Case summary:
The continental luggage company manufactures the best selling Trotter and various other types of luggage. The process of producing Trotter includes five stages of assembly. The company decides to implement the process control procedure that includes inspecting the working in each stage of assembly.
To explain: The impact of quality improvement program on the product yield of the company.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Plastomer, Inc., specializes in the manufacture of high-grade plastic film used to wrap food products. Film is rejected and scrapped for a variety of reasons (e.g., opacity, high carbon content, incorrect thickness or gauge, scratches, etc.). During the past month, management collected data on the types of rejects and the amount of scrap generated by each type. The following table presents the results:
Type of Failure
Amount of Scrap (lbs.)
Air bubbles Bubble breaks Carbon content Unevenness Thickness or gaugeOpacity ScratchesTrim Wrinkles
50019,6501503,81027,6004503,84050010,650
Draw a Pareto chart to identify which type of failure management should attempt to eliminate first.
Abernathy, Inc., produces two different generators and is concerned about their quality. The company has identified the following quality activities and costs associated with the two products:
Generator A
Generator B
Units produced
170,000
340,000
Warranty work (units)
1,700
850
Scrapped units (number)
3,400
850
Inspection (hours)
3,400
1,700
Quality training (hours)
85
85
Activities:
Performing warranty work
$816,000
Scrapping units
612,000
Inspecting
306,000
Quality training
85,000
Required:
1. Calculate the quality cost per unit for each product, and break this unit cost into quality cost categories. If required, round your answers to the nearest cent.
Generator A
Generator B
Unit cost
$fill in the blank 1
$fill in the blank 2
Flextronchip, an OEM manufacturer, has a fifth-generation chip for cell phones, with chip specification of 0.2 ± 0.0002 mm for the distance between two adjacent pins. The loss due to a defective chip has been estimated as $28.
Required:
1. Compute the value of k, the cost coefficient in the Taguchi quality loss function (QLF), L(x) = k(x − T)2.
2. Assume that the quality control manager takes a sample of 100 chips from the production process. The results are as follows:
Measurement
Frequency
0.1996
2
0.1997
6
0.1998
14
0.1999
9
0.2000
45
0.2001
9
0.2002
8
0.2003
5
0.2004
2
a. & b. Use the appropriate Taguchi quality loss function, L(x), to calculate the estimated quality loss for each of the observed measurements. Additionally, calculate the expected (i.e., average) loss per unit for the production process as a whole.
Chapter 2 Solutions
OPERATIONS AND SUPPLY CHAIN MANAGEMENT
Ch. 2 - Prob. 2.1ASCCh. 2 - Prob. 3.1ASCCh. 2 - Prob. 4.1ASCCh. 2 - Prob. 5.1ASCCh. 2 - Prob. 6.1ASCCh. 2 - Prob. 7.1ASCCh. 2 - Prob. 8.1ASCCh. 2 - Prob. 9.1ASCCh. 2 - Prob. 10.1ASCCh. 2 - Prob. 11.1ASC
Ch. 2 - Prob. 13.1ASCCh. 2 - Prob. 1QCh. 2 - Prob. 2QCh. 2 - Prob. 3QCh. 2 - Prob. 4QCh. 2 - Prob. 5QCh. 2 - Prob. 6QCh. 2 - Prob. 8QCh. 2 - Prob. 9QCh. 2 - Prob. 10QCh. 2 - Prob. 12QCh. 2 - Prob. 13QCh. 2 - Prob. 14QCh. 2 - Prob. 15QCh. 2 - Prob. 17QCh. 2 - Prob. 21QCh. 2 - Prob. 22QCh. 2 - Prob. 23QCh. 2 - Prob. 24QCh. 2 - Prob. 25QCh. 2 - Prob. 26QCh. 2 - Prob. 27QCh. 2 - Prob. 28QCh. 2 - Prob. 29QCh. 2 - Prob. 30QCh. 2 - Most students live in a dormitory or apartment...Ch. 2 - Prob. 32QCh. 2 - Describe, in general, how the J.D. Power Circle...Ch. 2 - Select a product that you own (like a cell phone,...Ch. 2 - Prob. 35QCh. 2 - Prob. 36QCh. 2 - Prob. 37QCh. 2 - Prob. 38QCh. 2 - Prob. 39QCh. 2 - Prob. 40QCh. 2 - Prob. 41QCh. 2 - Prob. 42QCh. 2 - Prob. 43QCh. 2 - Prob. 44QCh. 2 - Prob. 45QCh. 2 - Prob. 47QCh. 2 - Prob. 48QCh. 2 - Prob. 49QCh. 2 - Prob. 50QCh. 2 - Prob. 51QCh. 2 - Prob. 55QCh. 2 - Prob. 56QCh. 2 - Prob. 57QCh. 2 - Prob. 60QCh. 2 - Prob. 61QCh. 2 - Prob. 67QCh. 2 - Prob. 68QCh. 2 - Prob. 1PCh. 2 - The Backwoods American company in Problem 2-1...Ch. 2 - Prob. 3PCh. 2 - In Problem 2-3, if the direct manufacturing cost...Ch. 2 - Prob. 5PCh. 2 - The Colonial House Furniture Company manufactures...Ch. 2 - Prob. 8PCh. 2 - Prob. 9PCh. 2 - Prob. 10PCh. 2 - Prob. 11PCh. 2 - Prob. 12PCh. 2 - Prob. 14PCh. 2 - Prob. 1.1CPCh. 2 - Prob. 2.1CPCh. 2 - Prob. 3.1CPCh. 2 - Prob. 3.3CPCh. 2 - Prob. 3.4CPCh. 2 - Prob. 3.5CPCh. 2 - Prob. 3.6CPCh. 2 - Prob. 3.7CPCh. 2 - Prob. 3.8CPCh. 2 - Prob. 4.1CP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- As part of an insurance company’s training program, participants learn how to conduct an analysis of clients’ insurability. The goal is to have participants achieve a time in the range of 30 to 45 minutes. Test results for three participants were the following: Armand, a mean of 36.0 minutes and a standard deviation of 2.0 minutes; Jerry, a mean of 37.0 minutes and a standard deviation of 2.0 minutes; and Melissa, a mean of 37.5 minutes and a standard deviation of 2.6 minutes. a.Compute process capability for the participants and determine whether each is capable, given 4-sigma quality standards. (Do not round intermediate calculations. Round your answers to 2 decimal places.)arrow_forwardAs part of an insurance company’s training program, participants learn how to conduct an analysis of clients’ insurability. The goal is to have participants achieve a time in the range of 30 to 45 minutes. Test results for three participants were the following: Armand, a mean of 36.0 minutes and a standard deviation of 3.0 minutes; Jerry, a mean of 34.0 minutes and a standard deviation of 2.0 minutes; and Melissa, a mean of 37.5 minutes and a standard deviation of 1.7 minutes. a.Compute process capability for the participants and determine whether each is capable. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Melissa ? Cp what is itarrow_forwardManagement of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time- 0.7 daysWait time (from order to start of production) -16.6 daysProcess time -2.7 daysMove time -1.3 daysQueue time- 4.5 daysRequired:1. Compute the throughput time. (Round your answer to 1 decimal place.) 2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your answer to the nearest whole percentage (i.e., 0.12 should be entered as 12).) 3. What percentage of the throughput time was spent in non–value-added activities? (Round your answer to the nearest whole percentage (i.e., 0.12 should be entered as 12).) 4. Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.) 5. If by using Lean Production all queue…arrow_forward
- An automobile manufacturer plans to spend one billion dollars to improve the quality of a new model. The manufacturer expects the quality improvement program to eliminate the need for recall and reduce the costs for warranty repairs. The manufacturer’s experience has been, on average, 1.5 recalls for each new model at a cost of $300 per vehicle per recall. The average cost per recall, if one is needed, is expected to increase by 10% for the new model. Costs for other warranty repairs are expected to decrease from $200 to $80 per unit. Sales of the new model were expected to be 500,000 units without the quality-improvement program. The firm believes that the proposed, well-advertised quality program expected to cost an additional $50 million will increase total sales to 650,000 units. The gross profit per unit on the new model sold is $5,000. Required: Would you recommend the proposed quality-improvement program? Please show all your computations to support your answer.arrow_forwardAn automobile manufacturer plans to spend one billion dollars to improve the quality of a new model. The manufacturer expects the quality improvement program to eliminate the need for recall and reduce the costs for warranty repairs. The manufacturer’s experience has been, on average, 1.5 recalls for each new model at a cost of $300 per vehicle per recall. The average cost per recall, if one is needed, is expected to increase by 10% for the new model. Costs for other warranty repairs are expected to decrease from $200 to $80 per unit. Sales of the new model were expected to be 500,000 units without the quality-improvement program. The firm believes that the proposed, well-advertised quality program expected to cost an additional $50 million will increase total sales to 650,000 units. The gross profit per unit on the new model sold is $5,000.arrow_forwardA production operation is making 150 units of a product by engaging five workers for 300 hours. However, 40 percent of the units appear to have various quality problems, and the company decides to sell them as seconds at a price of £50 each when a normal unit is sold for £150. To improve the situation, several initiatives are proposed, including a scheme where, for every improvement, 50 percent will be given to workers and the other 50 percent will be held by the company. This results in a significant drop in defects as now only 10 units are faulty out of an output of 130 units. a) Compare the productivity after Bonus with the initial productivity b) Determine the appropriate bonus per hour for the workers under the bonus scheme if the cost per piece is £70 both before and after the scheme.arrow_forward
- Vilfredo Pareto was a famous engineer/economist in the 19th and early 20th centuries. He reportedly expressed this 80/20 Rule: 80% of all progress results from 20% of the actions taken. The Pareto Diagram, also called a Juran Diagram, depicts a variant 80/20 Rule: 80% of all production problems come from 20% of the problem areas. a. What kind of statistical chart is the Pareto Diagram? ____ (enter H for histogram, P for probability distribution, T for a Taguchi chart, A for all three of these. N for none of these. b. The value of the Pareto Diagram is its highlighting the areas causing 80% of quality problems. ____ (enter T for true or F for false)arrow_forwardAn airline company wishes to reduce the customer waiting time at the gates at a major airport using Taguchi Design of Experiments. The management decides to use Taguchi design of experiments for this project. Control Factors Level 1 Level 2 Assigned seating Yes (Y) No (N) Number of check-in bags allowed 1 2 Food and beverage supply on flight Beverage only (B) Food and Beverage (FB) Since there are 3 control factors with 2 levels in each, a total of 8 “runs” are possible. However, since performing the experiment with all possible runs is time-consuming, the management decides to consider only 4 runs. The noise factors are four different gates assigned to the airline. The experiment data is shown in the following table: Assigned Bags Food/Bev Gate 1 Gate 2 Gate 3 Gate 4 Y 1 B 31 27 29 32 Y 2 FB 46 40 38 35 N 1 FB 31 29 28 37 N 2 B 45 43 42 41 Make recommendations to the…arrow_forwardBoston Electric Generators has been getting manycomplaints from its major customer, Home Station, about thequality of its shipments of home generators. Daniel Shimshak,the plant manager, is alarmed that a customer is providing himwith the only information the company has on shipment quality.He decides to collect information on defective shipments througha form he has asked his drivers to complete on arrival at customers'stores. The forms for the first 279 shipments have been turnedin. They show the following over the past 8 weeks: Even though Daniel increased his capacity by adding more workersto his normal contingent of 30, he knew that for many weekshe exceeded his regular output of 30 shipments per week. Areview of his turnover over the past 8 weeks shows the following: a) Develop a scatter diagram using total number of shipmentsand…arrow_forward
- Super metals manufacturing company very competitive metal products business. It employs over 2,000 people. Because of the similarity in the product design and the competitive prices with those of its competitors, it maintains it’s market share by emphasizing quality and service. About a year ago the company lost two of its customers who had been dissatisfied with excessive manufacturing defects. After studying the problem, the company decided that its basic engineering was sound but carelessness and lack of quality consciousness on the part of production workers, inspectors and manufacturing supervisors were the prime cause of the trouble. Accordingly, it introduced a quality control training program to solve the problem. The course was given after working hours from 7 to 9 pm each Thursday for 10 weeks. Employees were not paid any additional amounts to attend the class. Technically attendance was voluntary. However, management intimated that employees who attend sincerely would…arrow_forwardSuper metals manufacturing company very competitive metal products business. It employs over 2,000 people. Because of the similarity in the product design and the competitive prices with those of its competitors, it maintains it’s market share by emphasizing quality and service. About a year ago the company lost two of its customers who had been dissatisfied with excessive manufacturing defects. After studying the problem, the company decided that its basic engineering was sound but carelessness and lack of quality consciousness on the part of production workers, inspectors and manufacturing supervisors were the prime cause of the trouble. Accordingly, it introduced a quality control training program to solve the problem. The course was given after working hours from 7 to 9 pm each Thursday for 10 weeks. Employees were not paid any additional amounts to attend the class. Technically attendance was voluntary. However, management intimated that employees who attend sincerely would…arrow_forwardSuper metals manufacturing company very competitive metal products business. It employs over 2,000 people. Because of the similarity in the product design and the competitive prices with those of its competitors, it maintains it’s market share by emphasizing quality and service. About a year ago the company lost two of its customers who had been dissatisfied with excessive manufacturing defects. After studying the problem, the company decided that its basic engineering was sound but carelessness and lack of quality consciousness on the part of production workers, inspectors and manufacturing supervisors were the prime cause of the trouble. Accordingly, it introduced a quality control training program to solve the problem. The course was given after working hours from 7 to 9 pm each Thursday for 10 weeks. Employees were not paid any additional amounts to attend the class. Technically attendance was voluntary. However, management intimated that employees who attend sincerely would…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.