Chapter E, Problem 22P
a)
Summary Introduction
To determine: The number of boats, the firm can make in 1 year.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
b)
Summary Introduction
To determine: The number of boats, the firm can make in 1 year.
Introduction:
Learning curve:
Learning curve is based on the premise that when a person is repeating a task or job again and again, the performance of the person on that job or task will improve. It will depict relationship between cost and output over a definitive period of time.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Omega Technology is starting production of a new supercomputer for use in large research universities. It has just completed the i rst unit, which took 120 labor hours to produce. Based on its experience, it estimates its learning percentage to be 80 percent. How many labor hours should it expect the second unit to require to manufacture?
A contractor is preparing a bid to install swimming pools at a new housing addition. The estimated time to build the first pool is 21 hours. The contractor estimates a 90 percent learning rate.
Part 2
a. How long do you estimate the time required to install the second pool?
enter your response here
hours. (Enter your response rounded to two decimal places.)
Part 3
b. How long do you estimate the time required to install the fourth pool?
enter your response here
hours. (Enter your response rounded to two decimal places.)
Omega Technology is starting production of a new supercomputer for use in large research universities. It has just completed the first unit, which took 120 labor hours to produce. Based on its experience, it estimates its learning percentage to be 80 percent. How many labor hours should it expect in manufacturing the second unit?
Chapter E Solutions
MYOMLAB W/O PEARSON ETEXT--INSTANT ACCE
Ch. E - Prob. 1DQCh. E - Prob. 2DQCh. E - Prob. 3DQCh. E - Prob. 4DQCh. E - Prob. 5DQCh. E - Prob. 6DQCh. E - Prob. 7DQCh. E - Prob. 8DQCh. E - Prob. 1PCh. E - Prob. 2P
Ch. E - Prob. 3PCh. E - Prob. 4PCh. E - Prob. 5PCh. E - Prob. 6PCh. E - Prob. 7PCh. E - Prob. 8PCh. E - Prob. 9PCh. E - Prob. 10PCh. E - Prob. 11PCh. E - Prob. 12PCh. E - Prob. 13PCh. E - Suad Alwan, the purchasing agent for Dubai...Ch. E - Prob. 15PCh. E - Prob. 16PCh. E - Regional Power owns 25 small power generating...Ch. E - Prob. 18PCh. E - Prob. 19PCh. E - Prob. 20PCh. E - Prob. 21PCh. E - Prob. 22PCh. E - Prob. 23PCh. E - Prob. 24PCh. E - Prob. 25PCh. E - Using the accompanying log-log graph, answer the...Ch. E - Prob. 1CSCh. E - Prob. 2CSCh. E - Prob. 3CS
Knowledge Booster
Similar questions
- Omega Technology is starting production of a new supercomputer for use in large research universities It has just completed the first unit, which took 120 labor hours to produce. Based on its experience, it estimates its learning percentage to be 80 percent How many labor hours should it expect the second unit to require to manufacture?arrow_forwardThe most important factor(s) effecting the learning curve rate include(s): Select one: A. Complexity of the task B. Percentage of mechanical input C. Percentage of human input D. Only A and C Yield management, also known as revenue management is the amount of output of acceptable quality emerging from a production system compared with the amount that entered it. Select one: True False Obtaining lower unit costs through the use of larger facilities is called economies of scope. Select one: True False It is not unusual for fire departments to use “slack months” for building inspections, conducting prevention programs and giving talks as a way to have anticyclic outputs. Select one: True False In addition to showing time schedules, Gantt charts can also be used for capacities of facilities, workers, jobs,activities, and so forth. Select one: True Falsearrow_forwardAqeel bought 6 bookcases for his place. Each required unpacking of parts and assembly, which included some nailing and bolting. Aqeel completed the first bookcase in 5 hours and the second in 4 hours. 1-What is his learning rate (k)? 2-What is his learning-curve value of b? 3-Assuming that the same rate continues, how long will the 3rd, 4th, 5th, and 6th bookcases take? Y3 = hours Y4 = hours Y5 = hours Y6 = hours 5-How long will take him to finish all the 6 cases? It will take him hours.arrow_forward
- Suppose a manufacturer of copiers has concluded that a 70 percent learning curve applies to the time a beginning service technician takes to install copy machines. Use the Learning Curve Excel template to answer the following questions: If the time required to install the first copy machine is estimated to be five hours, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 it takes hours For x = 3 it takes hours If the learning rate changes to 65 or 95 percent, what is an estimate of the time required by a new technician to install the second and third copiers? Round your answers to one decimal place. For x = 2 and a 65% LC, it takes hours For x = 3 and a 65% LC, it takes hours For x = 2 and a 95% LC, it takes hours For x = 3 and a 95% LC, it takes hoursarrow_forwardAn aircraft company has an order to refurbish the interiors of 18 jet aircraft. The work has a learning curve percentage of 80. On the basis of experience with similar jobs, the industrial engineering department estimates that the first plan will require 300 hours to refurbish. Estimate the amount of time needed to complete: The 5th plane, The first 5 planes, All 18 planes. For a, use logarithmic approach formula, for b and c, use learningcurve approach formula.arrow_forwardCumulative Average-Time Learning CurvePohlman Company makes aircraft engines. Pohlman has noticed that, in general, each new engine design is subject to an 80 percent learning rate. Assume that the first unit produced takes500 hours, and direct labor is paid an average of $30 per hour. Required:1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total pro-duction of: one engine, two engines, four engines, eight engines, sixteen engines, and thirty-two engines. (Round hour answers to two significant digits.) 2. What is the total labor cost if Pohlman manufactures the following number of engines: one,four, or sixteen? What is the average cost per engine for the following number of engines:one, four, or sixteen? (Round your answers to the nearest dollar.)3. What if Pohlman is preparing a bid to build 16 engines? Calculate budgeted labor cost for anengine design which…arrow_forward
- Assume a learning curve following the power law. If you double the initial cost c(1) of aproduct, the cost of the 21st unit, c(21), will:a. stay the same.b. be reduced by 50 percent.c. be doubled.d. increase by a factor of ln(2).arrow_forwardIf it took 410 hours to produce the first unit of a product, and the learning curve is 90%, how long will it take to produce units 12 through 25???arrow_forwardIf the first unit of a product took 25 minutes to produce and the learning curve rate is 80%, how much time will the production of the 100th unit take?arrow_forward
- Assuming an 80 percent learning rate, if the 4th unit takes 100 hours to produce, the 16th unit should take how long to produce?arrow_forwardRichard Dulski's firm is about to bid on a new radar system. Although the product uses new technology, Dulski believes that a learning rate of 90% is appropriate. The first unit is expected to take 780 hours, and the contract is for 14 units. a) The total amount of hours to build the 14 units = hours (round your response to the nearest whole number).arrow_forwardThe time to assemble the first unit on a production line is 12. hours. The learning rate is 0.94. Approximately how long will it take for the seventh unit to be assembled? The number of hours needed for the seventh unit to be assembled is ? hours. (Round to one decimal place.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.