ENGR.ECONOMIC ANALYSIS
ENGR.ECONOMIC ANALYSIS
14th Edition
ISBN: 9780190931919
Author: NEWNAN
Publisher: Oxford University Press
Question
Book Icon
Chapter 9, Problem 55P
To determine

(a)

The alternative that should be selected.

Expert Solution
Check Mark

Answer to Problem 55P

The alternative F should be selected.

Explanation of Solution

Calculations:

The table for cash flow and cumulative cash flow for project E is shown below.

Year Cash flow Cumulative cash flow
0 $90 $90
1 $20 $70
2 $20 $50
3 $20 $30
4 $20 $10
5 $20 $10
6 $20 $30

Table (1)

Here, the cumulative cash flow becomes positive in 5th year. At the end of 4th year the cash inflow is only $10 less than the cash outflow. Thus $10 is required to equal the benefits and costs. In the 5th year total cash inflow is $20.

Calculate the payback period for project E.

Payback period=(4+ $10 $20)=(4+0.5)=4.5 years

The table for cash flow and cumulative cash flow for project F is shown below.

Year Cash flow Cumulative cash flow
0 $110 $110
1 $35 $75
2 $35 $40
3 $35 $5
4 $35 $30
5 $0 $30
6 $0 $30

Table (2)

Here, the cumulative cash flow becomes positive in 4th year. At the end of 3rd year the cash inflow is only $5 less than the cash outflow. Thus $5 is required to equal the benefits and costs. In 4th year total cash inflow is $35.

Calculate the payback period for project F.

Payback period=(3+ $5 $35)=(3+0.14)=3.14 years

The table for cash flow and cumulative cash flow for project G is shown below.

Year Cash flow Cumulative cash flow
0 $100 $100
1 $0 $100
2 $10 $90
3 $20 $70
4 $30 $40
5 $40 $0
6 $50 $50

Table (3)

Here, the cumulative cash flow becomes NIL in 5th year. The profit equals cost in 5th year. The payback period will be 5th year.

The table for cash flow and cumulative cash flow for project H is shown below.

Year Cash flow Cumulative cash flow
0 $120 $120
1 $0 $120
2 $0 $120
3 $0 $120
4 $0 $120
5 $0 $120
6 $180 $60

Table (4)

Here, the cumulative cash flow becomes positive in 6th year. At the end of 5th year the cash inflow is only $120 less than the cash outflow. Thus $120 is required to equal the benefits and costs. In 6th year total cash inflow is $180.

Calculate the payback period for project H.

Payback period=(5+ $120 $180)=(5+0.6)=5.6 years

The payback period for project F is minimum which is equal to 3.1 years.

Thus, the alternative F should be selected.

Conclusion:

The alternative F should be selected.

To determine

(b)

The alternative that should be selected.

Expert Solution
Check Mark

Answer to Problem 55P

The alternative G should be selected.

Explanation of Solution

Given:

The interest rate is 5%.

Concept used:

Write the expression for future worth factor.

factor=(1+i)n ...... (I)

Here, the time period is n and the interest rate is i.

Calculations:

The table for future worth analysis of alternatives is shown below.

Year Future worth factor (1.05)n 1 Project (E) Project (F) Project (G) Project (H)
Cash flow2 Future worth3 (1×2) Cash flow4 Future worth5 (1×4) Cash flow6 Future worth7 (1×6) Cash flow8 Future worth9 (1×8)
0 1.3401 $90 $120.61 $110 $147.411 $100 $134 $120 $160.8
1 1.2762 $20 $25.52 $35 $46.67 $0 $0 $0 $0
2 1.2155 $20 $24.31 $35 $42.5425 $10 $12.155 $0 $0
3 1.57625 $20 $31.525 $35 $55.17 $20 $31.52 $0 $0
4 1.1025 $20 $22.05 $35 $38.587 $30 $30.75 $0 $0
5 1.05 $20 $21 $0 $0 $40 $42 $0 $0
6 1.00 $20 $20 $0 $0 $50 $50 $180 $180
Total $23.8 $6.45 $32.425 $19.2

Table (5)

The alternative G has the maximum future worth.

Thus, thee alternative G should be selected.

Conclusion:

The alternative G should be selected.

To determine

(c)

The alternative that should be selected.

Expert Solution
Check Mark

Answer to Problem 55P

The alternative G should be selected.

Explanation of Solution

Given:

The interest rate is 20%.

Calculations:

The table for future worth analysis of alternatives is shown below.

Year Future worth factor (1.05)n 1 Project (E) Project (F) Project (G) Project (H)
Cash flow 2 Future worth 3 (1×2) Cash flow 4 Future worth 5 (1×4) Cash flow 6 Future worth 7 (1×6) Cash flow 8 Future worth 9 (1×8)
0 2.986 $90 $268.74 $110 $328.46 $100 $298.6 $120 $358.32
1 2.488 $20 $49.76 $35 $87.08 $0 $0 $0 $0
2 2.073 $20 $41.47 $35 $72.57 $10 $20.73 $0 $0
3 1.728 $20 $34.56 $35 $60.48 $20 $34.56 $0 $0
4 1.44 $20 $28.8 $35 $50.04 $30 $43.2 $0 $0
5 1.2 $20 $25.2 $0 $0 $40 $48 $0 $0
6 1.00 $20 $20 $0 $0 $50 $50 $180 $180
Total $68.95 $58.29 $102.1 $178.32

Table (6)

The alternative G has the maximum future worth.

Thus, the alternative G should be selected.

Conclusion:

The alternative G should be selected.

To determine

(d)

The benefit cost ratio for alternate G.

Expert Solution
Check Mark

Answer to Problem 55P

The benefit cost ratio for alternate G is 0.96.

Explanation of Solution

Given:

The interest rate is 10%.

Concept used:

Write the expression for present worth of benefits.

PWB=G[( 1+i)nin1i2( 1+i)n] ...... (I)

Here rate of interest is i, time period is n and uniform gradient is G.

Write the expression for benefit cost ratio.

BC ratio=PWBPWC ...... (II)

Here, the present worth of costs is PWC.

Calculations:

Calculate the present worth of benefits.

Substitute $10 for G, 10% for i and 6 for n in Equation (I).

PWB=$10[ ( 1+0.1) 60.1×61 0.1 2 ( 1+0.1) 6]=$10[1.771.60.01×1.77]=$10(9.6)=$96

Calculate the benefit cost ratio.

Substitute $96 for PWB, and $100 for PWC in Equation (I).

BC ratio=$96$100=0.96

Thus, the benefit cost ratio for alternate G is 0.96.

Conclusion:

The benefit cost ratio for alternate G is 0.96.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!

Chapter 9 Solutions

ENGR.ECONOMIC ANALYSIS

Knowledge Booster
Background pattern image
Recommended textbooks for you
Text book image
ENGR.ECONOMIC ANALYSIS
Economics
ISBN:9780190931919
Author:NEWNAN
Publisher:Oxford University Press
Text book image
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Text book image
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Text book image
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Text book image
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Text book image
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education