ToysPlus, Inc.: MRP eXcel
Dale Long, vice president of manufacturing for ToysPlus, Inc., finished reading the weekly production report for the week ended September 16, 2016. Inventories were up once again, and service levels were lower than expected. Dale wondered why these problems could not be solved once and for all. Last year he had installed a new production and inventory
Dale took the report and walked to Andrea Meline’s office next door. Andrea had received her M.B.A. a few years ago from a prestigious business school and was now in charge of production control for the company. After exchanging the usual greetings, Dale asked Andrea why the latest figures were not better. Andrea responded, "Dale, we continue to get poor
BACKGROUND
ToysPlus is a small, privately held company in the toy industry, with sales of about $20 million a year. The company was started in 1951, manufacturing an innovative line of plastic toys and trucks that were very durable and low-priced. Over the years it has added several lines of toys and is now making 22 different toys, including games, dolls, toy vehicles, and novelty items. The company has a typical functional organization, as shown in Exhibit 1.
EXHIBIT 1 Organization chart.
ToysPlus has had relatively poor financial results, as shown in Exhibit 2. Profits are averaging only 5 percent of sales, and return on assets is less than 10 percent. To improve the situation, the company has decided to make a major effort to reduce inventories and to improve customer service. In an effort to reduce costs, the company has begun to redesign the toys for manufacturability and automate its production process. The company feels that unit production costs could be reduced at least 5 percent per year by these efforts. The company also wants to achieve at least 15 inventory turns per year1 and a service level of 95 percent. Service level is defined as the percentage of orders filled within one week of customer order. The current service level is 90 percent.
EXHIBIT 2 Financial statements.
Manufacturing operations are organized around the different types of toys that are manufactured. Each type of toy has its own assembly line and its own dedicated workers. For example, three plastic toys—trucks, autos, and robots—are assembled on line 1. Only one toy can be assembled at a time on this line; then there is a changeover to the next toy. Currently, line 1 has 10 workers who engage in assembly, inspection, and packing of the toys. Some of the parts that are assembled into the finished toys are made on the company’s plastic-molding machines. Other parts are purchased from outside suppliers.
Production control is based on the MRP system. Every week a master
EXHIBIT 3 Master schedule prepared September 16, 2016.
The computer performs a parts explosion using the bill of materials and the on- hand inventories shown in Exhibit 4. Each toy requires several parts, as indicated in the bill of materials. For example, each auto requires one body, four wheels, two side windows, and one windshield. These parts are assembled, the product is inspected, and the toy is packed, which requires a total of .1 labor hour per auto. With 10 people working on the assembly line, at present, there are 350 hours of productive time available per week (35 hours each times 10). If the entire week is used to make autos, a total of 3,500 autos can be produced (350/.1). It takes .2 hour to make a truck and .15 hour to make a robot, thereby making it possible to produce a maximum of 1,750 trucks or 2,333 robots, if the entire line is devoted to either of these products. Production, however, is scheduled in lots, and the entire week is not necessarily devoted to only one toy.
EXHIBIT 4 Bill of materials.
In between products it takes all 10 people one hour to change the setup of the line. This changeover involves moving out the parts for the old toy, moving in the parts for the new toy, arranging the jigs and fixtures for assembly, and making trial runs to make sure that quality is right. The shop labor rate is $14 per hour for wages, including
Purchasing does not always buy the exact number of parts that are ordered by the production control department. Adjustments are made to take advantage of price breaks from suppliers or to achieve full-truckload shipments. As a result, some additional parts might be purchased in order to reduce purchasing costs. Also, suppliers do not always ship the component parts when promised. As a result, ToysPlus carries safety stock inventory to protect the master production schedule and to keep the assembly lines running, no matter what. About one week of safety stock is carried to protect for late supplier deliveries. Management has mandated that the assembly lines will not shut down.
Dale Long has stated that the company will not lay off workers on a week-to- week basis. Thus, if demand should be less than capacity, for example, by 10 percent in a week, production will be scheduled to full capacity to keep the workers busy. If this condition should continue for several weeks, workers will be laid off to adjust capacity. In a similar way, workers will be put on overtime to meet demand temporarily. But if demand exceeds normal capacity for several weeks, more workers will then be added.
A six-week rolling production schedule, based on existing capacity and lead times, is used. Each week one more week is added to keep the total master schedule horizon at six weeks. Production is adjusted each week in line with available parts, capacity, and observed demand for toys.
HAPPY HOUR
Andrea walked to General Joe’s, a favorite watering hole, for happy hour with her friend from purchasing, John White. Andrea began,
John, I don’t know what I am going to do. Dale Long has laid the law down that I must reduce inventory and improve service levels. There is no alternative or excuses this time, I must do it! I’m not sure where to start. I would like better sales forecasts, but is that realistic to expect? Can I depend on marketing? I also could reduce inventory by achieving more reliable deliveries from our suppliers. Will they cooperate? Maybe we will have to react faster in laying off and hiring workers in order to keep capacity closer to demand. What do you think of this situation? Is there a solution?
John answered,
You must remember, Andrea, the world is filled with hustlers and liars. The salespeople lie to you about forecasts, so they can have more inventory, just in case they need it. We in purchasing lie to our suppliers about when we need the parts, so that we can be sure to get them when we really need them. You pad the production schedule a little bit, just to make sure you can meet the shipments. We all are trying to cover ourselves so that we don’t run out of stock. There isn’t a solution to this problem, because we are dealing with human nature. I hate to say it, but maybe top management’s expectations are a bit unrealistic that inventory should be reduced and service improved. How can they expect anyone to accomplish these goals in an environment like this?
Discussion Questions
- 1. Calculate economic order quantities for each of the three types of toys. The EOQ formula is recommended from the supplement to Chapter 14 that considers uniform lot delivery of the toys.
- 2. Prepare a master production schedule for the next six weeks using the EOQs calculated in question 1 and a workforce of 10 employees. What inventory turnover ratio is achieved by this master schedule? How does this turnover compare with past levels and with management’s goals?
- 3. Prepare a parts explosion to support the master schedule. What parts should be ordered each week? Are there enough planned orders in time to support your master schedule?
- 4. What should Andrea Meline do to meet the inventory and service goals stated by management? Hint: If the turnover is too low from your first analysis and is not feasible using available parts, try another master schedule that is feasible with reduced production levels, uses the available parts and has a turnover of 15.
- 5. How should Andrea deal with the organization issues presented in this case?
This case was prepared as a basis for class discussion, not to illustrate either effective or ineffective handling of an administrative situation.
Want to see the full answer?
Check out a sample textbook solutionChapter CS Solutions
Loose Leaf for Operations Management in the Supply Chain: Decisions and Cases 7e
- Exercise 8-37, 8-38, 8-39 & 8-40 (Static) (LO 8-2, 3, 5) Skip to question [The following information applies to the questions displayed below.]Pacific Ink had beginning work-in-process inventory of $744,960 on October 1. Of this amount, $304,920 was the cost of direct materials and $440,040 was the cost of conversion. The 48,000 units in the beginning inventory were 30 percent complete with respect to both direct materials and conversion costs. During October, 102,000 units were transferred out and 30,000 remained in ending inventory. The units in ending inventory were 80 percent complete with respect to direct materials and 40 percent complete with respect to conversion costs. Costs incurred during the period amounted to $2,343,600 for direct materials and $3,027,840 for conversion. Exercise 8-37 (Static) Compute Costs per Equivalent Unit: Weighted-Average Method (LO 8-3) Required: a. Compute the equivalent units for the materials and conversion cost calculations. b.…arrow_forwardVikiki Furniture, Inc. produces all types of office furniture. The "Executive Secretary" is a sofa-bed that has been designed using ergonomics to provide comfort during long work hours. The sofa-bed sells for $138. There are 580 minutes available during the day, and the average daily demand has been 65 items. There are eight tasks: Task performance time (min) task must follow task listed A 4 -- B 7 -- C 6 A, B D 5 C E 6 D F 7 E G 8 E H 6 F, G Total 49 min What is the Cycle time for this operation?arrow_forwardEven if she does not, the car will be a showpiece for the rest of the business. Roberts asked the director of service operations to prepare a report about what is involved in restoring the car and whether it can be done in time for the Detroit show in 45 working days using PERT/CPM. The parts manager, the body shop manager, and the chief mechanic have provided the following estimates of times and activities that need to be done, as well as cost estimates. A. Order all needed material and parts (upholstery, windshield, carburetor, and oil pump). Time: 2 days. Cost (telephone calls and labor): $100. B. Receive upholstery material for seat covers. Cannot be done until order is placed. Time: 30 days. Cost: $2,100. C. Receive windshield. Cannot be done until order is placed. Time: 10 days. Cost: $800. D. Receive carburetor and oil pump. Cannot be done until order is placed. Time: 7 days. Cost: $1,750. E. Remove chrome from body. Can be done immediately. Time: 1 day. Cost: $200. F. Remove…arrow_forward
- The following production data were taken from the records of the finishing department for June: Inventory in process, June 1, 25% completed 260 units Transferred to finished goods during June 5,000 units Equivalent units of production during June 5,495 units Determine the number of equivalent units of production in the June 30, finishing department inventory, assuming that the first-in, first-out method is used to cost inventories. The completion percentage of 25% applies to both direct materials and conversion costs. a.448 units b.840 units c.672 units d.560 unitsarrow_forwardNumerous IT companies are staffed by Tip Top Staffing with personnel qualified for certain projects. Lisa Nuevo and Bill Goodman are developing the logical model for Tip Top's billing and records system with the use of DFDs, a data dictionary, and process descriptions. While working on the logical basis of the system, Lisa realized that Tip Top's data forms for job applications may be enhanced. Better forms: a problem with physical implementation? By considering how something will be completed, is Lisa deviating from the work at hand?arrow_forwardWhy do bottlenecks occur at Jaguar? The main reason is that the work centre atwhich the bottleneck forms, has less capacity than the work centre before and afterit.Advise Jaguar of methodologies that are available to deal with bottlenecks andwhich one you believe is the best choice.arrow_forward
- What type of process—project, job shop, flow shop, and continuous flow—would most likely be used to produce the following? Explain your reasoning. Personal computers - Weddings- Paper-Continuous Paper Books- Tax preparation - What type of process – project, job shop, flow shop, and continuous flow – would most likely be used to produce the following? Gasoline- Air-conditioners - Specialized machine tools- Ships- Producing many flavors of ice cream-arrow_forwardThe Total Manufacturing costs incurred for the month was $620,525. Beginning work inprocess was $152,000. There were $260,000 of partially finished goods remaining inwork in process inventory at the end of the month. What was the cost of goodsmanufactured during the month?arrow_forwardOperations Management PLEASE SHOW AND EXPLAIN ALL STEPS & CALCULATIONS- THANK YOU! ABC Construction has developed the following set of activities for its budgeting process. Activity Predecessor Normal Activity Time (Days) Resulting Activity Time if Activity is Crashed (Days) Total Cost to complete activity in Normal Time Total Cost to complete activity in Crash Time A -- 4 2 $200 $600 B A 6 3 $300 $1200 C A 4 1 $300 $900 D B, C 3 2 $500 $550 E D 4 1 $500 $1700 a) Using the Normal Times, what is the critical path and project completion time for the budgeting process? Also, what is the cost to complete the project based on the Normal Times? b) If we want to reduce the project completion time to the minimum possible time by crashing all activities as needed, what is the new project completion time and what is the new total project cost? c) Modify the problem as follows. There is now an indirect cost of $75 per day, which is in addition to the cost identified above.…arrow_forward
- Explain the objectives, inputs and outputs of an MRP system ?arrow_forwardGiven the following data, can an order for 40 more units for delivery in week 5 beaccepted? If not, what do you suggest can be done? There are zero units on hand.arrow_forwardKlassen Toy Company, Inc., assembles two parts(parts I and 2): Part I is first processed at workstation A for15 minutes per unit and then processed at workstation B for330 PART 2 DESIGNING OPERATIONS10 minutes per unit. Part 2 is simultaneously processed at workstationC for 20 minutes per unit. Workstations B and C feed theparts to an assembler at workstation D, where the two parts areassembled. The time at workstation Dis 15 minutes.a) What is the bottleneck of this process?b) What is the hourly capacity of the process?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.