OPERATIONS MANAGEMENT LL PACKAGE
OPERATIONS MANAGEMENT LL PACKAGE
11th Edition
ISBN: 9781323592632
Author: KRAJEWSKI
Publisher: Pearson Custom Publishing
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 11, Problem 10P

An end item’s demand forecasts for the next 10 weeks are 30, 30, 30, 30, 20, 20, 30, 30, 30, and 30 units. The current on-hand inventory is 100 units. The order policy is to produce in lots of 75. The booked customer orders for the item, starting with week 1, are 15, 38, 7, 5, 0, 3, 10, 0, 0, and 0 units. The lead time is 2 weeks.

  1. Develop an MPS for this end item.
  2. The marketing department has received five orders for this item in the following sequence:
  3. Order 1 is for 20 units to be delivered in period 1.

    Order 2 is for 75 units to be delivered in period 4.

    Order 3 is for 90 units to be delivered in period 6.

    Order 4 is for 75 units to be delivered in period 7.

    Order 5 is for 90 units to be delivered in period 10.

Assuming that the prospective MPS you developed in part (a) does not change, which orders would you be able to accept based on the available to promise (ATP)?

Blurred answer
Students have asked these similar questions
Prepare a Master Production Schedule (MPS) for an Agri-Chemical company given the following information: The forecast for each week of an eight￾week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows:Week Customer Orders1          522          353          204         12Use a production lot size of 75 units and no beginning inventory.
) The following data have been prepared for master production scheduling purposes in IKEA Australia:     End product A: Beginning inventory of 60, Period forecast of 10, Lot size of 30, and 30 hours in lot size.    End product B: Beginning inventory of 20, Period forecast of 5, Lot size of 20, and 20 hours in lot size. End product C: Beginning inventory of 30, Period forecast of 15, Lot size of 50, and 50 hours in lot size.  Capacity: 38 hours/ week        (i) Prepare the master production schedule for these items during the next four periods using the Ethan Allen master production scheduling method.                           (ii) Suppose that the master production schedule is frozen for the next three periods. What specific impact would the policy have on the IKEA's performance?
An end item’s demand forecasts for the next 6 weeks are 30 units, followed by forecasts of 25 units for weeks 7 through 10. The current on-hand inventory is 60 units. The order policy is to produce in lots of 100. The booked customer orders for the item, starting with week 1, are 22, 30, 15, 11, 0, 0, 9, 0, 0, and 0 units. The lead time is 2 weeks.a. Develop an MPS for this end item.b. The marketing department has received six orders for this item in the following sequence:Order 1 is for 40 units to be delivered in period 3Order 2 is for 60 units to be delivered in period 4Order 3 is for 70 units to be delivered in period 6Order 4 is for 40 units to be delivered in period 3Order 5 is for 20 units to be delivered in period 5Order 6 is for 115 units to be delivered in period 9Assuming that the prospective MPS you developed in part (a) does not change, which orders would you be able to accept based on the available to promise (ATP)?

Chapter 11 Solutions

OPERATIONS MANAGEMENT LL PACKAGE

Ch. 11 - A forecast of 240 units in January, 320 units in...Ch. 11 - An end items demand forecasts for the next 6 weeks...Ch. 11 - An end items demand forecasts for the next 10...Ch. 11 - Consider the bill of materials (BOM) in Figure...Ch. 11 - Product A is made from components B, C, and D....Ch. 11 - What is the lead time (in weeks) to respond to a...Ch. 11 - Product A is made from components B and C. Item B,...Ch. 11 - Refer to Figure 11.23 and Solved Problem 1. If...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - The partially completed inventory record for the...Ch. 11 - Figure 11.38 shows a partially completed inventory...Ch. 11 - A partially completed inventory record for the...Ch. 11 - The BOM for product A is shown in Figure 11.40,...Ch. 11 - The BOMs for products A & B and data from the...Ch. 11 - Figure 11.42 illustrates the BOM for product A....Ch. 11 - The following information is available for three...Ch. 11 - Figure 11.44 shows the BOMs for two products, A...Ch. 11 - The BOM for product A is shown in Figure 11.45....Ch. 11 - Refer to Solved Problem 1 (Figure 11.23) for the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The bill of materials and the data from the...Ch. 11 - The McDuff Credit Union advertises their ability...Ch. 11 - Suppose that the POQ for item B is changed from 3...Ch. 11 - As the on-hand inventory for item C increases from...Ch. 11 - As the fixed order quantity (FOQ) for item D...Ch. 11 - As the lead time for item C changes, what happens...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY