the R-value is 7.62%.

Formula to calculate the NPV:

NPV=Present value of cash inflowPresent value of cash outflow

Note: As the discount rate is over a range of 0% to 25%, calculate NPV for 0%, 5%, 10%, 15%, 20%, and 25%.

Compute the NPV with the discount rate of 0% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($13,100(1+0)+$9,480(1+0)2+$7,890(1+0)3)$23,400=$7,070

Compute the NPV with the discount rate of 0% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($9,200(1+0)+$10,620(1+0)2+$11,180(1+0)3)$23,400=$7,600

Hence, the NPV for project X and Y at 0% are $7,070 and $7,600 respectively.

Compute the NPV with the discount rate of 5% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($13,100(1+0.05)+$9,480(1+0.05)2+$7,890(1+0.05)3)$23,400=$12,476.19048+$8,598.639456+$6,815.678652$23,400=$4,490.51

Compute the NPV with the discount rate of 5% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($9,200(1+0.05)+$10,620(1+0.05)2+$11,180(1+0.05)3)$23,400=$8,761.904762+$9,632.653061+$9,657.704352$23,400=$4,652.26

Hence, the NPV for project X and Y at 5% are $4,490.51 and $4,652.26 respectively.

Compute the NPV with the discount rate of 10% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($13,100(1+0.10)+$9,480(1+0.10)2+$7,890(1+0.10)3)$23,400=$11,909.09091+$7,834.710744+$5,927.873779$23,400=$2,271.68

Compute the NPV with the discount rate of 10% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($9,200(1+0.10)+$10,620(1+0.10)2+$11,180(1+0.10)3)$23,400=$8,363.636364+$8,776.859504+$8,399.699474$23,400=$2,140.20

Hence, the NPV for project X and Y at 10% are $2,271.68 and $2,140.20 respectively.

Compute the NPV with the discount rate of 15% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($13,100(1+0.15)+$9,480(1+0.15)2+$7,890(1+0.15)3)$23,400=$11,391.30435+$7,168.241966+$5,187.803074$23,400=$347.35

Compute the NPV with the discount rate of 15% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($9,200(1+0.15)+$10,620(1+0.15)2+$11,180(1+0.15)3)$23,400=$8,000+$8,030.245747+$7,351.031479$23,400=$18.72

Hence, the NPV for project X and Y at 15% are $347.35 and -$18.72 respectively.

Compute the NPV with the discount rate of 20% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($13,100(1+0.20)+$9,480(1+0.20)2+$7,890(1+0.20)3)$23,400=$10,916.66667+$6,583.333333+$4,565.972222$23,400=$1,334.03

Compute the NPV with the discount rate of 20% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($9,200(1+0.20)+$10,620(1+0.20)2+$11,180(1+0.20)3)$23,400=$7,666.666667+$7,375+$6,469.907407$23,400=$1,888.43

Hence, the NPV for project X and Y at 20% are -$1,334.03 and -$1,888.43 respectively.

Compute the NPV with the discount rate of 25% for project X:

NPV=Present value of cash inflowPresent value of cash outflow=($13,100(1+0.25)+$9,480(1+0.25)2+$7,890(1+0.25)3)$23,400=$10,480+$6,067.2+$4,039.68$23,400=$2,813.12

Compute the NPV with the discount rate of 25% for project Y:

NPV=Present value of cash inflowPresent value of cash outflow=($9,200(1+0.25)+$10,620(1+0.25)2+$11,180(1+0.25)3)$23,400=$7,360+$6,796.8+$5,724.16$23,400=$3,519.04

Hence, the NPV for project X and Y at 25% are -$2,813.12 and -$3,519.04 respectively.

NPV profile:

ESSENTIALS OF CORPORATE FINANCE (LL), Chapter 8, Problem 11QP , additional homework tip  16

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Reconsider Example 11.6, where the expected cash flows for the Capstone project arePeriod             0                1                2               3            4             5Cash Flow  -$55,000    $17,094     $20,439   $20,069   $20,212    $29,660Suppose that Capstone consider the MicroCHP project to be just one of their normal risky projects. Then the appropriate discount rate to use is 15%. However, Capstone considers the MicroCHP project to be much riskier than normal projects, so it believes an additional risk premium of 6.93% should be added. If management has decided to use a risk-adjusted discount rate of 21.93% to compensate for the uncertainty of the cash flows, is this project acceptable?
P2)*A project will have one of the following time 1 payoffs, each with the corresponding probability. $99 with probability 13%.$314 with probability 58%.$506 otherwise. The discount rate is 9.8%. The project is partially financed with debt with a time 1 promised payoff of $218. What is the promised return on the debt? Give your answer in percentage to the nearest 0.1 percent.
Y8 For the given cash flows, suppose the firm uses the NPV decision rule. Year Cash Flow 0 −$ 149,000 1 67,000 2 72,000 3 56,000 At a required return of 8 percent, what is the NPV of the project? Note: Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16. At a required return of 21 percent, what is the NPV of the project? Note: A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.

Chapter 8 Solutions

ESSENTIALS OF CORPORATE FINANCE (LL)

Ch. 8.6 - Prob. 8.6ACQCh. 8.6 - If NPV is conceptually the best tool for capital...Ch. 8 - Prob. 8.1CCh. 8 - Prob. 8.2CCh. 8 - Prob. 8.3CCh. 8 - Prob. 8.4CCh. 8 - Prob. 1CTCRCh. 8 - Prob. 2CTCRCh. 8 - Prob. 3CTCRCh. 8 - Prob. 4CTCRCh. 8 - Net Present Value. Concerning NPV: a.Describe how...Ch. 8 - LO3 8.6.Internal Rate of Return. Concerning IRR:...Ch. 8 - Prob. 7CTCRCh. 8 - Prob. 8CTCRCh. 8 - Prob. 9CTCRCh. 8 - Prob. 10CTCRCh. 8 - Prob. 11CTCRCh. 8 - Prob. 12CTCRCh. 8 - Internal Rate of Return. In a previous chapter, we...Ch. 8 - Net Present Value. It is sometimes stated that the...Ch. 8 - Prob. 15CTCRCh. 8 - LO1 l.Calculating Payback. What is the payback...Ch. 8 - Calculating Payback. An investment project...Ch. 8 - Prob. 3QPCh. 8 - Calculating AAR. Youre trying to determine whether...Ch. 8 - Calculating IRR. A firm evaluates all of its...Ch. 8 - LO4 6. Calculating NPV. For the cash flows in the...Ch. 8 - Calculating NPV and IRR. A project that LO3, LO4...Ch. 8 - Prob. 8QPCh. 8 - Prob. 9QPCh. 8 - LO3 LO4 10.NPV versus IRR. Zayas, LLC, has...Ch. 8 - Prob. 11QPCh. 8 - Prob. 12QPCh. 8 - Prob. 13QPCh. 8 - LO4 LO6 14.Problems with Profitability Index. The...Ch. 8 - LO1, LO3, LO4, LO6 15.Comparing Investment...Ch. 8 - LO3 LO4 16.NPV and IRR. Reece Company is presented...Ch. 8 - LO4 LO6 17.NPV and Profitability Index. Robben...Ch. 8 - Crossover Point. Hodgkiss Enterprises has gathered...Ch. 8 - Payback Period and IRR. Suppose you have a project...Ch. 8 - NPV and Discount Rates. An investment has an...Ch. 8 - NPV and Payback Period. Kaleb Konstruction, Inc.,...Ch. 8 - Prob. 22QPCh. 8 - MIRR. Suppose the company in the previous problem...Ch. 8 - Crossover and NPV. Seether, Inc., has the...Ch. 8 - LO3 LO4 25.Calculating IRR. A project has the...Ch. 8 - Prob. 26QPCh. 8 - LO1, LO4, LO6 27.Cash Flow Intuition. A project...Ch. 8 - Prob. 28QPCh. 8 - Prob. 29QPCh. 8 - LO3 LO4 30.NPV and IRR. Anderson International...Ch. 8 - Bullock Gold Mining Seth Bullock, the owner of...Ch. 8 - Bullock Gold Mining Seth Bullock, the owner of...Ch. 8 - Prob. 3CC
Knowledge Booster
Background pattern image
Finance
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Essentials Of Investments
Finance
ISBN:9781260013924
Author:Bodie, Zvi, Kane, Alex, MARCUS, Alan J.
Publisher:Mcgraw-hill Education,
Text book image
FUNDAMENTALS OF CORPORATE FINANCE
Finance
ISBN:9781260013962
Author:BREALEY
Publisher:RENT MCG
Text book image
Financial Management: Theory & Practice
Finance
ISBN:9781337909730
Author:Brigham
Publisher:Cengage
Text book image
Foundations Of Finance
Finance
ISBN:9780134897264
Author:KEOWN, Arthur J., Martin, John D., PETTY, J. William
Publisher:Pearson,
Text book image
Fundamentals of Financial Management (MindTap Cou...
Finance
ISBN:9781337395250
Author:Eugene F. Brigham, Joel F. Houston
Publisher:Cengage Learning
Text book image
Corporate Finance (The Mcgraw-hill/Irwin Series i...
Finance
ISBN:9780077861759
Author:Stephen A. Ross Franco Modigliani Professor of Financial Economics Professor, Randolph W Westerfield Robert R. Dockson Deans Chair in Bus. Admin., Jeffrey Jaffe, Bradford D Jordan Professor
Publisher:McGraw-Hill Education
Financial Risks - Part 1; Author: KnowledgEquity - Support for CPA;https://www.youtube.com/watch?v=mFjSYlBS-VE;License: Standard youtube license