ASSIGNMENT 1
SUBJECT: PROJECT SCHEDULING AND COST
MANAGEMENT
Due on Feb 12, 2024, 11:59 PM
PROFESSOR: RUCHIKA AGGARWAL
SUBMITTED BY: VIKRANT SAINI ROLL NO: A00183805
1.
Estimating Activity Resources and Methods for Organizing Susan and Steve's Wedding:
EXPERT JUDGEMENT: Inquiring about food alternatives, Sally contacts a national wedding consultant with expertise in Caribbean-themed weddings. She depends on the consultant's knowledge and judgment because they have worked on comparable wedding plans before. Hence if there is anything missing can be tweaked according to the wedding and provide the best possible outcome. Sally asks Susan and Steve to visit many caterers and try out different menu items. When deciding on the menu items, she consults their knowledge and judgment. Catering is one of the major aspects of a wedding including Food, drinks, and dining. Sally gets an estimate of how long each of the two catering firms will take to complete the task from the head chef at each establishment. To give precise estimations, she depends on the chefs' experience.
ALTERNATIVE ANALYSIS:
Sally thinks of having a string quartet, a rock band, or a DJ to play music at the wedding. This makes her think through a variety of possibilities for allocating resources, such as changing the kind and quantity of resources (musical groups) for the task (music arranging). Making sure what to play as per the bride and groom's expectations and the timing of everything should be on point. As Sally has
already done similar weddings and it takes a similar time to complete the basic enmities of catering, double checking everything and planning out forward.
PUBLISHED ESTIMATING DATA
Sally cites the most recent edition of Wedding Planner's Journal, which has a table
outlining the number of waiters needed for a range of guest lists along with an essay on collaborating with caterers. Also making sure everything is in the Trend and up to date as the wedding industry is ever-changing and what is in trend needs to be kept in mind as well. To predict resource demands entails depending on publicly available data from sources in the industry and from her past data and
experiences of weddings in that area. From destinations to everything including management.
PROJECT MANAGEMENT SOFTWARE
To assist with wedding preparation, Sally downloads and completes a customized spreadsheet created by a project manager. This entails making use of capabilities in project management software that calculates resource requirements and restrictions. It also makes sure everything is scheduled and maintained in the best feasible way. To allocate the resources, labour, tasks prioritizing what comes first and analysis of any risks and backups.
BOTTOM UP ESTIMATING
To allocate tasks, Sally divides the effort required to set up the reception hall into five distinct activities. This entails calculating the estimated resources required for each distinct task and then summing these up to generate an overall estimate.
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
To: Muna Tarek(Lead Technical Staff) and Zinedine Abubakar(Purchasing DIR)
From: Duha Sami(Exec Dir of Bus Operations?Main)
Subject: Urgent Need for a new Reporting Mechanism For Maintenance Request
Date: 10/25/22
CC: Zayna Izz Ud-Din (Exec Dir Of Finance and Planning)
Muna and Zinedine,Hope the weekend went well for the both of you! I’m just reaching out today as I think we have an urgentoperational need I’m uncertain how to fulfill and could you use your advice on?Over the last several weeks we have gotten some particularly scathing email and web feedback as well assome online reviews about maintenance requests not being submitted correctly or completed for ourstudent apartment buildings near campus. Some of these have been excerpted or screen captured andshared online via social media and gone viral within our local population. My office has already hadabout two dozen calls from parents and students threatening either legal action or withholding of their rentpayments until this…
arrow_forward
Task: Writing of MEMO
Scenario:
The CEO of company ABC is planning to restructure the whole organization over the next few months (to be implemented effective 20 July 2022), due to a continuous drop in profitability. ABC is a technology company and manufacture and sell all kinds of electronic equipment.The CEO did some research and the data revealed that the competitors are growing their profits by 10% on a monthly basis - Company ABC are experiencing a drop in profits of 5% on a organization over the next few months (to be implemented effective 20 July 2022), due to a continuous drop in profitability. ABC is a technology company and manufacture and sell all kinds of electronic equipment.The CEO did some research and the data revealed that the competitors are growing their profits by 10% on a monthly basis - Company ABC are experiencing a drop in profits of 5% on a monthly basis. Company ABC wanted to launch 3 new products for Ramadan but now the company cannot afford this expense and…
arrow_forward
TO: DUHA SAMI (EXEC DIR OF BUS OPERATIONS/MAINT), MUNA TAREK (LEAD TECHNICALSTAFF)FROM: EMILY JONES (SENIOR LEASING AGENT)SUBJECT: FEEDBACK ON PROPOSED MOBILE APPDATE: 11/17/22CC: NINA COOPER (CUSTOMER EXPERIENCE REP, FTS INC.)Duha and Muna,Thank you for taking up the request to add a mobile app, this is something that students are always askingabout when shopping for apartments. It is so good to know that the answer will be “yes we have one”, nolonger “we are planning to have one”.I do have a concern about the current design proposal as I understand it. It is not uncommon for us to havesubleases and we should have a way for those tenants to be able to use the app. I know we have thosesublease contracts stored in the system so hopefully it would not be too much work to have thefunctionality to link a request to a sublease contract not just the original lease.Cheers,EmilyTO: DUHA SAMI (EXEC DIR OF BUS OPERATIONS/MAINT)FROM: JOSH MASON (MAINTANCE LEAD)SUBJECT: PROBLEM WITH THE MOBILE…
arrow_forward
Part 1: The 5 project management groups have wide industry application in modern day project management. By using practical examples of your choice, demonstrate the practical application of the project management processes in bringing a project to a successful end (Detailed response required, also acknowledge information sources).
Part 2: A gantt chart is widely applied in project management as a project scheduling tool,whose format is in bar chart form. Critically examine a gantt chart as a project scheduling tool and practically demonstrate how it can also be used as a project planning and control technique (Detailed response required, also acknowledge information sources).
arrow_forward
MANAGEMENT SCIENCE
TOPIC: Project Management | Due on November 29, 2023 (2:30pm, Yellow Paper)
Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the
Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is
a dominant force in the small city, with more students during fall and spring than permanent residents.
A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the
top 20 in college football rankings. To bolster its chances of reaching the elusive and long-desired number-one
ranking, in 2009, SWU hired the legendary Phil Flamm as its head coach.
One of Flamm's demands on joining SWU had been a new stadium. With attendance increasing, SWU
administrators began to face the issue head-on. After 6 months of study, much political arm wrestling, and some
serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached…
arrow_forward
Q2 Please help with correct answers in details: Step by step. Last submission got incorrect answers.
Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table.
Time (Weeks)
Activity
Description
ImmediatePredecessor
Optimistic
Most Probable
Pessimistic
A
Meet with board
1
1
2
B
Hire coaches
A
4
6
8
C
Conduct fundraiser
A
2
4
6
D
Announce program
B, C
1
2
3
E
Meet with coaches
B
2
3
4
F
Order team equipment
A
1
2
3
G
Register athletes
D
1
2
3
H
Reserve buses for meets
G
1
2
3
I
Plan first practice
E, H, F
1
1
1
Develop an activity schedule. (Round your answers to two decimal places.)
Activity
EarliestStart
LatestStart…
arrow_forward
Assignment No. 11
Answer 2 a, b, c
arrow_forward
Practice Question EVM:
A simple project consists of five tasks and is scheduled to take 13 weeks to complete. The actual
status of the project at the end of week 9 is given in the following table:
Project Plan
Task | Duration Start
(weeks)
Actual status
Actual
current cost complete
S350
S225
$475
$300
End
Budget
Percent
week week
$300
100%
100%
$250
$450
$600
$500
B
2
100%
75%
75%
C
4
4
7.
9.
13
D
3
6
8
$300
a) For each activity, compute the ACWP, BCWP, BCWS and add the columns to get the
projected total. Record your answers in the table below.
Task
ACWP
BCWP
BCWS
E
b) Calculate: CV,SV,CPI, and SPI:
arrow_forward
V
what is feasibility Report ?Define when and why we need it And also define who prepare this document.
arrow_forward
PROJECT NAME: ERRANDMATE ANDROID-BASED MARKET APPLICATION
Question:
1. To Identify the current processes acquiring errand service
2. To Identify the current processes acquiring errand service
3. Research work on errand service business and related or existing errand service system
arrow_forward
Question 2
Problem Statement: Project Control and Monitoring
You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project.
Required:
Calculate Cost and Schedule Variance
What is SPI and CPI of the project?
Estimate at completion and Estimated time to complete?
arrow_forward
Details
arrow_forward
nity College | Pima x
B Module 12 Practice Assignment
6 Question 1- Module 12 Practice x
A ezto.mheducation.com/ext/map/index.html?_con=con&external_browser=D0&launchUrl=https%253A%252F%252Flms.mheducation.com%252Fmghmiddleware%252Fr
ediStay v4
E New Scorpion
O Redistay - (Unknown) U Ulitpro -New
e Scorpion (UAT)
5) Springfield - Home
inContact
Dashboards
RediStay v4 (UAT) -...
lodule 12 Practice Assignment_Ch.17 i
Saved
1
Challenge Problem 17-25 (Static) [LU 17-2 (2)]
A delivered price (including attachments) of a crawler dozer tractor is $135,000 with a residual value of 35%. The useful life of the
tractor is 7,700 hours
eBook
Print
a. What is total amount of depreciation allowed?
References
Total amount
b. What is the amount of depreciation per hour? (Round your answer to the nearest cent.)
Amount of depreciation
per hour
arrow_forward
Q1 ) Scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a ‘Website’:
Activity
Description
Duration (weeks)
Preceding Activities
A
Determine user needs
8
--
B
Review s/w and languages
4
--
C
Purchase software
10
--
D
Design format and style
10
B
E
Write programs
6
A
F
Review outcome product with user
12
C
G
Make revisions
4
C
H
Select server site
8
E
I
Install on server
14
D,F
J
Test
8
G,H,I
Draw the path.
Calculate the early finishing time (forwards calculations)
Highlight the total time to complete the project (days)
Calculate the late finishing time (backwards calculations)
Calculate the slack time of the non-critical path activities
Identify the critical path (highlight critical path activities)
what would happen if activity D revised to take 14 instead of 10 days?
arrow_forward
Q/ 1- Explain this sentence:-In practice, the most common requirement for project re-planning are concerns time and cost.2- What is the relation between the planning process and statement of work, work breakdown structure?
arrow_forward
1.
Using Microsoft Excel TM prepare a Gantt Chart for the following project.
Activity
Predecessor(s) Duration (Days)
1. Forming the problem
statement
2. Identifying functional
requirements
3. Identifying constraints and
limitations
4. Defining a schedule
5. Defining the design
parameters
6. Identifying alternatives
7. Evaluating and analyzing
alternatives
8. Select a solution
9. Gather supplies
10. Construct prototype
11. Test performance
12.
1
1
1
1
1
2,3
1
2
1
2
7
1
8
4
10
1
Redesign
13.
11
2
Demonstrate solution to
12
1
class
5
CO
arrow_forward
Draw a network diagram for the project.
Find the minimum project completion time.
Identify the critical activities and critical path.
arrow_forward
assignment:
topic:
1.National defence and science in china
2.china aerospace
arrow_forward
Question 11
A Project Charter has high level information such as high level requirements, high
level risks, etc whereas a Scope Statement has detailed information
True
False
arrow_forward
Recommendations for North East Link project in Victoria.
Recommendations on how to solve budget blowout.
Please include references.
arrow_forward
Activity-4
Dear Students,
Search in the internet and submit a written report
(minimum three (3) pages) of an effective sales
training program conducted by any company.
arrow_forward
Question:
A Hospital Management System Development Project has a budgeted cost of Rs. 11,900,000/-. The project is to be completed in 11 months. After 4 months, you have completed 24 percent of the project at a total expense of Rs. 1,475,000/-. You, as a Project Manager, needs to submit the monthly performance report to the Steering Committee. Based on EVM methodology, please identify the current progress of the Project.
Find Budget at Completion (BAC), Actual Cost(AC), Planned Value (PV) and Earned Value (EV).
Calculate the Project Health by finding values of Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV) and Cost Performance Index (CPI). What these value shows?
If the project continues at the current pace, what will be the true cost of the Project or Estimate at completion of the project.
What actions, You would suggest or take as a Project Manager, to keep the budget and time under control.
arrow_forward
The Advanced Tech Company has a project to design an integrated information databasefor a major bank. Data for the project are given in Table Q2 below. Indirect project costsamount to $300 per day. The company will incur a $150 per day penalty for each day theproject lasts beyond day 14.(a)What is the shortest time duration and cost for this project?B)What is the total cost and time of the minimum-cost schedule?
arrow_forward
Plz provide correct Answer for it previous one was wrong
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Related Questions
- To: Muna Tarek(Lead Technical Staff) and Zinedine Abubakar(Purchasing DIR) From: Duha Sami(Exec Dir of Bus Operations?Main) Subject: Urgent Need for a new Reporting Mechanism For Maintenance Request Date: 10/25/22 CC: Zayna Izz Ud-Din (Exec Dir Of Finance and Planning) Muna and Zinedine,Hope the weekend went well for the both of you! I’m just reaching out today as I think we have an urgentoperational need I’m uncertain how to fulfill and could you use your advice on?Over the last several weeks we have gotten some particularly scathing email and web feedback as well assome online reviews about maintenance requests not being submitted correctly or completed for ourstudent apartment buildings near campus. Some of these have been excerpted or screen captured andshared online via social media and gone viral within our local population. My office has already hadabout two dozen calls from parents and students threatening either legal action or withholding of their rentpayments until this…arrow_forwardTask: Writing of MEMO Scenario: The CEO of company ABC is planning to restructure the whole organization over the next few months (to be implemented effective 20 July 2022), due to a continuous drop in profitability. ABC is a technology company and manufacture and sell all kinds of electronic equipment.The CEO did some research and the data revealed that the competitors are growing their profits by 10% on a monthly basis - Company ABC are experiencing a drop in profits of 5% on a organization over the next few months (to be implemented effective 20 July 2022), due to a continuous drop in profitability. ABC is a technology company and manufacture and sell all kinds of electronic equipment.The CEO did some research and the data revealed that the competitors are growing their profits by 10% on a monthly basis - Company ABC are experiencing a drop in profits of 5% on a monthly basis. Company ABC wanted to launch 3 new products for Ramadan but now the company cannot afford this expense and…arrow_forwardTO: DUHA SAMI (EXEC DIR OF BUS OPERATIONS/MAINT), MUNA TAREK (LEAD TECHNICALSTAFF)FROM: EMILY JONES (SENIOR LEASING AGENT)SUBJECT: FEEDBACK ON PROPOSED MOBILE APPDATE: 11/17/22CC: NINA COOPER (CUSTOMER EXPERIENCE REP, FTS INC.)Duha and Muna,Thank you for taking up the request to add a mobile app, this is something that students are always askingabout when shopping for apartments. It is so good to know that the answer will be “yes we have one”, nolonger “we are planning to have one”.I do have a concern about the current design proposal as I understand it. It is not uncommon for us to havesubleases and we should have a way for those tenants to be able to use the app. I know we have thosesublease contracts stored in the system so hopefully it would not be too much work to have thefunctionality to link a request to a sublease contract not just the original lease.Cheers,EmilyTO: DUHA SAMI (EXEC DIR OF BUS OPERATIONS/MAINT)FROM: JOSH MASON (MAINTANCE LEAD)SUBJECT: PROBLEM WITH THE MOBILE…arrow_forward
- Part 1: The 5 project management groups have wide industry application in modern day project management. By using practical examples of your choice, demonstrate the practical application of the project management processes in bringing a project to a successful end (Detailed response required, also acknowledge information sources). Part 2: A gantt chart is widely applied in project management as a project scheduling tool,whose format is in bar chart form. Critically examine a gantt chart as a project scheduling tool and practically demonstrate how it can also be used as a project planning and control technique (Detailed response required, also acknowledge information sources).arrow_forwardMANAGEMENT SCIENCE TOPIC: Project Management | Due on November 29, 2023 (2:30pm, Yellow Paper) Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is a dominant force in the small city, with more students during fall and spring than permanent residents. A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the top 20 in college football rankings. To bolster its chances of reaching the elusive and long-desired number-one ranking, in 2009, SWU hired the legendary Phil Flamm as its head coach. One of Flamm's demands on joining SWU had been a new stadium. With attendance increasing, SWU administrators began to face the issue head-on. After 6 months of study, much political arm wrestling, and some serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached…arrow_forwardQ2 Please help with correct answers in details: Step by step. Last submission got incorrect answers. Due to population growth in the area, the new Liberty High School has just opened in a local school district. The athletic director at Liberty High is planning the launch of the school's track and field team. The first team practice is scheduled for April 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are listed in the following table. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 6 8 C Conduct fundraiser A 2 4 6 D Announce program B, C 1 2 3 E Meet with coaches B 2 3 4 F Order team equipment A 1 2 3 G Register athletes D 1 2 3 H Reserve buses for meets G 1 2 3 I Plan first practice E, H, F 1 1 1 Develop an activity schedule. (Round your answers to two decimal places.) Activity EarliestStart LatestStart…arrow_forward
- Assignment No. 11 Answer 2 a, b, carrow_forwardPractice Question EVM: A simple project consists of five tasks and is scheduled to take 13 weeks to complete. The actual status of the project at the end of week 9 is given in the following table: Project Plan Task | Duration Start (weeks) Actual status Actual current cost complete S350 S225 $475 $300 End Budget Percent week week $300 100% 100% $250 $450 $600 $500 B 2 100% 75% 75% C 4 4 7. 9. 13 D 3 6 8 $300 a) For each activity, compute the ACWP, BCWP, BCWS and add the columns to get the projected total. Record your answers in the table below. Task ACWP BCWP BCWS E b) Calculate: CV,SV,CPI, and SPI:arrow_forwardV what is feasibility Report ?Define when and why we need it And also define who prepare this document.arrow_forward
- PROJECT NAME: ERRANDMATE ANDROID-BASED MARKET APPLICATION Question: 1. To Identify the current processes acquiring errand service 2. To Identify the current processes acquiring errand service 3. Research work on errand service business and related or existing errand service systemarrow_forwardQuestion 2 Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?arrow_forwardDetailsarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON