Chapter 12, Problem 12.20P

1a.

To determine

Introduction: Throughput time is the total time required for the completion of a process. For instance, the time required to manufacture machinery from the beginning till its end is the throughput time. The throughput time comprises process time, inspection time, move time, and queue time. Wait time is not a part of throughput time.

The throughput time for each month.

2.

To determine

Introduction: Throughput time, manufacturing cycle efficiency, and delivery cycle time are all such indicators that help in analyzing the company’s performance. Throughput time is the elapsed time from the time of inception of the production process till the goods are dispatched to the customer, manufacturing cycle refers to the amount of time in the manufacturing process that is spent on enriching or improving the product, and delivery cycle time is the total time required to produce as well as deliver the product to the customers.

To evaluate: The company’s performance over the last four months.

3a.

To determine

Introduction: Throughput time is the elapsed time from the time of inception of the production process till the goods are dispatched to the customer. The manufacturing cycle refers to the amount of time in the manufacturing process that is spent on enriching or improving the product.

The throughput time and MCE for Month 5.

Blurred answer
Students have asked these similar questions
D: Measures of Internal Business Process PerformanceDataSpan, Inc., automated its plant at the start of the current year and installed a flexiblemanufacturing system. The company is also evaluating its suppliers and moving toward LeanProduction. Many adjustment problems have been encountered, including problems relating toperformance measurement. After much study, the company has decided to use the performancemeasures below, and it has gathered data relating to these measures for the first four months ofoperations.Month1 2 3 4Throughput time (days) ? ? ? ?Delivery cycle time (days) ? ? ? ?Manufacturing cycle efficiency (MCE) ? ? ? ?Percentage of on-time deliveries 91% 86% 82% 78%Total sales (units) 3460 3312 3143 3025Management has asked for your help in computing throughput time, delivery cycle time, and MCE.The following average times have been logged over the last four months: Average per Month (in days)1 2 3 4Move time per unit 0.7 0.5 0.6 0.6Process time per unit 2.8 2.7 2.6…
DataSpan, Incorporated, automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations.     Month 1 2 3 4 Throughput time (days) ? ? ? ? Delivery cycle time (days) ? ? ? ? Manufacturing cycle efficiency (MCE) ? ? ? ? Percentage of on-time deliveries 82% 77% 74% 71% Total sales (units) 3830 3667 3479 3347   Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months:     Average per Month (in days) 1 2 3 4 Move time per unit 0.8 0.5 0.6 0.6 Process time per unit 2.3 2.2…
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 4 Throughput time (days) Delivery cycle time (days) Manufacturing cycle efficiency (MCE) Percentage of on-time deliveries Total sales (units) ? ? ? 89% 84% 81% 78% 3880 3714 3524 3390 Management has asked for your help in computing throughput time, delivery cycle time, and MCE. The following average times have been logged over the last four months: Average per Month (in days) 2 3 4 Move time per unit Process time per unit Wait time per order before start of production Queue time per unit Inspection time per…
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Text book image
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
alue Chain Analysis EXPLAINED | B2U | Business To You; Author: Business To You;https://www.youtube.com/watch?v=SI5lYaZaUlg;License: Standard Youtube License