EBK OM
EBK OM
6th Edition
ISBN: 9781305888210
Author: Collier
Publisher: YUZU
bartleby

Concept explainers

bartleby

Videos

Question
Book Icon
Chapter 18, Problem 12PA
Summary Introduction

Interpretation: The total project completion time is to be calculated along with the lowest cost solution if the project is to be completed 3 weeks early.

Concept Introduction:

Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.

Expert Solution & Answer
Check Mark

Explanation of Solution

The activity with their immediate predecessor and estimated time, crash time, crash cost and normal cost is tabulated below.

    ActivityImmediate PredecessorEstimated Normal TimeCrash TimeNormal CostCrash Cost
    A-54400750
    BA8618002200
    CA768001100
    D-656001000
    EB, D, C8617002200
    FD328001000
    GD32500650
    HE43400600
    IF, G, H659001300

Table (1)

The network diagram for the activity shown in table (1) is shown below.

  EBK OM, Chapter 18, Problem 12PA , additional homework tip  1

Figure (1)

Therefore, the network diagram of the given project is shown in Figure (1).

The expression for the cost slope is given by,

  Cost Slope=Crash CostNormal CostNormal TimeNormal Cost

The cost slope for each activity is tabulated below.

    ActivityImmediate PredecessorEstimated Normal TimeCrash TimeNormal CostCrash CostCost Slope
    A-54400750350
    BA8618002200200
    CA768001100300
    D-656001000400
    EB, D, C8617002200250
    FD328001000200
    GD32500650150
    HE43400600200
    IF, G, H659001300400

Table (2)

Consider figure (1), the different paths and their completion times is tabulated below.

    PathCompletion time (weeks)
    A-B-E-H-I5+8+8+4+6=31
    A-C-E-H-I5+7+8+4+6=30
    D-E-H-I6+8+4+6=24
    D-G-I6+3+6=15
    D-F-I6+3+6=15

Table (3)

From Table (3), the maximum completion time is taken by path A-B-E-H-I . So, this is the critical path.

Therefore, the critical path is A-B-E-H-I and its duration is 31weeks .

Now the project is to be completed 3 weeks earlier.

Consider the critical path activities.

The lowest crash cost per week is of activity B and activity H.

Crash Activity B by 2 weeks and activity H by 1week .

  Crash B=2×200=400

And,

  Crash H=1×200=200

Thus, the additional cost of crashing the activity by 3weeks is,

  Additional cost=200+400=600

The new network diagram is shown in figure below.

  EBK OM, Chapter 18, Problem 12PA , additional homework tip  2

Figure (2)

Consider figure (2), the different paths and their completion times is tabulated below.

    PathCompletion time (weeks)
    A-B-E-H-I5+7+7+3+6=28
    A-C-E-H-I5+7+8+3+6=29
    D-E-H-I6+8+3+6=23
    D-G-I6+3+6=15
    D-F-I6+3+6=15

Table (4)

From Table (4), the maximum completion time is taken by path A-C-E-H-I . So, this is the critical path.

Therefore, the critical path is A-C-E-H-I and its duration is 29weeks .

But the desired project duration is 28 weeks .

Try different option.

Crash Activity B by 1 week, activity E by 1week and activity H by 1week .

  Crash B=1×200=200

And,

  Crash H=1×200=200

And,

  Crash E=1×250=250

Thus, the additional cost of crashing the activity by 3weeks is,

  Additional cost=200+200+250=650

The new network diagram is shown in figure below.

  EBK OM, Chapter 18, Problem 12PA , additional homework tip  3

Figure (3)

Consider figure (3), the different paths and their completion times is tabulated below.

    PathCompletion time (weeks)
    A-B-E-H-I5+7+7+3+6=28
    A-C-E-H-I5+7+7+3+6=28
    D-E-H-I6+7+3+6=22
    D-G-I6+3+6=15
    D-F-I6+3+6=15

Table (4)

From Table (4), the maximum completion time is taken by path A-C-E-H-I and A-B-E-H-I So, this are the critical path.

Therefore, the critical path are A-C-E-H-I and A-B-E-H-I and its duration is 28weeks .

Therefore, the crashing cost of the project is $650 .

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
There are four critical paths in a network. A-B-C-D-E, A-F-E, A-B-H-J-K-E and A-S-T-E. Each activity in this network can be crashed by a maximum of 4 weeks. The crashing cost (per week), for the first week, for activity A is: $560, E is $565 and all other activities is : $140 (per week per activity). The crashing cost, second week and onwards, for activity A is $1120 per week, E is $1400 per week and for all other activities is $420 per activity per week. You have a maximum crashing budget of $2385. The maximum possible reduction in the project duration will be: a. 5 weeks b. 3 weeks c. 4 weeks d. 2 weeks e. 1 week
. New York Building Corporation uses the critical path method to monitor construction jobs. The company is     currently 2 weeks behind schedule on Job #181, which is subject to a P10,500 per week completion penalty.     Path A-B-C-F-G-H-I has a normal completion time of 20 weeks, and critical path A-D-E-F-G-H-I has a normal     completion time of 22 weeks. The following activities can be crashed.                Activities                         Cost to Crash 1 Week                 Cost to Crash 2 Weeks                    BC                                     P  8,000                                          P15,000                    DE                                       10,000                                            19,600                    EF                                         8,800                                             19,500         REQUIRED: New York Building desires to reduce the normal completion time Job #181 and, at the same time, report…
The project manager is tasked with the responsibility of balancing project constraints to increase the probability of project success, and ensure that the project meets its objectives. Identify and explain at least five (5) project constraints, and explain the working of the triple constraint model of project management.
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY