Concept explainers
(a)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project
(a)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
For
Hence, the probability that the project is completed within
(b)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.
(b)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
For
Hence, the probability that the project is completed within
(c)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.
(c)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
For
Hence, the probability that the project is completed within
(d)
Interpretation: The probability that the project is completed within
Concept Introduction:
Project Scheduling is used in Project planning and coordination by using Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). PERT is a network based scheduling procedure. This technique is used to plan, schedule and control different project such as construction works, design installation of system, maintenance work and research and development process.
(d)
Explanation of Solution
The activity with optimistic, most probable and pessimistic time is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time |
A | |||
B | |||
C | |||
D | |||
E | |||
F | |||
G |
Table (1)
The expression for the estimated time is given by,
Here,
The expression for variance is given by,
The variance and estimated time of each activity is tabulated below.
Activity | Optimistic time | Most Probable Time | Pessimistic Time | Estimated Time | Variance |
A | |||||
B | |||||
C | |||||
D | |||||
E | |||||
F | |||||
G |
Table (2)
Calculate
Refer probability distribution table.
There is no value for
Hence, the probability that the project is completed within
Want to see more full solutions like this?
- The optimistic duration for a project is 10 weeks. The worst case estimate is 22 weeks, and the most likely duration is 13 weeks. Using 2 sigma estimates and PERT, what is the range of the duration estimate? 12 to 16 weeks 13 to 17 weeks 10 to 18 weeks 11 to 19 weeksarrow_forwardgiven the following information for a 1-year project, answer the following questions. Assume you have actual and earned value data at the end of the second month. Recall that PV is the plan value, Evie is the earned value, AC is the actual cost, and BAC is the budget at completion.pv =$ 23,000ev = 20,000ac= 25,000bac = 130,000a. what is the cost variance, schedule variance, cost performance index CPI and schedule performance index SPI for the project?B. how is the project progressing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?C. use the CPI to calculate the estimate at completion EAC for this project.d. use the SPI to estimate how long it will take to finish this project.e. sketch the earned value chart for this project, use the figure below as a guide. Assume the data for month one is half of the values given for Pv, Ev and ac at the end of month 2arrow_forwardExercise regular time acceleration time Normal Cost acceleration cost Precedents A 4 3 900 1000 --- B. 8 6 300 400 --- C 4 3 500 650 --- D 6 4 900 1200 A AND 7 4 1000 1600 C a. The duration of the project in normal time and without acceleration is Response days . b. The minimum cost to accelerate the project in 2 days is Response .arrow_forward
- Your company has just received an order from a good customer for a specially designed electric motor. The contract states that, starting on the 13th day from now, your firm will experience a penalty of $100 per day until the job is completed. Indirect project costs amount to $200 per day. The data on direct costs and activity precedence relationships are given in Table. Electric Motor Project Data Activity Normal Time(days) Normal Cost ($) Crash Time (days) Crash Cost ($) ImmediatePredecessor(s) A B C D E F G H 4 7 5 6 3 11 4 3 1000 1400 2000 1200 900 2500 800 300 3 4 4 5 2 6 3 1 1300 1200 2700 1400 1100 3750 1450 500 None None None A B C D,E F,G a. Draw the project network diagram.b. What completion date would you recommend?arrow_forwardThe project described in the following table has just begun. It is scheduled to be completed in 11 weeks.Use Table B1 and Table B2. Activity Estimated Time(weeks) Standard Deviation(wks.) 1-2 4 0.70 2-4 6 0.90 1-3 3 0.62 3-4 9 1.90 a. If you were the manager of this project, would you be concerned? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) because the probability of finishing on schedule is only about . b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability Have worked this with various formulas and all come back wrong. Where am I making a mistakearrow_forwardGiven the following table, construct a network diagram, either AOA or AON. Times are in days.a. Determine the expected duration of the project.b. Compute the probability that the project will take at least 18 days.Path Activity Time EstimatesA 4-5-6Top B 7-8-10C 3-5-9D 7-8-11Bottom E 2-3-4F 1-4-6arrow_forward
- Use the following project status information to calculate each of the requested EVM numbers below (a-i).The project status is reported at the end of week 13. Task Budget Cost Budget Duration Status as of Week 13 A $5,000 2 Weeks 100 percent complete $5,000B $8,500 3 Weeks 100 percent complete $9,000C $15,000 4 Weeks 75 percent complete $14,000D $10,000 4 Weeks 50 percent complete $9,000 E $12,000 4 Weeks Not startedF $15,000 5 Weeks Not started a. Planned Valuedb. Actual costc. Cost varianced. Schedule variancee. Cost performance indexf. Schedule performance indexg. Budget at completionh. Estimation to completei. Estimation at completionarrow_forwardThe following information has been computed from a project: Expected total project time = T = 62 weeks Project variance = 81 1- What is the probability that the project will be completed 18 weeks before its expected completion date? 2- Draw Normal Curve & Analysis your solution with conclusionarrow_forwardYour firm MS MACKAY LTD. won a contract of €1,785,000 to construct a 161kV/33kV sub-station. You have been selected as the project manager to lead the project team for the successful execution of the project. You are the project manager, there are a total of 8,400 hours of work schedule on the project. You made your checks with the accounting department, and they told you that you have spent a total of €1,144,000. According to the schedule, your team should have worked 5000 hours, but your foreman says that the team was allowed to work some overtime, and they have actually put in 5600 hours of work. (i) Write the scope of the project (ii) Provide the WBS for the project.arrow_forward
- The expected time and variances for the major activities of an R&D project are depicted in the following PERT chart. Determine the probability that the project completion time will be: A. Less than 50 weeks B. More than 50 weeksarrow_forwardYou are the head of the project selection team at Broken Arrow Records. Your team is considering two different recording projects. Based on past history, Broken Arrow expects at least a rate of return of 20 percent. Given the follwoing information for each project, which one should be Broken Arrow's first priority? Should Broken Arrow fund any of the other projects? If so, what should be the order of priority based on return on investment?arrow_forward1. Analyze the cost variance metric, and include the equation and what the acronyms stand for. 1. Describe one project software program that could help a project manager control costs.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.