• 13.14 Jerusalem Medical Ltd., an Israeli producer of portable kidney dialysis units and other medical products, develops a 4-month aggregate plan. Demand and capacity (in units) are
The cost of producing each dialysis unit is $985 on regular time, $1,310 on overtime, and $1,500 on a subcontract. Inventory carrying cost is $100 per unit per month. There is to be no beginning or ending inventory in stock and backorders are not permitted. Set up a production plan that minimizes cost using the transportation method.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Q.14
At M3 Marketing a new marketing campaign development project for a client begins with two activities ideation and budgeting/contracting. Ideation, or coming up with ideas for the campaign, occurs in parallel with (i.e., at the same time as,) the budgeting/contracting work which determines the costs and terms of the relationship. These activities take four and three weeks, respectively.
Once ideation is complete, advertising content drafting begins and lasts two weeks. When the budget is set and the ad drafting is complete, the activity to determine the advertising channels can begin. Determining the ad channels takes three weeks.
When ad drafting is complete and the advertising channels are determined, two activities can start. First, final campaign collateral can be developed over the next six weeks. The second activity is rollout planning, which requires four weeks.
After collateral development and rollout planning are finished, the advertising campaign rollout is executed over…
Cost Classification Discussion Question
The table below shows monthly data collected on production costs and on the number of units produced over a twelve month period.
Month
Total Production Costs
Level of Activity (Units Produced)
July
$230,000
3,500
August
250,000
3,750
September
260,000
3,800
October
220,000
3,400
November
340,000
5,800
December
330,000
5,500
January
200,000
2,900
February
210,000
3,300
March
240,000
3,600
April
380,000
5,900
May
350,000
5,600
June
290,000
5,000
Prepare the scatter diagram and insert the trendline or line of best-fit. Use a scale of 2 cm to represent 1,000 units on the x-axis & 2 cm to represent $50,000 on the yaxis.
Using the line of best-fit, determine the company’s fixed cost per month and the variable cost per unit. (Use 0 & 5,000 units.) I'd like to see a breakdown please.
Which of the two methods appear more appropriate?…
Discussion Question: Discuss the requirements for strategic management of IS/IT. What are some challenges to implementing these requirements?
Chapter 13 Solutions
New Myomlab With Pearson Etext -- Access Card -- For Operations Management
Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Question: 7. What is level scheduling? What is the...Ch. 13 - Question: 8. Define mixed strategy. Why would a...Ch. 13 - Prob. 9DQCh. 13 - Prob. 10DQ
Ch. 13 - Question: 11. What is the relationship between the...Ch. 13 - Prob. 12DQCh. 13 - Question: 13. What are major limitations of using...Ch. 13 - Prob. 14DQCh. 13 - Question: 13.1 Prepare a graph of the monthly...Ch. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Prob. 7PCh. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Question: 13.10 The SOP team (see Problem 13.9)...Ch. 13 - Prob. 11PCh. 13 - Prob. 12PCh. 13 - Prob. 13PCh. 13 - Question: 13.14 Jerusalem Medical Ltd., an...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Question: 13.18 Jose Martinez of El Paso has...Ch. 13 - Prob. 19PCh. 13 - Prob. 20PCh. 13 - Prob. 21PCh. 13 - Prob. 22PCh. 13 - Prob. 1CSCh. 13 - Prob. 2CSCh. 13 - Prob. 1VCCh. 13 - Prob. 2VCCh. 13 - Question: 3. What are some concerns the team needs...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- QUESTION: Present a closing statement explaining the benefits to Stayer of applying activity-based costing to its R&D activity for both in-house and outside charging purposes.arrow_forwardQ2) 3. What is long range plan?arrow_forwardQuestion 1: Kimji Company is engaged in the business of export of garments. In the past, the performance of the company had been up to the expectations. In line with the latest technology, the company decided to upgrade its machinery. For this, the Finance Manager, Abdullah estimated the amount of funds required and the timings. This will help the company in linking the investment and the financing decisions on a continuous basis. Abdullah therefore, began with the preparation of a sales forecast for the next four years. He collected the relevant data about the profit estimates in the coming years. By doing this, he wanted to be sure about the availability of funds from the internal sources of the business. For the remaining funds he is trying to find out alternative sources from outside like loan from bank etc Answer the following question based on the case study in 500-1000 words. a. What is the role of Financial Management and what are the financial decisions Involved in the above…arrow_forward
- Question 1At Tropico, the activities required to service a car at a dealer can be viewed as a mini-project summarised in the following table: The variability in times required to perform each activity is due to the different types, sizes, and conditions of the cars to be serviced. Round off to two decimal places were fractional.A. Draw the activity network diagram for this problem (either AON or AOA) (5 marks)B. Determine the Expected Time and Variance for each activity. (4 marks)C. Show the activity schedule (ES, EF, LS, and LF) as well as slack times. (5 marks)D. Use the ES, EF, LS, and LF from your activity schedule or table to determine the critical path for the project. (2 marks)E. What are the expected time and the variance of the project? (2 marks)F. What is the probability the project will be finished within 10 minutes? (2 marks)arrow_forwardQUESTION THREEa) Zambia Breweries has a backlog of 250 crates of Fanta drinks at the end of December. The demand of Fanta drinks is expected to be 400 crates in January, 500 crates in February and 550 crates in March. Each worker can produce 50 crates of drinks per month with regular wage costing the company K10 000 per worker per month. Hiring cost has been calculated to be K25 000 per. Hiring cost has also been calculated to be K50 000 per worker. Backlog cost have been determined to cost the company K250 per worker. There are no cost associated with carrying the inventory. Develop a level of production plan (aggregate plan) and determine the cost. b) Explain why aggregate planning is necessary in production and operation management.c) Define the meaning and what happens at each of these aggregate capacity planning;i) Matching Demand approachii) Level Capacity approach.arrow_forwardQuestion The following describes the expenditure cycle for a hypothetical company. The company has a centralized computer system with terminals located in various departments. The terminals are networked to a computer application, and digital accounting records are hosted on a server in the data processing department. Each day, the computer in the data processing center scans the inventory records looking for items that must be replenished. For each item below its reorder point, the system creates a digital purchase order and prints two hard copies. A technician in the data center sends the purchase orders to the purchasing department clerk. Upon receipt of the purchase orders, the purchasing clerk reviews and signs them. He sends Copy 1 to the supplier and files Copy 2 in the purchases department. A few days later, the supplier ships the order and thegoods arrive at the receiving department. The receiving clerk reviews the digital purchase order from his terminal, inspects the…arrow_forward
- question: How much profit is added if you are given an additional 50 Yards of Material?arrow_forwardQuestion TwoNew Ndola Airport, also known as Copperbelt International Airport, is an airport construction project that upon completion, will replace the current Ndola Simon Mwansa Kapwepwe International Airport. The project will be located on a 2000ha site northwest of Ndola and is projected to cost USD522 million. The airport will initially be capable of handling two million passengers p/a. The airport's facilities will include three aerodromes, a hotel, cargo terminal and business complex, with a 3500m runway. The new airport will also include aircraft hangars, a fire station, restaurants, waiting rooms, laundry facilities, kiosks, a car park, and other facilities. ZACL said the new airport will be the only green field airport to be built in over 30 years.As a Contract Manager under a Project for a Government Agency to construct a New Ndola Airport, identify and discuss the types of Procurement methods that are available to use and the Government laws and Regulations that apply to…arrow_forwardQuestion 1 "Every organization can be viewed as a set of loosely coupled network activities from the acquisition of raw material to the PT (production and transportation) of intermediate and finished goods (FG) up until the transportation of FG directly to the customer or a retail outlet. It is inventory (including work in progress WIP) that makes it "loosely" coupled, where inventory is defined as the accumulation and storage of products to be consumed in the next step of the network." Source: Adapted from Fordyce (2020) Analyse the above statement and justify if you agree or disagree with the sentiment of the author. Substantiate your answer.arrow_forward
- Question-2- Hershey Chocolate Corporation was the first company that produced milk chocolate in America. With the passage to time, it focused only on chocolate production, and manufactured many innovative products. After the Second World War, it managed to export its products to 90 countries. In2006, its sales reached 5 billion dollars, and employed over 14,300 people. The objective of the project is to deploy an ERP system covering sales and procurement process. The following is the required schedule of the event. (Marks-10) Activity Duration- Weeks Immediate Predecessors A–Select consultant for selecting system 2 _____________ B–Meet with consultant to discuss ERP 4 A C–Meet with Board of Directors to explain proposal 1 A D–Develop request for proposals to give to vendors 3 B,C E–Obtain vendor proposals 4 D F–Develop organization business cases including training 8 E G–Present business cases to Board of Directors 1…arrow_forwardQUESTION TWO A property development company is planning to build a block of student apartments in Lusaka’s Mass Media area. The company is yet to decide what size of block to build: a small, medium, or large. The payoffs of each size will depend on the demand for student accommodation in the area, which could be low, medium, high. The Developer estimates a 25%, 35%, and 40% chance of low, medium, and high demand, respectively. Below is a payoffs matrix (in K’000) showing the annual payoffs for the decision problem. Size of Block Market Demand Low Medium High Small 400 400 400 Medium 200 500 500 Large -400 300 800 Required: Identify the decision alternatives and uncertain conditions surrounding them? What is the optimal decision if the Developer is conservative? What is the optimal decision if the Developer is a risk taker? What is the optimal decision if the Developer wishes to minimize the Expected Opportunity Loss on the decision to…arrow_forwardWhat is graphical method in aggregate output planning?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY