Management at the Kerby Corporation has determined the following aggregated demand
An employee can produce an average of 10 units per month. Each worker on the payroll costs $2,000 in regular—time wages per month. Undertime is paid at the same rate as regular time. In accordance with the labor contract in force, Kerby Corporation does not work overtime or use subcontracting. Kerby can hire and train a new employee for $2,000 and lay off one for $500. Inventory costs $32 per unit on hand at the end of each month. At present, 140 employees are on the payroll and anticipation inventory is zero.
- Prepare a production plan that only uses a level workforce and anticipation inventory as its supply options. Minimize the inventory left over at the end of the year. Layoffs. undertime, vacations, subcontracting, backorders, and stockouts are not options. The plan may call for a one-time adjustment of the workforce before month 1 begins.
- Prepare a production plan using a chase strategy, relying only on hiring and layoffs.
- Prepare a mixed—strategy production plan that uses only a level workforce and anticipation inventory through month 7 (an adjustment of the workforce may be made before month 1 begins) then switches to a chase strategy for months 8 through 12.
- Contrast these three plans on the basis of annual costs.
Want to see the full answer?
Check out a sample textbook solutionChapter 10 Solutions
Operations Management: Processes and Supply Chains (11th Edition)
Additional Business Textbook Solutions
Principles Of Operations Management
Operations Management
Business in Action
Operations Management, Binder Ready Version: An Integrated Approach
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
- State the advantage and disadvantage of varying the workforce in accordance to the predicted changes in demand requirements.arrow_forwardAn embroidery business in the city of Obregon manufactures clothing, has seen high demand in the months of September-October 2020.The following data was collected: A total of 6000 Levis pants were manufactured in the month of September and October, which qualified as a demanding product. The stand was working hard, in a total of 60 days, from Monday to Sunday, 8 hours shifts, of that time 15 min were for changing the embroidery rolls and one hour for the workers. Due to the high demand of these months there are no Kanban times. Instructions: Determine the parts per hour of work that were produced during the months of September and October 2020. Important: Use the formula (the one I put in the image)arrow_forwardCompany A recently completed and sold an order of 50 units that had the following costs: Direct materials Direct labor* (1000 hours @ P8.50) |Variable overhead (1000 hours @ P4.00) Other overhead costs** Total 1500 8500 4000 1400 15400 | *Applied on the basis of direct labor hous **Applied at the rate of 10% of variable cost The company has now been requested to prepare a bid for 150 units of the same product. If an 80% incremental unit-time learning curve is applicable, Company A's total cost on this order would be estimated atarrow_forward
- The Big Black Bird Company (BBBC) has a large order for special plastic-lined military uniforms to be used in an urgent military operation. Working the normal two shifts of 40 hours each per week, the BBBC production process usually produces 2,500 uniforms per week at a standard cost of $120 each. 68 employees work the first shift and 28 the second. The contract price is $240 per uniform. Because of the urgent need, BBBC is authorized to use around-the-clock production six days per week. When each of the two shifts works 72 hours per week, production increases to 4,200 uniforms per week but at a cost of $152 each. a. The multifactor productivity level for two shifts working 72 hours when compared to the level of the normal two shifts. did not change decreased increasedarrow_forwardDainty Ltd has an average weekly payroll of $200 000. The employees are entitled to 2 weeks', non- vesting sick leave per annum. Past experience suggests that 56% of employees will take the full 2 weeks' sick leave and 22% will take 1 week's leave each year. The rest of the employees take no sick leave.Calculate the expected annual sick-leave expense for Dainty Ltd (on the basis of average salaries)arrow_forwardThe Big Black Bird Company (BBBC) has a large order for special plastic-lined military uniforms to be used in an urgent military operation. Working the normal two shifts of 40 hours each per week, the BBBC production process usually produces 2,400 uniforms per week at a standard cost of $140 each. 70 employees work the first shift and 28 the second. The contract price is $200 per uniform. Because of the urgent need, BBBC is authorized to use around-the-clock production six days per week. When each of the two shifts works 72 hours per week, production increases to 4,000 uniforms per week but at a cost of $144 each. The multifactor productivity level decreased for two shifts working 72 hours when compared to the level of the normal two shifts. The multifactor productivity ratio based on the normal two shifts changed by ___% as compared to two shifts working 72 hours per week. (Enter your response rounded to two decimal places.) Part 4 The labor productivity level decreased for…arrow_forward
