Monte Services, Inc. is trying to establish the
Actual time spent on the oil change | 1.0 hour |
Hourly wage rate | $12 |
Payroll taxes | 10% of wage rate |
Setup and downtime | 20% of actual labor time |
Cleanup and rest periods | 30% of actual labor time |
25% of wage rate |
Instructions
(a) Determine the standard direct labor hours per oil change.
(b) Determine the standard direct labor hourly rate.
(c) Determine the standard direct labor cost per oil change.
(d) If an oil change took 1.6 hours at the standard hourly rate, what was the direct labor quantity variance?
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Chapter 11 Solutions
Managerial Accounting, Binder Ready Version: Tools for Business Decision Making
Additional Business Textbook Solutions
Principles of Accounting Volume 1
Horngren's Financial & Managerial Accounting, The Financial Chapters (6th Edition)
Managerial Accounting (4th Edition)
Managerial Accounting (5th Edition)
Financial Accounting (11th Edition)
Principles of Accounting Volume 2
- Engines Done Right Co. is trying to establish the standard labor cost of a typical engine tune-up. The following data have been collected from time and motion studies conducted over the past month. Actual time spent on the tune-up 1.0 hour Hourly wage rate $16 Payroll taxes 10% of wage rate Setup and downtime 10% of actual labor time Cleanup and rest periods 20% of actual labor time Fringe benefits 25% of wage rate Determine the standard direct labor hours per tune-up, the standard direct labor hourly rate, the standard direct labor cost per tune-up (standard direct labor cost per oil change).arrow_forwardEngines Done Right Co. is trying to establish the standard labor cost of a typical engine tune-up. The following data have been collected from time and motion studies conducted over the past month. Actual time spent on the tune-up 1.0 hour Hourly wage rate $16 Payroll taxes 10% of wage rate Setup and downtime 10% of actual labor time Cleanup and rest periods 20% of actual labor time Fringe benefits 25% of wage rate If a tune-up took 1.5 hours at the standard hourly rate, what was the direct labor quantity variance? Identify whether the variance is favorite or unfavorite?arrow_forwardTexoma Trucking Company is exploring different prediction models that can be used to forecast indirect labor costs. One independent variable under consideration is machine hours. Following are matching observations on indirect labor costs and machine hours for the past six months: Machine hours Indirect labor costs $20,000 $24,000 $17,000 $22,000 $13,000 $14,000 Month 1 300 2 400 3 240 4 370 5 200 6 225 Using HIGH-LOW method, determine the following: 1. The total flexible cost formula? 2. The total indirect cost labor of Texoma Trucking Company if on the 10th month, they incurred 390 machine hours from operation.arrow_forward
- If a factory operates at 100% of capacity one month, 90% of capacity the next month, and 105% of capacity the next month, will a different cost per unit be charged to the work-in-process account each month for factory overhead assuming that a predetermined annual overhead rate is used?arrow_forwardIdentify cost graphs The following cost graphs illustrate various types of cost behavior: For each of the following costs, identify the cost graph that best illustrates its cost behavior as the number of units produced increases: A. Total direct materials cost B. Electricity costs of 1,000 per month plus 0.10 per kilowatt-hour C. Per-unit cost of straight-line depreciation on factory equipment D. Salary of quality control supervisor, 20,000 per month E. Per-unit direct labor costarrow_forwardThe expected costs for the Maintenance Department of Stazler, Inc., for the coming year include: Fixed costs (salaries, tools): 64,900 per year Variable costs (supplies): 1.35 per maintenance hour Estimated usage by: Actual usage by: Required: 1. Calculate a single charging rate for the Maintenance Department. 2. Use this rate to assign the costs of the Maintenance Department to the user departments based on actual usage. Calculate the total amount charged for maintenance for the year. 3. What if the Assembly Department used 4,000 maintenance hours in the year? How much would have been charged out to the three departments?arrow_forward
- SmokeCity, Inc., manufactures barbeque smokers. Based on past experience, SmokeCity has found that its total annual overhead costs can be represented by the following formula: Overhead cost = 543,000 + 1.34X, where X equals number of smokers. Last year, SmokeCity produced 20,000 smokers. Actual overhead costs for the year were as expected. Required: 1. What is the driver for the overhead activity? 2. What is the total overhead cost incurred by SmokeCity last year? 3. What is the total fixed overhead cost incurred by SmokeCity last year? 4. What is the total variable overhead cost incurred by SmokeCity last year? 5. What is the overhead cost per unit produced? 6. What is the fixed overhead cost per unit? 7. What is the variable overhead cost per unit? 8. Recalculate Requirements 5, 6, and 7 for the following levels of production: (a) 19,500 units and (b) 21,600 units. (Round your answers to the nearest cent.) Explain this outcome.arrow_forwardPlease use the information from this problem for these calculations. After grouping cost pools and estimating overhead and activities, Box Springs determined these rates: It estimates there will be five orders in the next year, and those jobs will involve: What is the total cost of the jobs?arrow_forwardBobcat uses a traditional cost system and estimates next years overhead will be $800.000, as driven by the estimated 25,000 direct labor hours. It manufactures three products and estimates the following costs: If the labor rate is $30 per hour, what is the per-unit cost of each product?arrow_forward
- Please use the information from this problem for these calculations. After grouping cost pools and estimating overhead and activities, Box Springs determined these rates: Box Springs estimates there will be four orders in the next year, and those jobs will involve: What is the total cost of the jobs?arrow_forwardAssume the following: Estimated fixed manufacturing overhead for the coming period of $202,000 Estimated variable manufacturing overhead of $2.00 per direct labor hour Actual manufacturing overhead for the period of $320,000 Actual direct labor - hours worked of 54,000 hours Estimated direct labor - hours to be worked in the coming period of 55,000 hours. The amount of overhead applied to production during the period is closest to: Note: Round your intermediate value of "Predetermined overhead rate" to two decimal placesarrow_forwardPyramid Company expects to incur $3,000,000 in manufacturing overhead costs this year. During the year, it expects to use 40,000 direct labor hours at a cost of $600,000 and 80,000 machine hours. Required: a. Prepare a predetermined overhead rate based on direct labor hours, direct labor cost, and machine hours. b. Why might Pyramid Company prefer to use machine hours to allocate manufacturing overhead? c. Using each of the predetermined overhead rates calculated in part a and the data that follows for job 128, determine the cost of job 128arrow_forward
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegePrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337902663/9781337902663_smallCoverImage.jpg)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337912020/9781337912020_smallCoverImage.jpg)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305970663/9781305970663_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305087408/9781305087408_smallCoverImage.gif)