Intermediate Accounting, Student Value Edition Plus MyLab Accounting with Pearson eText -- Access Card Package (2nd Edition)
2nd Edition
ISBN: 9780134833118
Author: Elizabeth A. Gordon, Jana S. Raedy, Alexander J. Sannella
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 8.6P
a.
To determine
The percent completed.
Given information:
Contract price is $800,000.
Actual construction cost for 2018 is $200,000.
Actual construction cost for 2019 is $300,000.
Actual construction cost for 2020 is $150,000.
Estimated total cost for 2018 is $600,000.
Estimated total cost for 2019 is $800,000.
Estimated total cost for 2020 is $650,000.
b.
To determine
The revenue and gross profit for all the years.
c.
To determine
To prepare: The
d.
To determine
To prepare: A t-account for construction in progress, billings on construction in progress and accounts receivable.
e.
To determine
The net assets or liability for each year of the contract.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Cosmo Computer Consultants (CCC) signed a contract in 2022 to develop a computer network system for Platinum Entertainment. Cosmo uses the percentage-of-
completion method and determines its measure of progress using the cost-to-cost approach. The firm provided the following information for 2022.
Contract Price
Actual construction costs incurred during the year
Estimated total costs
Progress billings made during the year
Cash collections during the year
$85,000
2022
$12,000
60,000
30,500
25,000
This problem has subparts that still need to be answered
Assume Avaya contracted to provide a customer with Internet infrastructure for $2,350,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below:
2024
2025
Costs incurred during the year
$ 328,000
$ 1,830,000
Estimated costs to complete as of 12/31
1,312,000
0
Billings during the year
436,000
1,690,000
Cash collections during the year
341,000
1,785,000
Required:
Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion.
Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time.
Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time…
Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,000,000. The project began in 2018 and was completed in 2019. Data relating to the contract are summarized below:2018 2019Costs incurred during the year $ 300,000 $ 1,575,000Estimated costs to complete as of 12/31 1,200,000 –0–Billings during the year 380,000 1,620,000Cash collections during the year 250,000 1,750,000Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2018 and 2019 assuming Nortelrecognizes revenue over time according to percentage of completion
Chapter 8 Solutions
Intermediate Accounting, Student Value Edition Plus MyLab Accounting with Pearson eText -- Access Card Package (2nd Edition)
Ch. 8 - What are the primary issues involved in revenue...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - Prob. 8.4QCh. 8 - Prob. 8.5QCh. 8 - How is a performance obligation defined?Ch. 8 - What are the two criteria to define a good or...Ch. 8 - Prob. 8.8QCh. 8 - What principles regarding timing and measurement...Ch. 8 - Prob. 8.10Q
Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Percentage-of-Completion Method, Journal Entries....Ch. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Percentage-of-Completion Method. Gary Construction...Ch. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Sales with the Right of Return. Webster Hall, Inc....Ch. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Percentage-of-Completion Method. R Wayne Computer...Ch. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Sales on Consignment. Pablo Products. Ltd sells...Ch. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 1SSCCh. 8 - Basis for Conclusions Case 1: Control According to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Assume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: 2024 2025 Costs incurred during the year $ 316,000 $ 1,700,000 Estimated costs to complete as of 12/31 1,264,000 0 Billings during the year 400,000 1,660,000 Cash collections during the year 290,000 1,770,000 Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming this project does not qualify for revenue recognition over time.arrow_forwardAssume Avaya contracted to provide a customer with Internet infrastructure for $2,910,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: 2024 2025 Costs incurred during the year $ 376,000 $ 2,265,000 Estimated costs to complete as of 12/31 1,504,000 0 Billings during the year 535,000 1,810,000 Cash collections during the year 500,000 1,845,000 Question: Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming this project does not qualify for revenue recognition over time.arrow_forwardAssume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,700,000. The project began in 2021 and was completed in 2022. Data relating to the contract are summarized below: 2021 2022 Costs incurred during the year $ 356,000 $ 2,135,000 Estimated costs to complete as of 12/31 1,424,000 0 Billings during the year 475,000 1,760,000 Cash collections during the year 415,000 1,820,000 Required:1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time according to percentage of completion.2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming this project does not qualify for revenue recognition over time.3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2021 assuming Nortel recognizes revenue over time according to…arrow_forward
- Assume Nortel Networks contracted to provide a customer with Internet infrastructure for $2,860,000. The project began in 2021 and was completed in 2022 Data relating to the contract are summarized below: 2021 $ 372,000 $1,899,00e 1,488,eee 524,000 318,eee 2022 Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year 2,336,800 2,542, 000 Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 assuming Nortel recognizes revenue over time occording to percentege of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2021 and 2022 ssuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented ot the end of 2021 assuming Nortel recognizes revenue over time according to percentege of completion. 4. Prepare a partial…arrow_forwardn January 1, 2021, ABC enters into a contract to construct a building for a customer. ABC identifies its performance obligation to satisfied over time. ABC uses the input method based on costs to measure its progress on the contract. The contract price is P9M Information on the construction is provided below: 2021 2022 2023 a. Contract cost incurred per year 2,760,000 3,540,000 500,000 b. Billing per year 50% 25% 25% c. Collections on billings per year d. Estimated costs to complete (at each yr. end) 4,140,000700,000 90% 90% balance Note: Billings per year are stated as percentages of the contract price. The contract is non-cancellable. The collection on billings in 2021 and 2022 are net of 10% retention. "Retention" is an amount withheld by the contracted and payable to the contractor at the end of the contract when the project is completed and accepted. Requirements; a. Compute for the gross profits, 2021 2022 2023arrow_forwardContract price of $2,400,000. Estimated. Information relating to the costs and billings for this contract is as follows: 2019 2020 2021 Costs incurred during the year 700,000 1,100,000 750,000 Estimated costs to complete 1,300,000 800,000 Instructions 1- Using the percentage-of-completion method, compute the gross profit or loss to be recognized each year. 2- Using the cost recovery method, compute the gross profit or loss to be recognized each yeararrow_forward
- On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which The is estimated cost P31,200,000. company recognizes construction to Data on this project for 2022-2024 follow: Est'd Costs revenue over time. Contract Costs Billings 10,500,000 12,500,000 14,440,000 incurred to Complete 20,540,000 13,156,000 2022 5,460,000 9,984,000 2023 2024 15,756,000 The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. contract was delayed for 8 weeks In 2024, the What is the gross profit for 2024? 1,164,000 1,466,400 1,724,000 1,824,000 А. с. в. D.arrow_forward1.On March 1, 2022, AGGREGATES Company enters a contract to build a hotel which is estimated to cost P31,200,000. The company recognizes construction revenue over time. Data on this project for 2022-2024 follow:Contract BillingsCosts incurredEst’d Costs to Complete2022 10,500,000 5,460,000 20,540,0002023 12,500,000 9,984,000 13,156,0002024 14,440,000 15,756,000 -The contract contains a penalty clause that penalizes the company a reduction of P70,000 from the contract price for every week of delay. In 2024, the contract was delayed for 8 weeksWhat is the gross profit for 2024?A. 1,164,000 C. 1,724,000B. 1,466,400 D. 1,824,000 2.MOC Construction Company started work on three job sites during the current year. Any costs incurred are expected to be recoverable. Data relating to the three jobs are given below:Site Contract PriceCost IncurredEstimated Costs to CompleteBillings on ContractCollections on Billings1 5,000,000 3,750,000 - 5,000,000 5,000,0002 7,000,000 1,000,000 4,000,000 900,000…arrow_forwardArab Construction Company began work in 2021 on contract XXXX, which provided for a contract price of €19,200,000. Other details follow: 2021 Costs incurred during the year Estimated costs to complete, as of December 31 Billings during the year Collections during the year OA €1,200,000. B. €1,600,000. C. €4,800,000. €3,200,000 9,600,000 3,600,000 2,400,000 Assume that Arab uses the percentage-of-completion method of accounting. The portion of the total gross profit to be recognized as income in 2021 is D. €6,400,000 €9,800,000 0 14,400,000 15,600,000 202 GUR OMarrow_forward
- SMC entered into a long-term construction contract for 3 years. Contract price agreed was P4,150,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract: December 31, 2021 December 31, 2022 Percentage of completion 30% 82.5% Estimated cost to complete 1,960,000 840,000 1. What is the total cost incurred in year 2022? С. 1,680,000 D. 3,120,000 A. 4,073,750 В. 840,000 2. The realized gross profit (loss) in year 2022 is A. 650,000 B. 405,000 C. (. 245,000) D. (1,055,000) 3. What is the construction cost of sales for year 2022? С. 3,233,750 D. 4,478,750 A. 3,960,000 В. 3,120,000 4. What is the construction-in-progress as of 2022? А. 3,423,750 C. 2,065,000 В. 3,310,000 D. 2,470,000arrow_forwardFender Construction Company receives a contract to construct a building over a period of 3 years for a price of $700,000. The contract represents a single performance obligation that will be satisfied over time. Information relating to the performance of the contract is summarized as follows: 2019 2020 2021 Construction costs incurred during the year $150,000 $242,000 $168,000 Estimated costs to complete 350,000 168,000 — Billings during the year 120,000 250,000 330,000 Collections during the year 100,000 260,000 340,000 Required: 1. Prepare journal entries for all 3 years. 2. Assume that the contract represents a single performance obligation that will be satisfied at a point in time. Prepare journal entries for all 3 years. 1. Assume the contract represents a single performance obligation that will be satisfied over time. Prepare journal entries on December 31 for all 3 years -to record costs of construction for cash -to record partial…arrow_forwardFender Construction Company receives a contract to construct a building over a period of 3 years for a price of $700,000. The contract represents a single performance obligation that will be satisfied over time. Information relating to the performance of the contract is summarized as follows: 2019 2020 2021 Construction costs incurred during the year $150,000 $242,000 $168,000 Estimated costs to complete 350,000 168,000 — Billings during the year 120,000 250,000 330,000 Collections during the year 100,000 260,000 340,000 Required: 1. Prepare journal entries for all 3 years. 2. Assume that the contract represents a single performance obligation that will be satisfied at a point in time. Prepare journal entries for all 3 years. Please dont provide image based answers thank youarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you