- The Big Black Bird Company (BBBC) has a large order for special plastic-lined military uniforms to be used in an urgent military operation. Working the normal two shifts of 40 hours each per week, the BBBC production process usually produces 2,500 uniforms per week at a standard cost of $120 each. 68 employees work the first shift and 30 the second. The contract price is $220 per uniform. Because of the urgent need, BBBC is authorized to use around-the-clock production six days per week. When each of the two shifts works 72 hours per week, production increases to 3,800 uniforms per week but at a cost of $144 each. a. The multifactor productivity level for two shifts working 72 hours when compared to the level of the normal two shifts.arrow_forwardBarker Company produces and sells a single product with budgeted or standard costs as follows: Inputs Standards Direct materials 10 lbs at $10.00 per pound Direct labor 8 hours at $12.50 per hour Variable factory overhead 8 hours at $20.00 per hour Fixed factory overhead 8 hours at $40.00 per hour Overhead rates are based on 8,000 standard direct labor hours per month, i.e., this is the master budget denominator activity level. Desired ending inventories of materials are based on 10% of the next months materials needed. Desired ending finished goods are based on 5% of next periods budgeted unit sales. Unit Sales are budgeted as follows: January February March April 1,000 1,200 1,600 1,400 The budgeted sales price is $1000 per unit. Sales are budgeted as 80% credit sales and 20% cash sales. Past experience indicates that 60% of credit sales are collected during the month of sale, 38% are collected in the following month, and…arrow_forward1. A worker earns a minimum daily wage of P537. His regular work hours are from 8:00 am to 5:00 pm with one hour lunch break. The worker's rest day is Thursday. Paydays are every 5th and 20th of the month. Compute his daily gross earnings if his time record shows the following data: Date 21 - Dec Thursday (Rest Day) 22 - Dec Friday 23 - Dec Saturday 24 - Dec Sunday ( Special Holiday) 8:00 am 11:00 am 25 - Dec Monday (Regular Holiday ) NO WORKINO WORK 26 - Dec Tuesday 27 - DecWednesday 28 - DecThursday ( Rest Day) 29 - DecFriday 30 - DecSaturday( Regular Holiday )8:00 am 5:00 pm 31 - Dec Sunday ( Special Holiday) 8:00 am 11:30 am 1- Jan Monday (Regular Holiday ) NO WORKINO WORK 2- Jan Tuesday 3- Jan Wednesday 4- Jan Thursday (Rest Day) |Day Time In Time Out 9:00 am 4:00 pm 8:00 am 5:00 pm 8:00 am 5:00 pm 8:30 am 5:00 pm 8:00 am 5:00 pm 10:00 am 3:00 pm 8:00 am 5:00 pm ]9,00 am 5:00 pm 8:00 am 5:00 pm 8:00 am 4:00 pmarrow_forward
- A business company has the following capacity per month based on the following: 30 working days per month; 1 shift operation at 8 hours per shift; 30 minutes break per shift per employee ABC company produces bicycles and has the following Capacities per process. Frame Welding: 60 bikes per hour per machine Painting: 20 bikes per hour per worker Assembly: 50 bikes per hour per worker Inspection: 100 bikes per hour per worker What can be observed from the system if the demand for the month is 5,000 bikes?arrow_forwardAcme, Corp. produces and sells tennis rackets. Each tennis racket is sold for $150 and average total costs per racket are $125, $100 of which are variable. Acme's fixed costs total $10,000 per month. What is Acme's unit contribution margin? A. $50 B. Neither of these C. $25arrow_forwardSkyChefs, Inc., prepares in-flight meals for a number of major airlines. One of the company’s products is grilled salmon in dill sauce with baby new potatoes and spring vegetables. During the most recent week, the company prepared 4,300 of these meals using 1,250 direct labor-hours. The company paid its direct labor workers a total of $11,250 for this work, or $9.00 per hour. According to the standard cost card for this meal, it should require 0.30 direct labor-hours at a cost of $8.50 per hour. Required: 1. What is the standard labor-hours allowed (SH) to prepare 4,300 meals? 2. What is the standard labor cost allowed (SH × SR) to prepare 4,300 meals? 3. What is the labor spending variance? 4. What is the labor rate variance and the labor efficiency variance?arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.