Traffic And Highway Engineering
5th Edition
ISBN: 9781133605157
Author: Garber, Nicholas J., Hoel, Lester A.
Publisher: Cengage Learning,
expand_more
expand_more
format_list_bulleted
Question
Chapter 12, Problem 5P
To determine
The productions and attractions generated in the work and residence zones for a person travelling to work in the morning and returning home in the evening.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
develop a WBS for your assumed building project. Mention duration for each activity of your project and total completion time.
A particular project is scheduled to complete in Week 50 at a budgeted cost of $150,000. As of Week 30, an earned value chart is prepared to
present the project progress as below:
Status Date
160-
140
PV
120
100
80
AC
60
40-
20
10
15
20
25
30
35
40
45
50
Weeks
1. Calculate schedule, cost and time variances, as well as schedule and cost performance indices for Week 30. Then use this information
to comment on the project progress at Week 30 (status date).
2. Based on the performance at Week 30, estimate the final project cost (EAC). Will the final project cost be higher or lower than the
budgeted cost, and by how much? Also estimate the revised project completion date. Will the project complete sooner or later than the
planned completion date, and by how many weeks?
000.S
Draw manually a WBS for your assumed building project. Mention duration for each activity of your project and total completion time.
Chapter 12 Solutions
Traffic And Highway Engineering
Ch. 12 - Prob. 1PCh. 12 - Prob. 2PCh. 12 - Prob. 3PCh. 12 - Prob. 4PCh. 12 - Prob. 5PCh. 12 - Prob. 6PCh. 12 - Prob. 7PCh. 12 - Prob. 8PCh. 12 - Prob. 9PCh. 12 - Given a table with production and attraction data,...
Ch. 12 - Given a table with production and attraction data,...Ch. 12 - Prob. 12PCh. 12 - Prob. 13PCh. 12 - Prob. 14PCh. 12 - Prob. 15PCh. 12 - Prob. 16PCh. 12 - Prob. 17PCh. 12 - Prob. 18PCh. 12 - Prob. 19PCh. 12 - Prob. 20PCh. 12 - Prob. 21PCh. 12 - Prob. 22PCh. 12 - Prob. 23PCh. 12 - Prob. 24PCh. 12 - Prob. 25PCh. 12 - Prob. 26PCh. 12 - Prob. 27PCh. 12 - Prob. 28P
Knowledge Booster
Similar questions
- 4. Using the following information, perform the following: a. Network diagram b. Determine which activities are on the critical path c. Compute the length of the critical path Activity Estimated time (days) 1-2 5 2-3 6 2-4 4. 3-6 10 6-7 4-5 5 4-7 16 5-7 10 Answer: 3.arrow_forwardQ/Find the completion time and critical path for a project with following: 5 F K 5 7 15 9 3. 4 M 10 A E 6. J 11 6. E.S X L.S E.S Y L.S Overlapping between E.F D LF finish of X and start of Y EF | D LF Duration (weeks) 2.arrow_forwardActivity durations for a 5km piping project are listed below. The minimum time buffer between activities is 5 days. Using Line of Balance technique, calculate the start and finish time of each activity and the project completion time. A B C D E F Activity Cleaning and Surveying Trenching Placing bedding Laying pipe and Connecting joints Welding Inspection & Testing Backfill and Grading Activity duration (days) 20 80 40 50 15 50arrow_forward
- Engineering Management ,i need solutions in 10 minutes please. MCQ/For the construction project represented by the activity network as shown below. Find one of the critical paths CP from the choices below. A-1-3-6-8-9 B-1-2-4-6-9 C-1-2-4-6-7-9 D-1-2-4-6-8-9 E-1-3-4-6-9 F-1-3-4-5-7-9arrow_forwardQ3/ A construction project have the following data in the table below:- Activity Duration (weeks) Activity total cost ($) 400 Critical Activity Dependency A ---- В 5 350 ---- C 3 A 300 D 3 В 450 E 12 960 ---- F 15 A, B 600 Total project cost = E Activity total cost ($) 3060 %3D Required:- Calculate the contract value, the monthly value of the planned work to be completed (Budget value) and the monthly amounts (payments) that expected to be received (Expected payments) If the ratio of profit that the contractor desires is (15%) and the contract for this type of project provides for the deduction of the amount of 5% (retention rate) from value of monthly payments to pay 50 of the total deductions upon completion of the work and pay the remaining 50 after the end of the maintenance period of 3 months and the first monthly payment received after one month from the start of the project, Draw the curves of the value of the planned work done and the amounts expected to be received.arrow_forwardShow work for both questions.arrow_forward
- ). The network and durations given below show the normal schedule for a project, and the table given below summarizes the time-cost information for the activities, the owner wants to finish the project in 110 days, so find the minimum possible cost for the project to finish in 110 days AND 20 A B C D (19) E F 9. Activity (days) 120 20 40 30 50 60 Normal du 120 60 Crash (days) 100 15 30 20 40 45 30 on 4 50 Norma Cost 12000 1800 16000 1400 3600 13500 Cost 14000 2800 22000 2000 4800 18000arrow_forwardWhat is the project completion time? a. 14 days b. 12 days c. 15 days d. 13 days When will fund raising activity end? a. April 19 b. April 16 c. April 15 d. April 18 When will fund raising activity start? a. April 15 b. April 13 c. April 14 d. April 18arrow_forwardFor the information of project shown in table below: 1. Draw the network diagram by using AOA method. 2. Prepare a table shown ES, EF, LS, LF, TF. 3. Identify Critical Path (C.P) and determine the total completion time. Activity Duration (week) Preceded by A C E G 2 1 2 4 2 3 1 B C, D E F, Garrow_forward
- The expected finishing date for the project with 64% probability. * Actv. Duration (month) a b 5-10 4 5-15 2 4 10-20 4 4 7 10-25 10-30 4 5 15-25 3.5 5.5 7.5 15-30 3 6. 20-35 9 12 25-35 5 30-35arrow_forwardQ3 / Find the critical path and (Es, EF, Lf, TF) for the activities of the project and determine the total project duration if you have the following information )5٠ درجة( Activity Duration 1-2 2-3 4 2-4 2-5 6. 3-5 3-6 4-5 4-7 3 5-8 7 6-8 6-9 7-8 7-10 5 8-10 9-10 4arrow_forwardThe required total period for project completion and the critical path is determined after calculating the values in the empty boxes as in the symbol attached to the drawingarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning