The Hickory Company manufactures wooden desks. Management schedules overtime every weekend to reduce the backlog on the most popular models. The automatic routing machine is used to cut certain types of edges on the desktops. The following orders need to be scheduled for the routing machine:

Chapter 10, Problem 18P, The Hickory Company manufactures wooden desks. Management schedules overtime every weekend to reduce

The due dates reflect the need for the order to be at its next operation.

  1. Develop separate schedules by using the FCFS and EDD rules. Compare the schedules on the basis of average flow time and average past due hours.
  2. Comment on the performance of the two rules relative to these measures.

Blurred answer
Students have asked these similar questions
Using the FCFS rule for scheduling, the sequence is Sunny Park Tailors has been asked to make three different types of wedding suits for separate customers. The table below highlights the time taken in hours for cutting and sewing (process 1) and delivery (process 2) of each of the suits Times Taken for Different Activities (hours) Cut and Sew Suit 1 2 3 7 4 5 Deliver 2 3 6 Assume that orders for suits have been listed in the above table in the order in which they were received. C
A process improvement team is working to improve the production output at the Johnson Manufacturing plant’sHeader Cell that manufactures a key component, headers, used in commercial air conditioners. A header is partof the circulatory system of a commercial air conditioner that moves coolant between various components suchas the evaporator coil and the condenser coil. Currently, the header production cell is scheduled separately fromthe main work in the plant. Often, individual headers are not sequenced to match the product they go into on thefinal assembly line in a timely fashion, and so the product can sit in queue waiting for a header
12-13 Mike Dreskin manages a large Los Angeles movie theater complex called Cinema I, II, III, and IV. Each of the four auditoriums plays a different film; the schedule is set so that starting times are staggered to avoid the large crowds that would occur if all four movies started at the same time. The theater has a single ticket booth and a cashier who can maintain an average service rate of 280 movie patrons per hour. Service times are assumed to follow an exponential distribution. Arrivals on a typically active day are Poisson distributed and average 210 per hour. To determine the efficiency of the current ticket operation, Mike wishes to examine several queue operating characteristics. a. Find the average number of moviegoers waiting in line to purchase a ticket. b. What percentage of the time is the cashier busy? c. What is the average time that a customer spends in the system? d. What is the average time spent waiting in line to get to the ticket window? e. What is the…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY