OPERATIONS MANAGEMENT (LL) >CUSTOM<
OPERATIONS MANAGEMENT (LL) >CUSTOM<
13th Edition
ISBN: 9781260352542
Author: Stevenson
Publisher: MCG CUSTOM
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 17, Problem 7P

Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table.

a. Draw the precedence diagram.

b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?

c. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24 and the probability of finishing by day 21.

Chapter 17, Problem 7P, Three recent college graduates have formed a partnership and have opened an advertising firm. Their , example  1

d. The partners have decided that shortening the project by two days would be beneficial, as long as it doesn’t cost more than about $20,000. They have estimated the daily crashing costs for each activity in thousands, as shown in the following table. Which activities should be crashed, and what further analysis would they probably want to do?

Chapter 17, Problem 7P, Three recent college graduates have formed a partnership and have opened an advertising firm. Their , example  2

a)

Expert Solution
Check Mark
Summary Introduction

To draw: A precedence diagram.

Answer to Problem 7P

Precedence diagram:

OPERATIONS MANAGEMENT (LL) >CUSTOM<, Chapter 17, Problem 7P , additional homework tip  1

Explanation of Solution

Given information:

Activity Immediate Predecessor Optimistic time Most likely time Pessimistic time
A 5 6 7
B 8 8 11
C A 6 8 11
D 9 12 15
E C 5 6 9
F D 5 6 7
G F 2 3 7
H B 4 4 5
I H 5 7 8
End E, G, I
Activity First crash Second crash
C  $       8.00  $         10.00
D  $     10.00  $         11.00
E  $       9.00  $         10.00
F  $       7.00  $           9.00
G  $       8.00  $           9.00
H  $       7.00  $           8.00
I  $       6.00  $           8.00

Precedence diagram:

OPERATIONS MANAGEMENT (LL) >CUSTOM<, Chapter 17, Problem 7P , additional homework tip  2

The precedence diagram is drawn from the first task till the last task. The activities are placed from left to right. The directions are represented with arrows to indicate the relationship between activities. The arrows are represented with the activity name.

b)

Expert Solution
Check Mark
Summary Introduction

To determine: The probability at which the projected can be completed in 24 days or less and 21 days or less.

Answer to Problem 7P

The probability at which the projected can be completed in:

24 days or less = 0.9686

21 days or less = 0.2350

Explanation of Solution

Given information:

Activity Immediate Predecessor Optimistic time Most likely time Pessimistic time
A 5 6 7
B 8 8 11
C A 6 8 11
D 9 12 15
E C 5 6 9
F D 5 6 7
G F 2 3 7
H B 4 4 5
I H 5 7 8
End E, G, I
Activity First crash Second crash
C  $       8.00  $         10.00
D  $     10.00  $         11.00
E  $       9.00  $         10.00
F  $       7.00  $           9.00
G  $       8.00  $           9.00
H  $       7.00  $           8.00
I  $       6.00  $           8.00

Formula to calculate expected time and variance:

Expected time=Optimistic time+(4×Most likely time)+Pessimistic time6

Standard deviation=Pessimistic time-Optimistic time6

Variance=(Pessimistic time-Optimistic time)262

Calculation of expected time and variance:

Activity Optimistic time Most likely time Pessimistic time Expected time Standard deviation Variance
A B C (A+(4*B)+C)/6 (C-A)/6 (C-A)^2/6^2
A 5 6 7 6 0.333 0.111
B 8 8 11 8.5 0.500 0.250
C 6 8 11 8.17 0.833 0.694
D 9 12 15 12 1.000 1.000
E 5 6 9 6.33 0.667 0.444
F 5 6 7 6 0.333 0.111
G 2 3 7 3.5 0.833 0.694
H 4 4 5 4.17 0.167 0.028
I 5 7 8 6.83 0.500 0.250

Calculation of expected duration, variance and standard deviation for each path:

A-C-E:

Expected duration=6+8.17+6.33=20.50

Variance=0.111+0.694+0.444=1.249

Standard deviation=Variance=1.249=1.1175=1.118

D-F-G:

Expected duration=12+6+3.50=21.50

Variance=1+0.111+0.694=1.805

Standard deviation=Variance=1.805=1.3435=1.344

B-H-I:

Expected duration=8.50+4.17+6.83=19.50

Variance=0.250+0.028+0.250=0.528

Standard deviation=Variance=0.528=0.726

Calculation of z value for all paths:

Formula:

Z=Specified time-Path meanPath standard deviation

24 days or less:

A-C-E:

Z=24-20.501.118=3.13

Since z value is greater than +3.00, probability of completion is 1.00.

D-F-G:

Z=24-21.501.344=1.86

From the standard normal distribution table,

The probability value for (z = 1.86) is 0.9686.

B-H-I:

Z=24-19.500.726=6.20

Since z value is greater than +3.00, probability of completion is 1.00.

Probability of completion in 24 days or less:

Probability=1.00×0.9686×1.00=0.9686

The probability at which the project can be completed in 24 days or less is 0.9686.

21 days or less:

A-C-E:

Z=21-20.501.118=0.45

From the standard normal distribution table,

The probability value for (z = 0.45) is 0.6736.

D-F-G:

Z=21-21.501.344=-0.37

From the standard normal distribution table,

The probability value for (z = -0.37) is 0.3557.

B-H-I:

Z=21-19.500.726=2.07

From the standard normal distribution table,

The probability value for (z = 2.07) is 0.9808.

Probability of completion in 21 days or less:

Probability=0.6736×0.3557×0.9808=0.2350

The probability at which the project can be completed in 21 days or less is 0.2350.

c)

Expert Solution
Check Mark
Summary Introduction

To determine: The probability of completing the project by day 24 and day 21.

Answer to Problem 7P

The probability at which the projected can be completed in:

Day 24 = 0.9328

Day 21 = 0.0186

Explanation of Solution

Given information:

  • At the end of 7th day activities A and B are completed and D is 50% completed.
  • Time estimates of activity D completion are 5, 6 and 7.
  • Activities C and H are ready to begin.
Activity Immediate Predecessor Optimistic time Most likely time Pessimistic time
A 5 6 7
B 8 8 11
C A 6 8 11
D 5 6 7
E C 5 6 9
F D 5 6 7
G F 2 3 7
H B 4 4 5
I H 5 7 8
End E, G, I
Activity First crash Second crash
C  $       8.00  $         10.00
D  $     10.00  $         11.00
E  $       9.00  $         10.00
F  $       7.00  $           9.00
G  $       8.00  $           9.00
H  $       7.00  $           8.00
I  $       6.00  $           8.00

Formula to calculate expected time and variance:

Expected time=Optimistic time+(4×Most likely time)+Pessimistic time6

Standard deviation=Pessimistic time-Optimistic time6

Variance=(Pessimistic time-Optimistic time)262

Calculation of expected time and variance:

Activity Optimistic time Most likely time Pessimistic time Expected time Standard deviation Variance
A B C (A+(4*B)+C)/6 (C-A)/6 (C-A)^2/6^2
A 5 6 7 6 0.333 0.111
B 8 8 11 8.5 0.500 0.250
C 6 8 11 8.17 0.833 0.694
D 5 6 7 6 0.333 0.111
E 5 6 9 6.33 0.667 0.444
F 5 6 7 6 0.333 0.111
G 2 3 7 3.5 0.833 0.694
H 4 4 5 4.17 0.167 0.028
I 5 7 8 6.83 0.500 0.250

Revised project diagram:

OPERATIONS MANAGEMENT (LL) >CUSTOM<, Chapter 17, Problem 7P , additional homework tip  3

Calculation of expected duration, variance and standard deviation for each path:

C-E:

Expected duration=7+(8.17+6.33)=21.50

Variance=0.694+0.444=1.138

Standard deviation=Variance=1.138=1.0667=1.067

D-F-G:

Expected duration=7+(6+6+3.50)=22.50

Variance=0.111+0.111+0.694=0.916

Standard deviation=Variance=0.916=0.9570=0.957

H-I:

Expected duration=7+(4.17+6.83)=18

Variance=0.028+0.250=0.278

Standard deviation=Variance=0.278=0.527

Calculation of z value for all paths:

Formula:

Z=Specified timePath meanPath standard deviation

24 days or less:

C-E:

Z=2421.501.067=2.34

From the standard normal distribution table,

The probability value for (z = 2.34) is 0.9904.

D-F-G:

Z=24-22.500.957=1.57

From the standard normal distribution table,

The probability value for (z = 1.57) is 0.9418.

H-I:

Z=24-180.527=11.39

Since z value is greater than +3.00, probability of completion is 1.00.

Probability of completion in 24 days or less:

Probability=0.9904×0.9418×1.00=0.9328

The probability at which the project can be completed in 24 days is 0.9328.

21 days or less:

C-E:

Z=2121.501.067=0.47

From the standard normal distribution table,

The probability value for (z = -0.47) is 0.3192.

D-F-G:

Z=21-22.500.957=1.57

From the standard normal distribution table,

The probability value for (z = -1.57) is 0.0582.

H-I:

Z=21180.527=5.69

Since z value is greater than +3.00, probability of completion is 1.00.

Probability of completion in 21 days or less:

Probability=0.3192×0.0582×1.000=0.0186

The probability at which the project can be completed in 21 days is 0.0186.

d)

Expert Solution
Check Mark
Summary Introduction

To determine: The activities that should be crashed and further analysis.

Explanation of Solution

Given information:

  • The partners want to shorten the project by 2 days as long as the cost is not more than $20,000.
Activity Immediate Predecessor Optimistic time Most likely time Pessimistic time
A 5 6 7
B 8 8 11
C A 6 8 11
D 5 6 7
E C 5 6 9
F D 5 6 7
G F 2 3 7
H B 4 4 5
I H 5 7 8
End E, G, I
Activity First crash Second crash
C  $       8.00  $         10.00
D  $     10.00  $         11.00
E  $       9.00  $         10.00
F  $       7.00  $           9.00
G  $       8.00  $           9.00
H  $       7.00  $           8.00
I  $       6.00  $           8.00

Paths and expected duration:

Paths Expected Duration
C-E 21.50
D-F-G 22.50
H-I 18.00

The critical path is D – F – G.

The activities are crashed based on the cost of crash given.

Activity Cost
F $7
G $8
D $10

Step 1:

Activity F has the lowest crashing cost ($7,000) and will be crashed first for 1 day. The expected duration of D-F-G will be 21.50 days.

Step 2:

Path Expected Duration
C-E 21.50
D-F-G 21.50
H-I 18.00

Now there are two critical paths C-E and D-F-G.

The critical activities are arranged in the order of low crash costs.

Path Activity Cost
C-E C $8
F $9
Path Activity Cost
D-F-G D $8
F $9
G $10

One activity in each path is chosen to crash.

Activity C is crashed for 1 day since it has the lowest crashing cost ($8,000) on path C-E. The expected duration of path C-E is now 20.50 days.

Activity G is crashed for 1 day since it has the lowest crashing cost ($8,000) on path D-F-G. The expected duration of path D-F-G is now 20.50 days.

Calculation of total crashing cost:

Total cost=$7,000+$8,000+$8,000=$23,000

The total cost of crashing is over the budget of $20,000 ($23,000 > $20,000). Hence, the partners will have to determine if crashing the project by 1 day or 2 days is really beneficial or not.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Three recent college graduates have formed a partnership and have opened an advertising firm. Their first project consists of activities listed in the following table. a. Draw the precedence diagram. b. What is the probability that the project can be completed in 24 days or less? c. Suppose it is now the end of the seventh day and that activities A and B have been completed while activity D is 50 percent completed. Time estimates for the completion of activity D are 5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing the project by day 24.     TIME IN DAYS Activity Precedes Optimistic Most Likely Pessimistic A — 5 6 7 B — 8 8 11 C A 6 8 11 D - 9 12 15 E C 5 6 9 F D 5 6 7 G F 2 3 7 H B 4 4 5 I H 5 7 8 End E,G,I           d. The partners have decided that shortening the…
Three recent college graduates have formed a partnership and have opened an advertising firm.Their first project consists of activities listed in the following table.a. Draw the precedence diagram.b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?c. Suppose it is now the end of the seventh day and that activities A and B have been completedwhile activity D is 50 percent completed. Time estimates for the completion of activity D are5, 6, and 7. Activities C and H are ready to begin. Determine the probability of finishing theproject by day 24 and the probability of finishing by day 21.TIME IN DAYSActivityImmediatePredecessor Optimistic Most Likely PessimisticA — 5 6 7B — 8 8 11C A 6 8 11D — 9 12 15E C 5 6 9F D 5 6 7G F 2 3 7H B 4 4 5I H 5 7 8End E, G, Id. The partners have decided that shortening the project by two days would be beneficial, as longas it doesn’t cost more than about $20,000. They have estimated the daily crashing costs for…
a. What is the​ project's duration if only normal times are​ used? b. What is the​ minimum-cost schedule? With the​ minimum-cost schedule, the project duration is ____​day(s).?

Chapter 17 Solutions

OPERATIONS MANAGEMENT (LL) >CUSTOM<

Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - CASE: The Case of the Mexican crazy quilt 1. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 2. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 3. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 4. The...Ch. 17 - CASE: The Case of the Mexican crazy quilt 5. The...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY