Amelia Ltd. makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. The company has orders for 48,000 of these trikes. Current schedules yield the following information.                                   Requirements         Component     Plastic     Time     Space Cost to     Manufacture Cost to   Purchase Front seat /Frame Rear wheel (each) 12 16 .20 40 24 8 8 8 .4 16 12 2 24 18 6 Available 100000 320000 60000         The company obviously does not have the resources available to manufacture everything needed for the completion of 24000 tricycles so has gathered purchase information for each component. Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 24000 fully completed tricycles at the minimum cost.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

3) Amelia Ltd. makes a plastic tricycle that is composed of three major components: a
handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. The
company has orders for 48,000 of these trikes. Current schedules yield the
following information.
                               

 

Requirements

 

 

 

 

Component

 

 

Plastic

 

 

Time

 

 

Space

Cost to  

 

Manufacture

Cost to

 

Purchase

Front seat /Frame Rear wheel (each)

12

16

.20

40

24

8

8

8

.4

16

12

2

24

18

6

Available

100000

320000

60000

 

 

 

 

The company obviously does not have the resources available to manufacture
everything needed for the completion of 24000 tricycles so has gathered purchase
information for each component. Develop a linear programming model to tell the
company how many of each component should be manufactured and how many
should be purchased in order to provide 24000 fully completed tricycles at the
minimum cost.

Expert Solution
steps

Step by step

Solved in 2 steps with 4 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.