The trip distribution using the average growth factor method.
Answer to Problem 14P
The trip distribution has been developed using the average growth factor method.
Explanation of Solution
Given:
For Zone
Present total observed trip ends is
Zonal growth rate is
For Zone
Present total observed trip ends is
Zonal growth rate is
For Zone
Present total observed trip ends is
Zonal growth rate is
For Zone
Present total observed trip ends is
Zonal growth rate is
Formula used:
Estimated growth total is given by,
The number of trips estimated from zone
Here,
The new growth factor is given as,
Calculation:
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The data of
Zones | |||
Table (1)
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The calculated trips from zone
Zones | |
Table (2)
The
The
Substitute
The
The
Substitute
The
The
Substitute
The
The
Substitute
The remaining movement between zones, new present total and new growth factor for zone s
Zones | New Present total | New Growth factor |
Table (3)
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The estimated growth total for zone
Substitute
The data of
Zones | |||
Table (4)
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The number of trips estimated from zone
Substitute
The calculated trips from zone
Zones | |
Table (5)
The
The
Substitute
The
The
Substitute
The
The
Substitute
The
The
Substitute
The remaining movement between zones, new present total and new growth factor for zone
Zones | New Present total | New Growth factor |
| ||
Table (6)
Conclusion:
The trip distribution has been done using the average growth factor method.
Want to see more full solutions like this?
Chapter 12 Solutions
Traffic And Highway Engineering
- QI) For the project data shown in table below. Find the probability of completing the project in 34 weeks. Activity 3-6 3-7 7-9 8-10 9-10 1-3 2 5 4-5 5-7 6-7 7-8 2 4 7 1-2 1-4 2-6 3-5 2 2 10 4 4 8 2 6. 8. 2 7 10 M 11 11 10 4 6 8 10 8 13 10 6. 14 4 olooarrow_forwardGiven the list of construction activities for your newly-acquired residential project. Determine the critical path for this project. Activity Depends on Duration (weeks) D A 5 B A 3 G E 3 4 E В. С 2 G. H, I 2 A 4 F C. D 5 E. F A none The critical path for this project is Note: Use this format in your final answer/s, such as if your answer is S, T, U, V, W, then type your final answer as S-T-U-V-Warrow_forwardWhat is the probability of being exceeded in 50 years when the return period for the building is 700 years? Use Poisson's Distributionarrow_forward
- What is the probability of completion of the project in 17.5 months? * Actv. Duration (month) a m 5-10 4 5-15 4 10-20 4 4 7 10-25 10-30 4 5 6. 15-25 3.5 5.5 7.5 15-30 3 20-35 9 12 25-35 5 8. 30-35arrow_forwardA particular project is scheduled to complete in Week 50 at a budgeted cost of $150,000. As of Week 30, an earned value chart is prepared to present the project progress as below: Status Date 160- 140 PV 120 100 80 AC 60 40- 20 10 15 20 25 30 35 40 45 50 Weeks 1. Calculate schedule, cost and time variances, as well as schedule and cost performance indices for Week 30. Then use this information to comment on the project progress at Week 30 (status date). 2. Based on the performance at Week 30, estimate the final project cost (EAC). Will the final project cost be higher or lower than the budgeted cost, and by how much? Also estimate the revised project completion date. Will the project complete sooner or later than the planned completion date, and by how many weeks? 000.Sarrow_forwardDraw the node diagram and perform the CPM computations for the schedule shown. Tabulate ES, EF, LS, LF, TT, and LF. Identify the critical path and the total duration of the project. Activity Duration IPA Lag ES EF LS LF TF FF A B A 4 A 3 D A E B F 7 В G 6 H 8 D 4 3 7 E, G F 2 K 4 F, G, H L 1 H 3 M K, L 2.arrow_forward
- Payback Period Method and Benefit-Cost Ratio Methodarrow_forwardQUESTION 6. The activities involved in the construction of a new shopping mall are given in Table Q6. One resource type will be used during the contract. Determine minimum level of the resource required to complete the project. Table Q6 Activity Duration Predecessors Resource (units/week) (Weeks) A B 2 2 2 1 2 3 1 5 3 1 E 2 6. 2 F G 3 H 6. 4 4 4 5, 6 6, 7 2, 8 2, 8, 9 10, 11, 12, 13 4 2 K 2 L. 2.arrow_forwardThe activity details of a project are given below: Activity Depends P Q R S T U V A 68 B The estimated minimum time (in days) for the completion of the project will be 51 C 85 on D 40 P Q,T R P Q,T U Duration (in days) 6 15 12 16 10 14 16arrow_forward
- 1- A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes.($000)arrow_forwardThe following eight activities constitute an overall bar chart portrayal of a 4-month project. After 1.5 months, Activities A, B, D, and half of E were completed, for a cost of $8,000. For this project, using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead or behind schedule.arrow_forward10. Assume that the duration of some activities is not known with certainty. The estimates of these activities are shown below. Activity A C D G H Optimistic Q 8 3 10 13 8 Most Likely 10 5 12 15 10 POM a. What is the project's expected completion time and its variance? b. What is the probability that the project will be completed in 61 days or more? c. What is the probability that the project will be completed in no more than 54 days? c. If the company wants a 94% probability of completing the project on time, state the latest time each activity should have started and completed. Pessimistic 5+ 12 7 14 17 12arrow_forward
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning