Chapter 12, Problem 1BE
a)
To determine
Lead Time: Lead time is the time consumed for the creation of a product. It refers to the time period between the time the order is placed and the product is completed. Lesser lead time creates a more competitive edge for the company.
Lead Time = Wait time + Process time + Queue time + Move time + Inspection Time
To Compute: The value added, non value added and lead time of this process.
b)
To determine
To Compute: The value added ratio (rounded to one place).
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
Lead Time
Pockets Inc. manufactures cargo pants in the cutting and sewing process. Cargo pants are manufactured in batches of 30. The cutting time is
4 minutes per unit. The sewing time is 12 minutes per unit. It takes 20 minutes to move a batch of jeans from cutting to sewing.
a. Compute the value-added, non-value-added, and total lead time of this process.
Value-added lead time
Non-value-added lead time
Total lead time
b. Compute the value-added ratio. Round to one decimal place.
%
minutes
minutes
minutes
Pockets Inc. manufactures cargo pants in the cutting and sewing process. Cargo pants are manufactured in batches of 30. The cutting time is 4 minutes per unit. The sewing time is 12 minutes per unit. It takes 20 minutes to move a batch of jeans from cutting to sewing.
a. Compute the value-added, non-value-added, and total lead time of this process.
Line Item Description
Lead Time
Value-added lead time
fill in the blank 1 minutes
Non-value-added lead time
fill in the blank 2 minutes
Total lead time
fill in the blank 3 minutes
b. Compute the value-added ratio. Round to one decimal place.fill in the blank 1 of 1%
8. Rough Riders Inc. manufactures jeans in the cutting and sewing process. Jeans are manufactured in 50-jean batch sizes. The cutting time is 6 minutes and the sewing time is 15 minutes per jean. It takes 5 minutes to move a batch of jeans from cutting to sewing.
(a) Compute the value-added, non-value-added, and total lead time of this process.
(b) Compute the value-added ratio. Round to one decimal place.
Chapter 12 Solutions
Bundle: Managerial Accounting, Loose-leaf Version, 14th - Book Only
Ch. 12 - What is the benefit of the lean philosophy?Ch. 12 - Prob. 2DQCh. 12 - Prob. 3DQCh. 12 - Prob. 4DQCh. 12 - Prob. 5DQCh. 12 - Why would a lean manufacturer strive to produce...Ch. 12 - Prob. 7DQCh. 12 - Prob. 8DQCh. 12 - Prob. 9DQCh. 12 - Prob. 10DQ
Ch. 12 - Prob. 11DQCh. 12 - Prob. 12DQCh. 12 - Prob. 13DQCh. 12 - Prob. 1BECh. 12 - Prob. 2BECh. 12 - Prob. 3BECh. 12 - Prob. 4BECh. 12 - Prob. 5BECh. 12 - Prob. 1ECh. 12 - Prob. 2ECh. 12 - Prob. 3ECh. 12 - Prob. 4ECh. 12 - Prob. 5ECh. 12 - Prob. 6ECh. 12 - Calculate lead time Williams Optical Inc. is...Ch. 12 - Prob. 8ECh. 12 - Prob. 9ECh. 12 - Prob. 10ECh. 12 - Prob. 11ECh. 12 - Prob. 12ECh. 12 - Lean accounting Modern Lighting Inc. manufactures...Ch. 12 - Prob. 14ECh. 12 - Prob. 15ECh. 12 - Prob. 16ECh. 12 - Prob. 17ECh. 12 - Prob. 18ECh. 12 - Process activity analysis The Brite Beverage...Ch. 12 - Prob. 20ECh. 12 - Prob. 21ECh. 12 - Prob. 1PACh. 12 - Prob. 2PACh. 12 - Lean accounting Dashboard Inc. manufactures and...Ch. 12 - Prob. 4PACh. 12 - Prob. 1PBCh. 12 - Lead time Master Chef Appliance Company...Ch. 12 - Lean accounting Com-Tel Inc. manufactures and...Ch. 12 - Pareto chart and cost of quality report for a...Ch. 12 - Prob. 1ADMCh. 12 - Prob. 2ADMCh. 12 - Prob. 3ADMCh. 12 - Ethics in Action In August, Lannister Company...Ch. 12 - Prob. 3TIF
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Lead Time Rough Riders Inc. manufactures jeans in the cutting and sewing process. Jeans are manufactured in 50-jean batch sizes. The cutting time is 6 minutes per jean. The sewing time is 15 minutes per jean. It takes 5 minutes to move a batch of jeans from cutting to sewing. a. Compute the value-added, non-value-added, and total lead time of this process. Value-added lead time minutes Non-value-added lead time minutes Total lead time minutes b. Compute the value-added ratio. Round to one decimal place. %arrow_forwardLead Time Blues Inc. manufactures jeans in the cutting and sewing process. Jeans are manufactured in 40-jean batch sizes. The cutting time is 5 minutes per jean. The sewing time is 20 minutes per jean. It takes 2 minutes to move a batch of jeans from cutting to sewing. a. Compute the value-added, non-value-added, and total lead time of this process. Value-added lead time ? minutes Non-value-added lead time ? minutes Total lead time ? minutes b. Compute the value-added ratio. Round to one decimal place.fill in the blank 4 %arrow_forward1. ABC Co. manufactures desks in the finishing and assembly process. Desks are manufactured in 20 unit batches. The finishing time is 12 minutes and the assembly time is 8 minutes per desk. It takes 20 minutes to move a batch of desks from finishing to assembly. (a) Compute the value added, non-value added, and total lead time of this process. (b) Compute the value-added ratio (round to one decimal place if necessary). (c) A study was conducted resulting in the following changes: Desks made in 30 unit batches Finishing time reduced to 8 minutes Move time reduced to 16 minutes Compute the total lead time and value added ratio after the process changes: 2. Johnny Co. operates under the lean philosophy. As a result, it has a production cell for its power drills. The…arrow_forward
- MCE Craig, Inc., has provided the following information for one of its products for each hour of production: Actual velocity: 200 units (per hour) Move time: 11 minutes Inspection time: 12 minutes Rework time: 12 minutes 1. MCE is 0.42 2. What is the theoretical cycle time? Calculate MCE using actual and theoretical cycle times. If required, round your answers to two decimal places. Theoretical cycle time fill in the blank minutes Actual cycle time 0.3 minutes MCE fill in the blankarrow_forwardEyring Manufacturing produces a component used in its production of washing machines. The time to set up and produce a batch of the components is two days. The average daily usage is 800 components, and the maximum daily usage is 875 components. Required: Compute the reorder point assuming that safety stock is carried by Eyring Manufacturing. How much safety stock is carried by Eyring?arrow_forwardBest Ink produces printers for personal computers. The following information is available for production of a recent order of 500 printers. Process time 16.0 hours Inspection time 3.5 hours Move time 9.0 hours Wait time 21.5 hours 1. Compute the company’s manufacturing cycle time. 2. Compute the company’s manufacturing cycle efficiency. 3. Assume the company wishes to increase its manufacturing cycle efficiency to 0.80. If process time is unchanged, what is the maximum number of hours of non-value-added time the company can have and meet this goal?arrow_forward
- Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 5 minutes in milling and 10 minutes in finishing. The move time between the two operations for a complete batch is 11 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 6 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Traditional Philosophy Lean Manufacturing Philosophy Value-added time ? min ? min Non-value-added time ? min ? min Total lead time ? min ? min Value-added ratio…arrow_forwardNavern Coporation manufactures and sells custom home elevators. From the time an order is placed until the time the elevator is installed in the customer's home averages 44 days. This 44 days is spent as follows: Wait time 12 days Inspection time Process time Move time Queue time 12 days 5 days 6 days 9 days What is Navern's manufacturing cycle efficiency (MCE) for its elevators? Multiple Cholce 38.6% 15.6% 61.4% 591% 65°F Cloudy search DELLarrow_forwardCharlotte Company produces folding chairs. It takes the company 18,000 hours to produce 90,000 chairs. Required: A. What is the velocity?fill in the blank 1 units per hour B. What is the cycle time in hours? Round your answer to one decimal place.fill in the blank 2 hoursarrow_forward
- Compute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 90 parts. A part requires 5 minutes in milling and 9 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 5 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Traditional Philosophy Lean Manufacturing Philosophy Value-added time 14 V min 14 V min Non-value-added time 1,246 X min 46 x min Total lead time 1,260 X min 70 V min…arrow_forwardCompute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 70 parts. A part requires 4 minutes in milling and 9 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Value-added time Non-value-added time Total lead time Value-added ratio (as a percent) Traditional Philosophy Lean Manufacturing Philosophy min min min % min min min %arrow_forwardCompute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 70 parts. A part requires 3 minutes in milling and 9 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Value-added time Non-value-added time Total lead time Value-added ratio (as a percent) Traditional Philosophy Lean Manufacturing Philosoph min min 0000 min min % min min %arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337912020/9781337912020_smallCoverImage.jpg)
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305970663/9781305970663_smallCoverImage.gif)
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
alue Chain Analysis EXPLAINED | B2U | Business To You; Author: Business To You;https://www.youtube.com/watch?v=SI5lYaZaUlg;License: Standard Youtube License