Question
Chapter 9, Problem 9.9P
To determine
Find the maximum permissible depth (H) of the cut before the occurrence of heaving.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Q14. A contractor is excavating the below trench. The contractor is supposed to dig the
trench 5ft deep and 3ft wide. The soil was tested to have an approximately swell factor of
112% and a shrinkage factor of 14%. The contractor is placing a 10" water pipe in the trench
and then backfilling with the soil that was removed. The dimensions are on center line.
Does the contractor have enough soil to backfill the trench, or will he /she have to need
more? If more soil are needed, how much does the contractor need to bring in. Answer in
LCY.
40ft
3ft
16ft
40ft
20ft
24ft
60ft
Q24/B- find the length of stilling basin USBR III ? If the
height of the chute block and the the end Sill are 25 cm and
37.5 cm respectively. Then draw the hydraulic structure with
all dimensions ?
Answer the number shown below for the least horizontal deformation and settlement and for the
most settlement. The braced excavation type of (3) below is chosen for the construction of
subway station and ground settlement is expected to be more than allowable due to the
drawdown of ground water. What do you think you should consider to reduce the settlement?
1) Slurry wall
2) CIP continuous wall
3) Soldier pile and woodlagging wall
4) Soldier pile and concrete wall
Chapter 9 Solutions
EBK PRINCIPLES OF GEOTECHNICAL ENGINEER
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- Define sand-cone method.arrow_forwardA stone A is thrown vertically upward at 10 m/sec. Another stone B is thrown vertically upward at 12 m/sec. after 1 second at an initial point of B is 2 m. higher the initial point of A. At what height that two stones have the same elevation?arrow_forward(BASE ON 100 M LONG) In m3 1. Calculate the Excavate 2. Trench and back fill 3. Disposal of surplus This drawing is not to scale 260 x 500 Grade Beam Cutback slope (HV) 1:1 260 x 150 Void Form. 3 Rows 10M Rebar 000 000 www 900 190 3 Rows 15M Rebar Existing Grade 50 mm Rigid Insulation (200 deep) 300 dia. Concrete Piles (see plan)arrow_forward
- Describe about the Sand-Cone Method in detail.arrow_forwardWater is flowing in a 2m deep rectangular aqueduct, with a measured speed of 2m/s at the surface. Assuming the side walls of the channel are far enough away to have negligible impact, what is the shear stress 1m deep in the middle of the channel?arrow_forwardO DrahmedsoilMechanicsnoteschapter5.pdf s/DrahmedsoilMechanicsnoteschapter5.pdf A V - 14 A 10-m-thick layer of stiff saturated clay is underlain by a layer of sand. The sand is under artesian pressure. A 5.75-m-deep cut is made in the clay. What would be the maximum permissible depth of cut before heaving would occur. Determine the factor of safety against heaving at point A. Ans.: H =6.88m, FOS = 1.36 P = 1925 kg/m 5.75 m 10 m Saturated clay 6 m Sand Par - 1840 kg/m 2.5 m Soil Mechanics Assistant Prof. Dr. Ahmed Al-Obaidi Civil Eng Dept - College of Eng. (173) 5.15 Refer to Problem 5.14. Water may be introduced into the cut to improvearrow_forward
- What are Mode of deflection and lateral pressure distribution for sheeting supporting a vertical cut?arrow_forwardDefine the Vertical Stress Due to Embankment Loading ?arrow_forwardA water tank is 10 m in diameter and 15 m high. If the tank is to becompletely filled, determine the minimum thickness of the tank plating if thestress is limited to 40 MPa.arrow_forward
- Explain Mode of deflection and lateral pressure distribution for sheeting supporting a vertical cut.arrow_forwardDefine Terzaghi-Peck Charts for Backfill Pressures.arrow_forwardPROBLEM 4 A standpipe with an open top has a diameter of 2.5m and a wall thickness of 22mm. What level of water from the bottom will result to a hoop stress of 15MPA of the standpipe?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Geotechnical Engineering (MindTap C...Civil EngineeringISBN:9781305970939Author:Braja M. Das, Khaled SobhanPublisher:Cengage Learning
Principles of Geotechnical Engineering (MindTap C...
Civil Engineering
ISBN:9781305970939
Author:Braja M. Das, Khaled Sobhan
Publisher:Cengage Learning