CASE 2-22 Plantwide versus Departmental Overhead Rates; Pricing LO2-1, LO2-2, LO2-3, LO2-4
'Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2000. It seems we’re either too half to pet the job or too low to make any money on half the jobs we bid.”
Teledex Company manufactures products to customers' specifications and uses a
Department
FabricatingMachiningAssemblyTotal Plant
Manufacturing overhead....$350,000$400,000$90,000$840,000
Direct labor.......$200,000$100,000$300,000$600,000
Jobs require varying amounts of work in the three departments. The Koopers job, for example, would have required
Department
Fabricating | Machining | Assembly | Total Plant | |
Direct materials | $3,000 |
$200 | $1,400 | $4,600 |
Direct labor | $2,800 | $500 | $6,200 | $9,500 |
Manufacturing overhead ... | ? |
? | ? | ? |
Required:
- Using the company's plantwide approach:
a. Compute the predetermined overhead rate for each department for the current year.
b. Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
Want to see the full answer?
Check out a sample textbook solutionChapter 2 Solutions
Managerial Accounting
- Factory overhead rate Fabricator Inc., a specialized equipment manufacturer, uses a job order cost system. The overhead is allocated to jobs on the basis of direct labor hours. The overhead rate is now $3,000 per direct labor hour. The design engineer thinks that this is illogical. The design engineer has stated the following: Our accounting system doesn't make any sense to me. It tells me that every labor hour carries an additional burden of $3,000. This means that while direct labor makes up only 5% of our total product cost, it drives all our costs. In addition, these rates give my design engineers incentives to "design out" direct labor by using machine technology. Yet, over the past years as we have had less and less direct labor, the overhead rate keeps going up and up. I won't be surprised if next year the rate is $4,000 per direct labor hour. I'm also concerned because small errors in our estimates of the direct labor content can have a large impact on our estimated costs. Just a 30~minute error in our estimate of assembly time is worth $ 1,500. Small mistakes in our direct labor time estimates really swing our bids around. I think this puts us at a disadvantage when we are going after business. What did the engineer mean about the large overhead rate being a disadvantage when plating bids and seeking new business?arrow_forwardPareto chart and cost of quality report for a manufacturing company The president of Mission Inc. has been concerned about the growth in costs over the last several years. The president asked the controller to perform an activity analysis to gain a better insight into these costs. The activity analysis revealed the following: Activities Activity Cost Correcting invoke errors 7,500 Disposing of incoming materials with poor quality 15,000 Disposing of scrap 27,500 Expediting late production 22,500 Final inspection 20,000 Inspecting incoming materials 5,000 Inspecting work in process 25,000 Preventive machine maintenance 15,000 Producing product 97,500 Responding to customer quality complaints 15,000 Total 250,000 The production process is complicated by quality problems, requiring the production manager to expedite production and dispose of scrap. Instructions 1. Prepare a Pareto chart of the company activities. 2. Classify the activities into prevention, appraisal, internal failure, external failure, and not costs of quality (producing product). Classify the activities into value-added and non-value- added activities. 3. Use the activity cost information to determine the percentages of total costs that are prevention, appraisal, internal failure, external failure, and not costs of quality. 4. Determine the percentages of total costs that are value-added and non-value-added. 5. Interpret the information.arrow_forward36. LO.3 (Activity analysis) Management at Glover & Lamb Inc. is concerned about controlling factory labor-related costs. Th e following summary is the result of an analy-sis of the major categories of labor costs for 2010:Category AmountBase wages $63,000,000Health-care benefi ts 10,500,000Payroll taxes 5,018,832Overtime 8,697,600Training 1,875,000Retirement benefi ts 6,898,500Workers’ compensation 1,199,940Following are some of the potential cost drivers identifi ed by the company for labor-related costs, along with their 2010 volume levels:Potential Activity Driver 2010 Volume LevelAverage number of factory employees 2,100Number of new hires 300Number of regular labor hours worked 3,150,000Number of overtime hours worked 288,000Total factory wages paid $71,697,600Volume of production in units 12,000,000Number of production process changes 600Number of production schedule changes 375a. For each cost pool, determine the cost per unit of the activity driver using the activ-ity…arrow_forward
- Question 3: An organization wants to prepare an aggregate plan for its manufacturing facility. The relevant information is shown as follows: Production time: 1 hour per unit Beginning inventory: 500 units Average labor cost: $10 per hour Safety stock: 50% of monthly demand Workweek: 5 days, Shift length: 8 hours Shortage cost: $20 per unit per month Days per month: 20 work days/month Carrying cost: $5 per unit per monthManagement prefers to keep a constant workforce and production level, absorbing variations in demand through inventory excesses and shortages. Demand not met is carried over to the following month. Develop an aggregate plan that will meet the demand and other conditions of the problemarrow_forwardLO.1 & LO.3 (Plant vs. departmental OH rates) Red River Farm Machine makes a wide variety' of products, all of which must be processed in the Cutting and Assembly departments. For the year 2013, Red River budgeted total overhead of $993,000, of which $385,500 will be incurred in Cutting and the remainder will be incurred in Assembly. Budgeted direct labor and machine hours are as follows: Cutting Assembly Budgeted direct labor hours 27,000 3,000 Budgeted machine hours 2,100 65,800 Two products made by Red River are the RW22SKI and the SD45ROW. The following cost and production time information on these items has been gathered: RW22SKI SD45ROW Direct material $34.85 $19.57 Direct labor rate in Cutting $20.00 $20.00 Direct labor rate in Assembly $8.00 $8.00 Direct labor hours in Cutting 6.00 4.80 Direct labor hours in Assembly 0.03 0.05 Machine hours in Cutting 0.06 0.15 Machine hours in Assembly 5.90 9.30 a. What is the plantwide predetermined…arrow_forwardLO.1 & LO.3 (Plant vs. departmental OH rates) Red River Farm Machine makes a wide variety' of products, all of which must be processed in the Cutting and Assembly departments. For the year 2013, Red River budgeted total overhead of $993,000, of which $385,500 will be incurred in Cutting and the remainder will be incurred in Assembly. Budgeted direct labor and machine hours are as follows: Cutting Assembly Budgeted direct labor hours 27,000 3,000 Budgeted machine hours 2,100 65,800 Two products made by Red River are the RW22SKI and the SD45ROW. The following cost and production time information on these items has been gathered: RW22SKI SD45ROW Direct material $34.85 $19.57 Direct labor rate in Cutting $20.00 $20.00 Direct labor rate in Assembly $8.00 $8.00 Direct labor hours in Cutting 6.00 4.80 Direct labor hours in Assembly 0.03 0.05 Machine hours in Cutting 0.06 0.15 Machine hours in Assembly 5.90 9.30 d. A competitor manufactures a product…arrow_forward
- QUESTION 34 The following cost information is available for David, Ltd.: Activity Allocation Base Volume of Activity Overhead Cost Purchasing Purchase orders 25,000 $150,000 Receiving Shipments received 17,000 68,000 Machine setups Setups 3,000 190,000 Quality control Inspections 20,000 100,000 Direct materials are $15 per unit for luxury handbags and $10 per unit for deluxe handbags. There were 12,000 direct labor hours. Each of which was charged to inventory at $18 per hour. Required: Calculate the overhead rate using activity-based costing for the Receiving Activity. $4 per shipment $5 per shipment $6 per shipment $7 per shipmentarrow_forwardQUESTION 4. Etsi GR is a Greek manufacturing company whose total factory overhead costs fluctuate from year to year according to the number of machine- hours worked in its production facility. These costs at HIGH and LOW levels of activity over recent years are given below: High Low Machine –hours 80,000 60,000 Total overhead costs €312,000 €274,000 The total overhead costs ABOVE AT 60,000 machine hours (Low point) are made up of the following costs: Indirect Materials (VARIABLE) € 90,000 Rent (FIXED) 130,000 Maintenance (MIXED) 54,000 274,000 B)Use the HIGH LOW method, break down the Maintenance costs into b(variable cost per machine hour) and a (total fixed maintenance cost)arrow_forwardquestoin 9 chapter 4 Assume a company provided the following information: Service Departments Operating Departments Cafeteria Janitorial Lab Tech Departmental costs $ 180,000 $ 140,000 $ 232,000 $ 950,000 Number of employees 10 20 40 60 Square feet of space occupied 3,000 2,000 11,000 9,000 If the company (1) uses the step-down method (beginning with the Cafeteria) to allocate service department costs to operating departments, (2) allocates Cafeteria costs based on the number of employees, and (3) allocates Janitorial costs based on square feet of space of occupied, then the cost allocated from the Cafeteria Department to the Lab Department is closest to: Multiple Choice $60,000. $54,871. $73,333. $113,333.arrow_forward
- Question 4 Stanford Corporation has four categories of overhead. The expected overhead costs for each category for next year are as follows: Maintenance $210,000 Materials handling 90,000 Setups 75,000 Inspection 150,000 The company has been asked to submit a bid for a proposed job. The plant manager believes that obtaining this job would result in new business in future years. Bids are usually based upon full manufacturing cost plus 30 percent. Estimates for the proposed job are as follows: Direct materials $5,000 Direct labor (375 hours) $7,500 Number of material moves 4 Number of inspections 3 Number of setups 2 Number of machine-hours 150 Expected activity for the four activity-based cost drivers that would be used is: Machine-hours 10,000 Material moves 2,000 Setups 100 Quality inspections 4,000 Required: a. Determine the amount of overhead that would be allocated to…arrow_forward48. LO.1 & LO. 3–LO.5 (Activity analysis, ABC; pricing; cost drivers; decision making)Hurley Corporation has identifi ed the following overhead costs and cost drivers for the coming year:Overhead Item Cost DriverBudgeted CostBudgeted Activity LevelMachine setup Number of setups $ 20,000 200Inspection Number of inspections 130,000 6,500Material handling Number of material moves 80,000 8,000Engineering Engineering hours 50,000 1,000$280,000Th e following information was collected on three jobs that were completed dur-ing the year:Job 101 Job 102 Job 103Direct material $5,000 $12,000 $8,000Direct labor $2,000 $ 2,000 $4,000Units completed 100 50 200Number of setups 1 2 4Number of inspections 20 10 30Number of material moves 30 10 50Engineering hours 10 50 10Budgeted direct labor cost was $100,000, and budgeted direct material cost was $280,000.a. If the company uses activity-based costing, how much overhead cost should be assigned to Job 101?b. If the company uses activity-based…arrow_forwardExercise 4-4 Contrast ABC and Conventional Product Costs [LO4-4] Pacifica Industrial Products Corporation makes two products, Product H and Product L. Product H is expected to sell 40,000 units next year and Product L is expected to sell 8,000 units. A unit of either product requires 0.4 direct labor-hours. The company's total manufacturing overhead for the year is expected to be $1,632,000. Required: 1-a. The company currently applies manufacturing overhead to products using direct labor-hours as the allocation base. If this method is followed, how much overhead cost per unit would be applied to each product? 1-b. Compute the total amount of overhead cost that would be applied to each product. 2. Management is considering an activity-based costing system and would like to know what impact this change might have on product costs. For purposes of discussion, it has been suggested that all of the manufacturing overhead be treated as a product-level cost. The total manufacturing…arrow_forward
- Survey of Accounting (Accounting I)AccountingISBN:9781305961883Author:Carl WarrenPublisher:Cengage LearningFinancial & Managerial AccountingAccountingISBN:9781337119207Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning