Textbook Question
Chapter 11, Problem 11.35BE
Calculate and explain direct material variances (Learning Objective 2)
Star Class Rings produces class rings. Its best-selling model has a direct material standard of 8 grams of a special alloy per ring. This special alloy has a
Requirements
- 1. What is the actual cost per gram of the special alloy that Star Class Rings purchased last month?
- 2. What is the direct material price variance?
- 3. What is the direct material quantity variance?
- 4. How might the direct material price variance for the company last month be causing the direct material quantity variance?
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
Average labor cost for the first 700 units of a product is RO 50 and the average labor cost of first 1400 units is RO 45. Average time per unit is 100 minutes. The learning ratio and the average labour cost for first 2800 units will be:
a.
80% and RO 36.000
b.
90% and RO 40.500
c.
85% and RO 38.250
d.
95% and RO 42.750
The following scenario relates to 5 questions.
Bear Co has developed a new model of television. The estimated labour time for the
first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight
units produced
Note: The learning index for a 75% learning curve is -0.415.
Overhead production costs must be estimated based on a previous model, the
Leonardo, that was made by Bear Co. Production quantities and total overhead costs
for the last four months of production of the Leonardo were as follows:
Month
Output
Total overhead cost
(units)
$
September
1,800
278,200
October
2,000
310,000
November
1,700
252,900
December
200,000
1,000
You have been asked to estimate the variable overhead cost per unit of the new television by assuming
that it will be the same as for the Leonardo, using the information provided for the last four months of its
manufacture, and applying a 6% inflation rate.
What is the variable cost per unit using the high-low method (to two decimal…
The following scenario relates to 5 questions.
Bear Co has developed a new model of television. The estimated labour time for the
first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight
units produced
Note: The learning index for a 75% learning curve is-0-415.
Overhead production costs must be estimated based on a previous model, the
Leonardo, that was made by Bear Co. Production quantities and total overhead costs
for the last four months of production of the Leonardo were as follows:
Month
Output
Total overhead cost
(units)
$
September
1,800
278,200
October
2,000
310,000
November
1,700
252,900
December
1,000
200,000
The first phase of production has now been completed for the new television. The first unit actually took
12-5 hours to make and the total time for the first eight units was 34-3 hours, at which point the learning
effect came to an end.
What is the actual learning rate, and did the labour force learn more quickly or less quickly than…
Chapter 11 Solutions
Managerial Accounting (5th Edition)
Ch. 11 - (Learning Objective 1) Which of the following is...Ch. 11 - (Learning Objective 2) The direct material price...Ch. 11 - Prob. 3QCCh. 11 - Prob. 4QCCh. 11 - Prob. 5QCCh. 11 - (Learning Objective 4) Which of the following is...Ch. 11 - Prob. 7QCCh. 11 - (Learning Objective 6) Which of the following is...Ch. 11 - Prob. 9QCCh. 11 - (Learning Objective 7Appendix) Which of the...
Ch. 11 - Compute the standard cost of direct materials...Ch. 11 - Compute the standard cost of direct labor...Ch. 11 - Explain a direct material variance (Learning...Ch. 11 - Prob. 11.4SECh. 11 - Calculate direct material variances when the...Ch. 11 - Calculate direct labor variances (Learning...Ch. 11 - Prob. 11.7SECh. 11 - Prob. 11.8SECh. 11 - Calculate fixed overhead variances (Learning...Ch. 11 - Calculate and interpret fixed overhead variances...Ch. 11 - Prob. 11.11SECh. 11 - Calculate and interpret overhead variances...Ch. 11 - Record costing transactions (Learning Objective 7)...Ch. 11 - Record standard costing transactions (Learning...Ch. 11 - Identify ethical standards violated (Learning...Ch. 11 - Vocabulary (Learning Objectives 1, 2, 3, 4, 5, 6)...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Calculate and interpret direct material and direct...Ch. 11 - Calculate the material and labor variances...Ch. 11 - Record materials and labor transactions (Learning...Ch. 11 - Calculate the standard cost of a product before...Ch. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Compute and interpret overhead variances (Learning...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Data Set for E11-28A through E11-32A Country...Ch. 11 - Make journal entries in a standard costing system...Ch. 11 - Prepare a standard cost income statement (Learning...Ch. 11 - Calculate standard cost and gross profit per unit...Ch. 11 - Calculate the standard cost per unit (Learning...Ch. 11 - Calculate and explain direct material variances...Ch. 11 - Calculate missing direct material variables...Ch. 11 - Calculate and explain direct labor variances...Ch. 11 - Prob. 11.38BECh. 11 - Prob. 11.39BECh. 11 - Prob. 11.40BECh. 11 - Prob. 11.41BECh. 11 - Recognize advantages and disadvantages of standard...Ch. 11 - Calculate and interpret overhead variances...Ch. 11 - Prob. 11.44BECh. 11 - Prob. 11.45BECh. 11 - Prob. 11.46BECh. 11 - Prob. 11.47BECh. 11 - Prob. 11.48BECh. 11 - Prob. 11.49APCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Prob. 11.52APCh. 11 - Prob. 11.53APCh. 11 - Prob. 11.54BPCh. 11 - Comprehensive standards and variances problem...Ch. 11 - Comprehensive standards and variances problem...Ch. 11 - Work backward through labor variances (Learning...Ch. 11 - Determine all variances and make journal entries...Ch. 11 - Calculate labor variances in a hotel (Learning...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- University Rings produces class rings. Its best-selling model has a direct materials standard of 15 grams of a special alloy per ring. This special alloy has a standard cost of $65.50 per In the past month, the company purchased 15,800 grams of this alloy at a total cost of $1,030,160. A total of 15,500 grams were used last month to produce 1,000 rings. gram.arrow_forwardYour company has received an order for 20 units of aproduct. Th e labor cost to produce the item is $9.50 per hour. Th esetup cost for the item is $60 and material costs are $25 per unit. Th e item is sold for $92. Th e learning rate is 80 percent. Overheadis assessed at a rate of 55 percent of unit labor cost.(a) Determine the average unit cost for the 20 units if the fi rstunit takes four hours.(b) Determine the minimum number of units that need to bemade before the selling price meets or exceeds the averageunit cost.arrow_forwardEsteban Products produces instructional aids, including white boards, which use colored markers instead of chalk. These are particularly popular for conference rooms in educational institutions and executive offices of large corporations. The standard cost of materials for this product is 10 pounds at $8.50 per pound. During the first month of the year, 3,600 boards were produced. Information concerning actual costs and usage of materials follows: Materials purchased 35,600 lbs. @ $8.60 Materials used 35,100 lbs. Required: 1. Compute the materials price and usage variances. 2. Prepare journal entries on Jan. 31 for all activity relating to materials.arrow_forward
- Esteban Products produces instructional aids, including white boards, which use colored markers instead of chalk. These are particularly popular for conference rooms in educational institutions and executive offices of large corporations. The standard cost of materials for this product is 12 pounds at $8.75 per pound. During the first month of the year, 3,700 boards were produced. Information concerning actual costs and usage of materials follows: Materials purchased 44,000 lbs. @ $8.85 Materials used 43,500 lbs. Required: 1. Compute the materials price and usage variances. 2. Prepare journal entries on Jan. 31 for all activity relating to materials. CHART OF ACCOUNTS General Ledger ASSETS 110 Cash 120 Accounts Receivable 131 Supplies 132 Prepaid Insurance 141 Materials 142 Work in Process 143 Overhead Control 144 Finished Goods 170 Land 180 Equipment 181 Accumulated Depreciation LIABILITIES 210…arrow_forwardNUBD Company is planning to introduce a new product with an 80 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the cumulative total time (labor hours) to produce 16,000 units based on the cumulative average-time learning curve? 655.36 hours 256 hours 160 hours 409.6 hoursarrow_forwardBased on recent experience, a company knows that its production follows an 80% learning eurve. The unit variable cost of the 100 unit, which the company just produced, was $30. To complete a price quote for a customer with a special order for another 100 units, the compary needs to knew what their unit variable cost will be at the end of the special project. Which of the following is the best answer? O A. $37.50 O B. $30.00 OC. $24.00 D D. $6.00 DE. Cannot be determinec from the information givenarrow_forward
- NUBD Company is planning to introduce a new product with an 80 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the cumulative total time (labor hours) to produce 16,000 units based on the cumulative average-time learning curve? A. 655.36 hours B. 256 hours C. 160 hours D. 409.6 hoursarrow_forwardThe manufacturing process of a new product is very labor intensive. The learning curve percentage (LC) for the process is 90%. It took 30 hours with 15 workers together to produce the first product. The average labor cost including overhead expenses is about $20 per hour. (a) Estimate the labor cost (including overhead expenses) to produce the tenth product? (Hint: 2 steps. How long is T_10? How much is the cost?) (b) A new training program is intended to lower the learning-curve percentage by 10% (minus 10%). If the program is successful, what cost savings will be realized for the tenth unit? (Hint: How long is the new T_10? How much is the new cost? How much is the cost saving?)arrow_forward1.A standard which represents an efficient level of performance that is attainable under expected operating conditions is called a(n) a.ideal standard. b.loose standard. c.tight standard. d.normal standard. 2.Tom Thumb Pie Company developed the following per unit standards for its product: 4 pounds of direct materials at $24 per pound of direct materials. Last month Tom Thumb Pie Company purchased 4,000 pounds of direct materials for $95,400. The direct materials price variance for last month was a.$11,400 favorable. b.$600 favorable. c.$300 favorable. d.$600 unfavorable. 3.Jane and John’s Kitchen has a per unit standards for direct materials of 4 gallons at $8 per gallon. Last month Jane and John’s Kitchen purchased 22,400 gallons of direct materials at an actual cost of $84,800. 12,000 gallons were used to produce 3,400 units of jams and jellies. The direct materials quantity variance for last month was a.$12,800 favorable. b.$9,600 favorable. c.$12,800 unfavorable. d.$22,400…arrow_forward
- NUBD manufactures specialty components for the electronics industry in a highly labor intensive environment. ABC Electronics has asked Lake to bid on a component that NUBD made for ABC last month. The previous order was for 80 units and required 160 hours of direct labor to manufacture. ABC would now like 560 additional components. NUBD experiences an 80% learning curve on all of its jobs. The number of direct labor hours needed for NUBD to complete the 560 additional components is?arrow_forwardWood Creations designs, manufactures, and sells modern wood sculptures. Sally Jensen is an artist for the company. Jensen has spent much of the past month working on the design of an intricate abstract piece. Jim Smoot, product development manager, likes the design. However, he wants to make sure that the sculpture can be priced competitively. Alexis Nampa, Wood's cost accountant, presents Smoot with the following cost data for the expected production of 75 sculptures: $ 8,000 30,000 37,000 33,000 25,000 15,000 Design cost Direct materials Direct manufacturing labor Variable manufacturing overhead Fixed manufacturing overhead Marketing Required: 1. Smoot thinks that Wood Creations can successfully market each piece for $2,400. The company's target operating income is 20% of revenue. a.) Wood Creations has a total capital investment of $240,000. Compute the target percentage of return on investment. b.) Calculate the markup percentage on full cost based on the current cost data. c.)…arrow_forwardMonoblocs, Inc. manufactures set-it-up-yourself furniture for students. He currently makes two products, bookcases and tables. Each bookcase contributes P240 to profits and each table, P200. Each product passes through two manufacturing departments, cutting and finishing. Bookcases take 4 hrs a unit in cutting and 4 in finishing. Table require 3 hours a unit in cutting and 5 in finishing. There are currently 40 hrs available in cutting and 30 in finishing. Find the product mix that will produce the maximum profit.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305970663/9781305970663_smallCoverImage.gif)
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY