You are expected to have the gift bags in Problem 14.1 ready at 5 P.M. However, you need to personalize the items (monogrammed pens, note pads, literature from the printer, etc.). The lead time is 1 hour to assemble 200 Js once the other items are prepared. The other items will take a while as well. Given the volunteers you have, the other time estimates are item K (2 hours), item L (1 hour), and item M (4 hours). Develop a time-phased assembly plan to prepare the gift bags.
• 14.1 You have developed the following simple product structure of items needed for your gift bag for a rush party for prospective pledges in your organization. You
Want to see the full answer?
Check out a sample textbook solutionChapter 14 Solutions
Operations Management
- Product Z is made from three units of A, two of B, and four of C. A, in turn, is made of one unit of C and five of D. A customer order was received for 200 units of Z in Week 8. (Hint: You will need to use "low-level coding", i.e., pull each item to the lowest level it appears on the BOM.) Item Lot Size On Hand Lead Time Z LFL 30 3 A LFL 40 1 B LFL 100 4 C 1000 50 3 D 500 2000 3 a. Show the Bill of Materials b. Develop MRP schedules showing gross/net requirements and planned order releases/receipts for each item.arrow_forwardConsider the following product structure (bill of material). One hundred and fifty (150) units of Product A are needed in week 10. Assuming no on-hand inventory of A exists, explode the bill of material, and use the following information to construct a net requirements plan for all the items. You must use the template provided by the instructor and provide all the information needed on the template. There are no scheduled receipts for all the items. Item On-hand Inventory Lead time (weeks) A 0 2 B 20 2 C 10 1 D 0 3 E 5 1 F 10 3 Item: LT= 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirements Scheduled Receipts Projected on Hand Net Requirements…arrow_forwardKid’s World sells outdoor play equipment for children. Oneof its most popular items is a 5-foot by 7-foot wooden sand-box shown below. General assembly instructions follow.Assembly Instructions: The wood pieces for the sand-box are ordered precut and treated. Kid’s World sands thewood, drills several holes in each piece as required for as-sembly, and coats each piece with 2 ounces of water sealer.The sides are then assembled one corner at a time by at-taching a 1-foot wood strip cater-corner between a5-foot and 7-foot side. Four bolts are inserted through thepredrilled holes and secured with nuts. After the left andright corners of the sandbox have been assembled, the twopieces are joined in a similar manner to form the box as-sembly. A triangular-shaped wooden seat is attached toeach corner of the box assembly with four flat-headed nailsfor each seat. The sandbox is now complete.Construct a multilevel bill of material for the sandbox.arrow_forward
- What method is used in the MRP process to ensure that all of the needs for a specific item are measured at the same time?arrow_forwardBill of material (BOM) details all the sub-component, material, and parts used to make one product. There is a dinner party at your home of a few guests, and you are managing your kitchen. Develop a BOM of any main dish (main course) of your own choice in a tree format. (Hint: Select number of people that will be served with dinner and quantity of that main course to be prepared in appropriate units). Units: tea spoon, table spoon, a cup, grams etc.arrow_forwardBill of material (BOM) details all the sub-component, material, and parts used to make one product. There is a dinner party at your home of a few guests, and you are managing your kitchen. a) Develop a BOM of any main dish (main course) of your own choice in a tree format. (Hint: Select number of people that will be served with dinner and quantity of that main course to be prepared in appropriate units). Units: tea spoon, table spoon, a cup, grams etc. b) Let us assume that you are managing the complete food for dinner, and the food will be served at 8:00 PM sharp. You have decided to serve one main course item, as mentioned in the previous part (a), one sweet dish of your choice, and salad. Prepare a lead-time tree for your complete project and explain the total lead-time from preparing to serving (start to complete) the dinner for your guests. Secondly, what is the latest time you must start preparing your dinner?arrow_forward
- Bill of material (BOM) details all the sub-component, material, and parts used to make one product. There is a dinner party at your home of a few guests, and you are managing your kitchen. a) Develop a BOM of any main dish (main course) of your own choice in a tree format. (Hint: Select number of people that will be served with dinner and quantity of that main course to be prepared in appropriate units). Units: tea spoon, table spoon, a cup, grams etc. b) Let us assume that you are managing the complete food for dinner, and the food will be served at 8:00 PM sharp. You have decided to serve one main course item, as mentioned in the previous part (a), one sweet dish of your choice, and salad. Prepare a lead-time tree for your complete project and explain the total lead-time from preparing to serving (start to complete) the dinner for your guests. Secondly, what is the latest time you must start preparing your dinner? NOTE: USE MS WORD FOR MAKING TREE CHART. COPY PASTE WORK IS…arrow_forwardWhat kind of items can be recycled by the Material Recovery Facility (MRF)? What is the purpose of a MRF? How does it work- write the steps of the process from when it arrives at the MRF to the end where everything is in bails.arrow_forwardTed Short, manager of procurement at the Lake Luna Medical Center (LLMC), is starting a process to examine at the general process that is followed at his center for procurement of medical supplies at his facility. His first step is to develop a flowchart for the current process that employees at his center follow. He has asked you to draw that flowchart for him and make any obvious changes to shorten the process. Here are the key steps that are followed: The LLMC employee fills out a paper requisition and sends that to his department head for approval. The department secretary first examines the requisition to see if all needed information is present. If it is, then she sends to the department head for approval. If not, she returns to the employee for any needed corrections. The employee then returns the requisition to the department secretary for review again. Requisitions with the correct information are sent to the department head. The department head reviews the item to determine…arrow_forward
- If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed?arrow_forwardProduct M is made of two units of N and two of P. N is made of two units of R and four units of S. R is made of one unit of S and three units of T. P is made of two units of T and four units of U. a. Show the bill-of-materials (product structure tree). b. If 100 Ms are required, how many units of each component are needed? c. Show both a single-level parts list and an indented parts list.arrow_forwardProduct Name: SMARTPAK (Smart Backpack) Product Description: The SMARTPAK makes use of cutting-edge technology to give you several benefits. It is easier to use because it contains several space-saving features and useful functionality. In this section, we go through the product's physical, mechanical, and chemical qualities, as well as how it may be used as a consumer commodity and an industry input. Task: (estimate, assume, anything will do); this is just a proposal. Plant Size and Production Schedule: Indicate minimum and maximum rated capacity of production. The number of shifts perday, the number of operating days per yeararrow_forward