![Intermediate Accounting, Student Value Edition Plus MyLab Accounting with Pearson eText -- Access Card Package (2nd Edition)](https://www.bartleby.com/isbn_cover_images/9780134833118/9780134833118_largeCoverImage.gif)
Intermediate Accounting, Student Value Edition Plus MyLab Accounting with Pearson eText -- Access Card Package (2nd Edition)
2nd Edition
ISBN: 9780134833118
Author: Elizabeth A. Gordon, Jana S. Raedy, Alexander J. Sannella
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 8, Problem 8.11P
a.
To determine
To prepare:
b.
To determine
To prepare: T-accounts for construction in progress, billing on construction in progress and accounts receivables.
c.
To determine
Net assets or liability for each year.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
n January 1, 2021, ABC enters into a contract to construct a building for a customer. ABC identifies its performance obligation to satisfied over time.
ABC uses the input method based on costs to measure its progress on the contract. The contract price is P9M
Information on the construction is provided below:
2021
2022
2023
a. Contract cost incurred per year
2,760,000 3,540,000 500,000
b. Billing per year
50%
25%
25%
c. Collections on billings per year
d. Estimated costs to complete (at each yr. end) 4,140,000700,000
90%
90%
balance
Note:
Billings per year are stated as percentages of the contract price. The contract is non-cancellable.
The collection on billings in 2021 and 2022 are net of 10% retention. "Retention" is an amount withheld by the contracted and payable to the
contractor at the end of the contract when the project is completed and accepted.
Requirements;
a. Compute for the gross profits,
2021
2022
2023
Pharoah Construction entered into a contract to construct a bridge for a contract price of $2.95 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract:
2019
2020
2021
Costs incurred during the year
$649,000
$836,000
$693,900
Estimated costs to complete
1,427,800
515,000
0
Calculate the revenue, expenses and gross profit to be recognized each year using the percentage-of-completion method. (Round the percentage completion to 2 decimal places, e.g. 52.75% and other answers to 0 decimal places, e.g. 1,525.)
2019
2020
2021
Revenue
$
$
$
Expenses
Gross Profit
$
$
$
Contract price of $2,400,000. Estimated. Information relating to the costs
and billings for this contract is as follows:
2019
2020
2021
Costs incurred during the year
700,000
1,100,000
750,000
Estimated costs to complete
1,300,000
800,000
Instructions
1- Using the percentage-of-completion method, compute the gross
profit or loss to be recognized each year.
2- Using the cost recovery method, compute the gross profit or loss to
be recognized each year
Chapter 8 Solutions
Intermediate Accounting, Student Value Edition Plus MyLab Accounting with Pearson eText -- Access Card Package (2nd Edition)
Ch. 8 - What are the primary issues involved in revenue...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - What is the fundamental principle underlying the...Ch. 8 - Prob. 8.4QCh. 8 - Prob. 8.5QCh. 8 - How is a performance obligation defined?Ch. 8 - What are the two criteria to define a good or...Ch. 8 - Prob. 8.8QCh. 8 - What principles regarding timing and measurement...Ch. 8 - Prob. 8.10Q
Ch. 8 - What is variable consideration and what factors...Ch. 8 - Describe and contrast the two approaches used to...Ch. 8 - Prob. 8.13QCh. 8 - What factors should accountants consider to...Ch. 8 - Prob. 8.15QCh. 8 - How does a seller account for any consideration...Ch. 8 - Prob. 8.17QCh. 8 - What are the two exceptions to the general rule...Ch. 8 - What are the three criteria required to recognize...Ch. 8 - When an entity does not meet the three criteria...Ch. 8 - Prob. 8.21QCh. 8 - Prob. 8.22QCh. 8 - How does a firm estimate the degree completed...Ch. 8 - Can a firm record inventory out on consignment as...Ch. 8 - What method do agents in a transaction use to...Ch. 8 - Prob. 8.26QCh. 8 - What qualitative disclosures do the standards...Ch. 8 - All of the following are elements of a contract...Ch. 8 - Prob. 8.2MCCh. 8 - Telecom Co. enters into a two-year contract with a...Ch. 8 - The transaction price must reflect the time value...Ch. 8 - Prob. 8.5MCCh. 8 - When allocating the transaction price to separate...Ch. 8 - Which of the following indicators is not...Ch. 8 - During Yoar 1 Moriwothor Construction Company...Ch. 8 - All of the following are indicators that the...Ch. 8 - Prob. 8.10MCCh. 8 - Prob. 8.11MCCh. 8 - Identify a Contract with a Customer. Complete the...Ch. 8 - Prob. 8.2BECh. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Identifying Performance Obligations. Perfect Party...Ch. 8 - Estimating Variable Consideration. Gear Garage...Ch. 8 - Estimating Variable Consideration. Using the...Ch. 8 - Estimating Variable Consideration. Sellet...Ch. 8 - Estimating Variable Consideration. Seliet...Ch. 8 - Prob. 8.9BECh. 8 - Allocation of Transaction Price. Martin Software...Ch. 8 - Prob. 8.11BECh. 8 - Allocation of Transaction Price. Sycamore Sidewalk...Ch. 8 - Allocation of Transaction Price. Sycamore enters...Ch. 8 - Prob. 8.14BECh. 8 - Allocation of Transaction Price. Using the...Ch. 8 - When to Recognize Revenue. For each scenario...Ch. 8 - Prob. 8.17BECh. 8 - Prob. 8.18BECh. 8 - Percentage-of-Completion Method, Journal Entries....Ch. 8 - Prob. 8.20BECh. 8 - Sales with the Right of Return. Both incorporated...Ch. 8 - Sales with the Right of Return. Using the...Ch. 8 - Sales Returns. Historically, about 5% or the...Ch. 8 - Sales on Consignment. Hanna Lighting recertify...Ch. 8 - Determining Performance Obligations. Pagit Inc, a...Ch. 8 - Prob. 8.2ECh. 8 - Estimating Variable Consideration. King Rat Pest...Ch. 8 - Prob. 8.4ECh. 8 - Prob. 8.5ECh. 8 - Prob. 8.6ECh. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Allocation of Variable Consideration. Green-Up Inc...Ch. 8 - Prob. 8.9ECh. 8 - Prob. 8.10ECh. 8 - Determination of When to Recognize Revenue. Far...Ch. 8 - Prob. 8.12ECh. 8 - Percentage-of-Completion Method. Gary Construction...Ch. 8 - Prob. 8.14ECh. 8 - Prob. 8.15ECh. 8 - Prob. 8.16ECh. 8 - Sales with the Right of Return. Webster Hall, Inc....Ch. 8 - Prob. 8.18ECh. 8 - Prob. 8.19ECh. 8 - Other Principal Agent Transactions, Net Revenue...Ch. 8 - Prob. 8.1PCh. 8 - Prob. 8.2PCh. 8 - Comprehensive Revenue Recognition Problem. Casale...Ch. 8 - Prob. 8.4PCh. 8 - Determining When to Recognize Revenue. Megrew...Ch. 8 - Prob. 8.6PCh. 8 - Prob. 8.7PCh. 8 - Prob. 8.8PCh. 8 - Percentage-of-Completion Method. R Wayne Computer...Ch. 8 - Prob. 8.10PCh. 8 - Prob. 8.11PCh. 8 - Sales on Consignment. Pablo Products. Ltd sells...Ch. 8 - Prob. 1JCCh. 8 - Prob. 1FSCCh. 8 - Prob. 1SSCCh. 8 - Basis for Conclusions Case 1: Control According to...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- On January 1, 2021. Robredo Co. started the construction of a building with a fixed contract price of P10,000,000. The outcome of the construction project can be estimated reliably and the contractor decided to employ cost to cost method. The following data are provided by the accountant and project manager concerning the construction costs for the three years of construction: Year 12/31/2021 12/31/2022 12/31/2023 P 3740000 Costs incurred during the year Realized gross profit/(loss) during the year Percentage of completion as of the end of the year ? ? P750,000 (P250,000) (P800,000) 50% 37.5% ? What is the balance of Construction in Progress on December 31, 2023?arrow_forwardFender Construction Company receives a contract to construct a building over a period of 3 years for a price of $700,000. The contract represents a single performance obligation that will be satisfied over time. Information relating to the performance of the contract is summarized as follows: 2019 2020 2021 Construction costs incurred during the year $150,000 $242,000 $168,000 Estimated costs to complete 350,000 168,000 — Billings during the year 120,000 250,000 330,000 Collections during the year 100,000 260,000 340,000 Required: 1. Prepare journal entries for all 3 years. 2. Assume that the contract represents a single performance obligation that will be satisfied at a point in time. Prepare journal entries for all 3 years. 1. Assume the contract represents a single performance obligation that will be satisfied over time. Prepare journal entries on December 31 for all 3 years -to record costs of construction for cash -to record partial…arrow_forwardSMDC Construction signed a contract to build a building over a period 3 years for a price of P10,000,000. Information relating to the performance of the contract is summarized as follows: 2017 2018 2019 contribution costs incurred during the year 2,500,000 2,400,000 1,800,000 estimated costs to complete 4,500,000 1,800,000 - buildings during the year 2,200,000 2,800,000 5,000,000 collections during the year 2,000,000 2,500,000 5,500,000 Prepare the entries under the percentage of completion.arrow_forward
- SMC entered into a long-term construction contract for 3 years. Contract price agreed was P4,150,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract: December 31, 2021 December 31, 2022 Percentage of completion 30% 82.5% Estimated cost to complete 1,960,000 840,000 1. What is the total cost incurred in year 2022? С. 1,680,000 D. 3,120,000 A. 4,073,750 В. 840,000 2. The realized gross profit (loss) in year 2022 is A. 650,000 B. 405,000 C. (. 245,000) D. (1,055,000) 3. What is the construction cost of sales for year 2022? С. 3,233,750 D. 4,478,750 A. 3,960,000 В. 3,120,000 4. What is the construction-in-progress as of 2022? А. 3,423,750 C. 2,065,000 В. 3,310,000 D. 2,470,000arrow_forwardAt the beginning of 2021, Batangas Road Construction entered into a contract to build a road for the government. Construction will take four years. The following information as of December 31, 2021 is available for the contract: Total revenue according to contract 10,000,000 Total expected cost 8,000,000 Cost incurred during 2021 1,200,000 Assume that the company estimated percentage complete based on costs incurred as a percentage of total estimated costs. Under the completed contract method, how much revenue will be reported in 2021? None 300,000 1,500,000arrow_forwardHow much is the contract revenue to date in the year 2019? Double Dragon receives a contract to build a building over a period of 3 years for a price of P14,000,000. Information relating to the performance of the contract is summarized as follows: 2019 Construction Costs incurred- yearly 3,000,000 4,840,000 3,360,000 2017 2018 Estimated Costs to Complete 7,000,000 3,360,000 Billings during the year 2,400,000 5,200,000 6,400,000 Collections during the year 2,000,000 5,400,000 6,600,000arrow_forward
- Chicago Heights company has 2 year contract to construct a warehouse. The contract value is 2949 and the estimated total cost is 1156. During the next 2 years, the costs are incurred as follows and the project is completed by the end of second year. Contract data Year for the year 2019 for the year 2020 Cost incurred 867$ 851$ Required Make the recognition of revenue, expenses and profits for 2020. Type in the profit value without using the currency sign and separators.arrow_forward4SMC entered into a long-term construction contract for 3 years. Contract price agreed was P4,150,000. The outcome of the contract was estimated reliably. The following data were ascertained for the contract:December 31, 2021December 31, 2022Percentage of completion30%82.5%Estimated cost to complete1,960,000840,0001.What is the total cost incurred in year 2022? 1.What is the total cost incurred in year 2022? A.4,073,750 C. 1,680,000. B.840,000. D. 3,120,000 2.The realized gross profit (loss) in year 2022 is A.650,000. C. (. 245,000) B.405,000 D. (1,055,000) 3.What is the construction cost of sales for year 2022? A.3,960,000. C. 3,233,750 B.3,120,000. D. 4,478,750 4.What is the construction-in-progress as of 2022? A.3,423,750. C. 2,065,000 B.3,310,000. D. 2,470,000arrow_forwardFender Construction Company receives a contract to construct a building over a period of 3 years for a price of $700,000. The contract represents a single performance obligation that will be satisfied over time. Information relating to the performance of the contract is summarized as follows: 2019 2020 2021 Construction costs incurred during the year $150,000 $242,000 $168,000 Estimated costs to complete 350,000 168,000 — Billings during the year 120,000 250,000 330,000 Collections during the year 100,000 260,000 340,000 Required: 1. Prepare journal entries for all 3 years. 2. Assume that the contract represents a single performance obligation that will be satisfied at a point in time. Prepare journal entries for all 3 years. Please dont provide image based answers thank youarrow_forward
- On January 1, 2021, Ka Leody Inc. entered into a long-term construction contract with fixed contract price of P 5,000,000. Ka Leody billed its client as follows: 30% during 2021, 40% during 2022 and the remainder at the end of project completion. The following data were provided by the cost accountant of the Ka Leody Inc: 2020 2021 2022 Cumulative cost incurred as of the end of the year P 2,200,000 P 3,600,000 P 4,800,000 Estimated remaining cost to complete at the end of the year P 3,300,000 P 900,000 What is the revenue to be recognized on December 31, 2021 under percentage of completion method ?arrow_forwardArab Construction Company began work in 2021 on contract XXXX, which provided for a contract price of €19,200,000. Other details follow: 2021 Costs incurred during the year Estimated costs to complete, as of December 31 Billings during the year Collections during the year OA €1,200,000. B. €1,600,000. C. €4,800,000. €3,200,000 9,600,000 3,600,000 2,400,000 Assume that Arab uses the percentage-of-completion method of accounting. The portion of the total gross profit to be recognized as income in 2021 is D. €6,400,000 €9,800,000 0 14,400,000 15,600,000 202 GUR OMarrow_forwardABC Co. entered into a long term construction contract for 3 years. Contract price agreed was P7,500,000. The following data were ascertained for the contract: Cost incurred for the year Estimated cost at completion 4,700,000 O6,250,000 5,275,000 2020 5,300,000 P1,900,000 The outcome of the contract can be estimated reliably. What is the construction cost for the year 2021? 5,700,000 2021 P5,300,000 800,000 2022 P49,500 ?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337788281/9781337788281_smallCoverImage.jpg)
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning