Question
Chapter 15, Problem 1CS
Summary Introduction
Case summary:
The case deals about the store that manufactures old Oregon tables. There are four employees (Person T, Person G, Person L, and Person C) who deal with the operations such as preparation, assembly, finishing, and packaging. Each one would deal with a specific operation. However, all the four are able to do all the four operations. Person R is hired to perform major duties and help when the employees are absent. The time taken by each employee to perform every task is as follows:
Preparation | Assembly | Finishing | Packaging | |
Person T | 100 | 60 | 90 | 25 |
Person G | 80 | 80 | 60 | 10 |
Person L | 110 | 90 | 80 | 10 |
Person C | 120 | 70 | 100 | 25 |
Person R | 110 | 80 | 100 | 10 |
To determine: The fastest way to manufacture the tables using original crew of four employees.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
QUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5
(ii) Illustrate the flow (throughput) times to complete the baking and decorating on atimeline chart.
QUESTION 5a. A Chef bakes and decorates cakes in a two-stage process. The cakes are baked and once cooledthey are then decorated based on the clients’ requirements. The Chef received seven orders forfully decorated cakes and has documented the orders with respective processing times for bakingand decorating, as shown in Table 7 that follows:.Table 7. Cake Job Orders received by the Chef with the respective processing times for Baking andDecoratingCake Job Order Baking Processing Time Decorating Processing TimeA 2 1B 8 5C 4 6D 9 7E 7 8F 9 6G 3 5
(i) Using Johnson’s Rule, determine the optimum sequence for processing the cake joborders through the baking and decorating stages.
Question 5The management of CDC Construction Pioneers have decided to build 900 new apartments in the Kasoa area due to the influx of immigrant workers into the country. Two Architectural Companies have provided building plans and technical schematics for the project. Management are happy with the proposals of both Standard apartment and Deluxe apartment. After investigating the steps involved in construction, management determined that each apartment complex built will require some resources. Management analysed each of the bids and concluded that if the plans of Standard apartment are built, it requires 0.7 days in foundation works, 0.5 days in the masonry, 1 day in finishing, and 0.1 days in painting works. Deluxe apartment will require 1 day in foundation works, 0.83 days in the masonry, 0.67 days in finishing, and 0.25 days in the painting works. Management estimate that, 630 days for foundation works, 600 days for masonry, 708 days for finishing and 135 days for 11painting works…
Chapter 15 Solutions
OPERATIONS MGMT(LOOSELEAF)W/MYOMLAB>IC
Ch. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - Prob. 3DQCh. 15 - Prob. 4DQCh. 15 - Prob. 5DQCh. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQCh. 15 - Prob. 10DQ
Ch. 15 - Prob. 11DQCh. 15 - Prob. 12DQCh. 15 - Prob. 13DQCh. 15 - Prob. 1PCh. 15 - Prob. 2PCh. 15 - Prob. 3PCh. 15 - Prob. 4PCh. 15 - Prob. 5PCh. 15 - Prob. 6PCh. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - Prob. 9PCh. 15 - Prob. 10PCh. 15 - Prob. 15PCh. 15 - Prob. 16PCh. 15 - Prob. 17PCh. 15 - Prob. 18PCh. 15 - Prob. 19PCh. 15 - Prob. 20PCh. 15 - Prob. 21PCh. 15 - Prob. 22PCh. 15 - Prob. 23PCh. 15 - Prob. 26PCh. 15 - Prob. 27PCh. 15 - Prob. 1CSCh. 15 - Prob. 2CSCh. 15 - Prob. 3CSCh. 15 - Prob. 4CSCh. 15 - Prob. 1.1VCCh. 15 - Prob. 1.2VCCh. 15 - Prob. 1.3VCCh. 15 - Prob. 2.1VCCh. 15 - Prob. 2.2VCCh. 15 - Prob. 2.3VCCh. 15 - Prob. 2.4VC
Knowledge Booster
Similar questions
- Question 5 Tasty Tim’s Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco): Chop and trim meat – 30 Chop vegetables – 20 Grill meat – 240 Grill vegetables – 180 Prepare toppings - Lettuce - 10 - Tomato - 15 - Guacamole - 40 Assemble taco - Add meat - 5 - Add vegetables - 5 - Add cheese - 5 - Add toppings - 10 Wrap taco - 20 During the lunch hour, Tasty Tim’s encounters demand for 120 tacos. In an ideal world, how many workers should Tim hire to make tacos?arrow_forwardQuestion:-M Full explain this question and text typing work only.arrow_forwardQUESTION 2 One of the employees at eden co ltd,described working at the company as to work at eden,you've got to be interested in a lot of stuff. you've got to be prepared to catch people when they fall,because people are trying stuff all the time and you've got to be prepared for unexpected because part of the way we work is almost liberately created chaos by doing more stuff than we've possibly got time to do,which means more junior members have more chances to become leaders because the senior ones can't do it all. you've got to be optimistic and smiley and damed hardwork. one of the senior managers connected,we try not to be prescriptive about defining talent and we try to encourage people to take individual responsibility for their own career path here as much as we can help them to a career path (a) in your own opinion what factors have contributed to organization citizenship behaviour among staffs at eden? elaborate your answers (b)discuss the leadership style that has help to…arrow_forward
- QUESTION 1: Differentiate between a project and a program and highlight two major characteristics of a PROJECTarrow_forwardQUESTION Rockwater management added two financial measures. Project profitability provided focus on the project as the basic unit for planning and control, and sales backlog helped reduce uncertainty of performance. Rockwater wanted to recognize the distinction between its two types of customers: Tier I customers, oil companies that wanted a high value-added relationship, and Tier II customers, those that chose suppliers solely on the basis of price. A price index, incorporating the best available intelligence on competitive position, was included to ensure that Rockwater could still retain Tier II customers’ business when required by competitive conditions. The company’s strategy, however, was to emphasize value-based business. An independent organization conducted an annual survey to rank customers’ perceptions of Rockwater’s services compared to those of its competitors. In addition, Tier I customers were asked to supply monthly satisfaction and performance ratings. Rockwater…arrow_forwardQUESTION Rockwater management added two financial measures. Project profitability provided focus on the project as the basic unit for planning and control, and sales backlog helped reduce uncertainty of performance. Rockwater wanted to recognize the distinction between its two types of customers: Tier I customers, oil companies that wanted a high value-added relationship, and Tier II customers, those that chose suppliers solely on the basis of price. A price index, incorporating the best available intelligence on competitive position, was included to ensure that Rockwater could still retain Tier II customers’ business when required by competitive conditions. The company’s strategy, however, was to emphasize value-based business. An independent organization conducted an annual survey to rank customers’ perceptions of Rockwater’s services compared to those of its competitors. In addition, Tier I customers were asked to supply monthly satisfaction and performance ratings. Rockwater…arrow_forward
- Question 6 Tasty Tim’s Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco): Chop and trim meat – 30 Chop vegetables – 20 Grill meat – 240 Grill vegetables – 180 Prepare toppings - Lettuce - 10 - Tomato - 15 - Guacamole - 40 Assemble taco - Add meat - 5 - Add vegetables - 5 - Add cheese - 5 - Add toppings - 10 Wrap taco - 20 During the lunch hour, Tasty Tim’s encounters demand for 120 tacos. During off-peak afternoon hours, demand at Tasty Tim’s drops to 40 tacos each hour. How many employees should Tim schedule to work during the afternoon? Again, ignore any effects of idle time or inefficiency due to poor line balancing.arrow_forwardQuestion 3 Tasty Tim’s Tasty Tim’s is a specialty taco restaurant. The following tasks are required for the successful assembly of a Tasty taco (times are in seconds per taco): Chop and trim meat – 30 Chop vegetables – 20 Grill meat – 240 Grill vegetables – 180 Prepare toppings - Lettuce - 10 - Tomato - 15 - Guacamole - 40 Assemble taco - Add meat - 5 - Add vegetables - 5 - Add cheese - 5 - Add toppings - 10 Wrap taco - 20 During the lunch hour, Tasty Tim’s encounters demand for 120 tacos. What is the labor content of one of Tasty Tim’s tacos?arrow_forwardQUESTION TWO Stephen Jones is the CEO of WISKY Contractors that has been in existence for the past 15 years. WISKY Contractors has acquired itself a good position in society through the leadership of Stephen Jones who realizes that his standing thrives on retaining a caliber of team members. The company has been awarded a new contract besides the two contracts that are currently running concurrently. To meet this demand, Stephen Jones needs to hire team leader that should be able to navigate a crowded construction site, read and write in order to keep up with the paper work, should have a high school diploma in construction and should have a minimum of 3 years practical work experience on a project, with supervisory roles as an added advantage. The team leader will be required to be on sight. Stephen Jones has thrived on the good name he has built for his organization on the basis of his commitment to undertaking and completing high quality projects within or under the project…arrow_forward
- Question: Based on the data provided. Which team do you think is better? Why Heat Data Table: HEAT PLAYERS POINTS PER GAME Bam Adebayo 19.1 Caleb Martin 9.2 Chris Silva 2.9 Dewayne Dedmon 6.3 Duncan Robinson 10.9 Gabe Vincent 8.7 Haywood Highsmith 2.3 Javonte Smart 5 Jimmy Butler 21.4 KZ Okpala 3.7 Kyle Guy 3.9 Kyle Lowry 13.4 Marcus Garrett 1.1 Markieff Morris 7.6 Max Strus 10.6 Mychal Mulder 7 Nik Stauskas 5.5 Omer Yurtseven 5.3 P.J. Tucker 7.6 Tyler Herro 20.7 Udonis Haslem 2.5 Victor Oladipo 12.4 Celtics Data Table CELTICS PLAYERS POINTS PER GAME Aaron Nesmith 3.8 Al Horford 10.2 Brodric Thomas 1.8 Bruno Fernando 1 CJ Miles 0 Daniel Theis 7.9 Dennis Schroder 14.4 Derrick White 11 Enes Freedom 3.7 Grant Williams 7.8 Jabari Parker 4.4 Jaylen Brown 23.6 Jayson Tatum 26.9 Joe Johnson 2 Josh Richardson 9.7 Juancho Hernangomez 1.1 Justin Jackson 2 Juwan Morgan 0 Kelan Martin 0 Luke Kornet 2.2…arrow_forwardQUESTION TWO As an operations management intern at a Limpopo-based company, HGK Holdings, your role is to assist the operationsanalyst with reconfiguring a brownfield project at HGK’s industrial estate in the Limpopo province, code-named LPCHP1. The reconfiguration involves the installation of an advanced biomass unit which generates electrical andthermal energy by burning wood pellets produced as a by-product of the wood processing industry in the province.The process is commonly called cogeneration or CHP (combined heat and power) and it is expected to save cost andincrease operational efficiency at HGK Holdings. The electrical and thermal energy generated is expected to be utilisedin the operations of HGK Holdings. REQUIRED:Answer each of the following questions: 2.1. With the aid of an appropriately labelled Input-Transformation-Output diagram, comprehensively discuss thetransformation process underpinning the operations of LP-CHP1. In your discussion, highlight the transformedand…arrow_forwardQuestion: What is resource pooling, and how is it used in resource management?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.