Textbook Question
Chapter E, Problem 14P
Suad Alwan, the purchasing agent for Dubai Airlines, is interested in determining what he can expect to pay for airplane number 4 if the third plane took 20,000 hours to produce. What would Alwan expect to pay for plane number 5? Number 6? Use an 85% learning curve and a $40-per-hour labor charge.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The 4th unit of a 10-unit job took seven hours to complete. The 6th unit has been worked on for two hours, but is not yet finished. Estimate the additional amount of time needed to finish the 6th unit if the work has a 65% learning curve slope
O a. 6.143 hours
O b. 5.114 hours
O c. 3.441 hours
O d. 3.058 hours
O e. 4.143 hours
Plot and analyze learning curves?
Elizabeth Perry, a student at SUNY, bought 6 bookcases for her dorm room. Each required unpacking of parts and assembly, which included some nailing and bolting. Elizabeth completed the first bookcase in 5 hours and the second in 4 hours. a) For Elizabeth, the learning rate = % (enter your response as an integer
Chapter E Solutions
MYOMLAB W/O PEARSON ETEXT--INSTANT ACCE
Ch. E - Prob. 1DQCh. E - Prob. 2DQCh. E - Prob. 3DQCh. E - Prob. 4DQCh. E - Prob. 5DQCh. E - Prob. 6DQCh. E - Prob. 7DQCh. E - Prob. 8DQCh. E - Prob. 1PCh. E - Prob. 2P
Ch. E - Prob. 3PCh. E - Prob. 4PCh. E - Prob. 5PCh. E - Prob. 6PCh. E - Prob. 7PCh. E - Prob. 8PCh. E - Prob. 9PCh. E - Prob. 10PCh. E - Prob. 11PCh. E - Prob. 12PCh. E - Prob. 13PCh. E - Suad Alwan, the purchasing agent for Dubai...Ch. E - Prob. 15PCh. E - Prob. 16PCh. E - Regional Power owns 25 small power generating...Ch. E - Prob. 18PCh. E - Prob. 19PCh. E - Prob. 20PCh. E - Prob. 21PCh. E - Prob. 22PCh. E - Prob. 23PCh. E - Prob. 24PCh. E - Prob. 25PCh. E - Using the accompanying log-log graph, answer the...Ch. E - Prob. 1CSCh. E - Prob. 2CSCh. E - Prob. 3CS
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 33 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the fifth pool?arrow_forwardMaxera Corporation has designed a new video game controller. It took the company 52 minutes to produce the first unit. If the company uses a 75% learning rate for this task, how long should it take the company to produce the 6th unit? the 18th unit? the 30th unit? the first 6 units? the first 18 units? the first 30 units? the units 7th through 18th? the units 19th through 30th?arrow_forwardWhat does a learning curve specifically measure?arrow_forward
- Aqeel bought 6 bookcases for his place. Each required unpacking of parts and assembly, which included some nailing and bolting. Aqeel completed the first bookcase in 5 hours and the second in 4 hours. 1-What is his learning rate (k)? 2-What is his learning-curve value of b? 3-Assuming that the same rate continues, how long will the 3rd, 4th, 5th, and 6th bookcases take? Y3 = hours Y4 = hours Y5 = hours Y6 = hours 5-How long will take him to finish all the 6 cases? It will take him hours.arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 38 hours. The contractor estimates an 80 percent learning rate. Using POM for Windows or OM Explorer, how long do you estimate the time required to install the sixth pool? The time required to install the sixth pool is enter your response herehours. (Enter your response rounded to two decimal places.) Part 2 What is your estimate of the total time for all six pools? The total time for all six pools is enter your response here hours. (Enter your response rounded to two decimal places.)arrow_forwardIf a company is preparing a bid on a government contract for 40 units of a certain product. The operations manager estimates the assembly time required for the first two units to be 10.4 hours and 8.8 hours respectively. What is the appropriate learning curve? Explain and show your answer.arrow_forward
- For an 80% learning curve, if the 100th unit produced required 280 hours, how long will it take to produce the 400th unit? Show your calculations.arrow_forwardA contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 35 hours. The contractor estimates an 85 percent learning rate. Without using the computer: a. How long do you estimate the time required to install the second pool? b. How long do you estimate the time required to install the fourth pool?arrow_forwardLearning Curve. Jericho Vehicles manufacturers special-purpose all terrain vehicles primarily for military and government agencies in Canada as well as for foreign governments. The company is planning to bid on a new all-terrain vehicle specially equipped for desert military action. The company has experienced an 87% learning curve in the past for producing similar vehicles. Based on a prototype model, it estimates the first vehicle produced will require 1,600 hours of direct labour. The order is for 60 all-terrain vehicles. Determine the time that will be required for the 30th and 60th units. Use an excel spreadsheet or tables to show your calculations and justify your answer. Note: Include a graph to represent the final answer.arrow_forward
- Beth Zion Hospital has received initial certification from the state of California to become a center for liver transplants. The hospital, however, must complete its first 18 transplants under great scrutiny and at no cost to the patients. The very first transplant, just completed, required 28 hours. On the basis of research at the hospital, Beth Zion estimates that it will have an 75% learning curve. Using Table E.3, estimate the time it will take to complete: Unit number 5 75% Unit time: .513 Total time: 3.459 80% Unit number 5 Unit time: .596 Total time: 3.738 85% Unit number 5 Unit time: .686 Total time: 4.031 Unit number 18 75% Unit time: .301 Total time: .8.245 Unit number 18 80% Unit time: 3.94 Total Time: 9.716 Unit number 18 85% Unit time: .508 Total time: 11.405 a) the 5th transplant = 14.36 hours b) the first 5 transplant = ? hours (round your response to two decimal places)arrow_forwardYou are asked to do a learning curve analysis as part of your internship project, but you discover that the data is pretty slim. Unfortunately you don't have time to do more field work and you have to come up with the best estimate based on the available data. Here's what you know: It took 98.71 minutes to complete the seventh unit and only 89.35 minutes to complete the twelfth unit. What is your best estimate of the Learning Rate for this process?arrow_forwardHOW ARE LEARNING CURVES MODELED?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY