The equivalent of a new kindergarten class is born every day at Orlando’s Arnold Palmer Hospital. With more than 13,000 births in the mid-2000s in a hospital that was designed 15 years earlier for a capacity of 6,500 births a year, the newborn intensive care unit was stretched to the limit. Moreover, with continuing strong population growth in central Florida, the hospital was often full. It was clear that new facilities were needed. After much analysis,
The vice president of business development, Karl Hodges, wanted a hospital that was designed from the inside out by the people who understood the Guiding Principles, who knew most about the current system, and who were going to use the new system, namely, the doctors and nurses. Hodges and his staff spent 13 months discussing expansion needs with this group, as well as with patients and the community, before developing a proposal for the new facility. An administrative team created 35 user groups, which held over 1,000 planning meetings (lasting from 45 minutes to a whole day). They even created a ‘Supreme Court’ to deal with conflicting views on the multifaceted issues facing the new hospital.
The vice president of business development, Karl Hodges, wanted a hospital that was designed from the inside out by the people who understood the Guiding Principles, who knew most about the current system, and who were going to use the new system, namely, the doctors and nurses. Hodges and his staff spent 13 months discussing expansion needs with this group, as well as with patients and the community, before developing a proposal for the new facility. An administrative team created 35 user groups, which held over 1000 planning meetings (lasting from 45 minutes to a whole day). They even created a “Supreme Court” to deal with conflicting views on the multifaceted issues facing the new hospital.
Funding and regulatory issues added substantial complexity to this major expansion, and Hodges was very concerned that the project stay on time and within budget Tom Hyatt, director of facility development, was given the task of onsite manager of the $103 million project, in addition to overseeing ongoing renovations, expansions, and other projects. The activities in the multiyear project for the new building at Arnold Palmer are shown in Table 3.7.
*This list of activities is abbreviated for purposes of this case study. For simplification, assume each week = . 25 months (i.e., 2 weeks = . 5 month, 6 weeks = 1.5 months, etc.).
4. What percent of the whole project duration was spent in planning that occurred prior to the proposal and reviews? Prior to the actual building construction? Why?
Want to see the full answer?
Check out a sample textbook solutionChapter 3 Solutions
Operations Management
Additional Business Textbook Solutions
Operations and Supply Chain Management 9th edition
Operations Management, Binder Ready Version: An Integrated Approach
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Principles Of Operations Management
Business in Action (8th Edition)
Business in Action
- SPANISH AIRPORT Inside the abandoned Spanish airport that cost £1billion to build An airport in Spain has been abandoned for years The Ciudad Real Airport opened in 2008, only for it to close three years later. The Ciudad Real Airport hoped to be an alternative to Madrid Airport. The airport, which was meant to handle overflow from Madrid’s Barajas airport, cost some €1.1 billion to build, including a large amount of public funding for infrastructure. The site is next to a town of just 72,000 people on the sparsely populated Castilian plain and lies more than 140 miles from Madrid. It was even named after Don Quixote, the deluded Castilian gentleman of Cervantes’s famous novel before wiser heads renamed it simply “Central”. Although launched by local private investors, the project has been fully supported by the regional government of Castilla La Mancha and was financed by Caja Castilla La Mancha (CCM), the regional savings bank, or caja. A huge Don Quixote-themed attraction was…arrow_forwardSPANISH AIRPORT Inside the abandoned Spanish airport that cost £1billion to build An airport in Spain has been abandoned for years The Ciudad Real Airport opened in 2008, only for it to close three years later. The Ciudad Real Airport hoped to be an alternative to Madrid Airport. The airport, which was meant to handle overflow from Madrid’s Barajas airport, cost some €1.1 billion to build, including a large amount of public funding for infrastructure. The site is next to a town of just 72,000 people on the sparsely populated Castilian plain and lies more than 140 miles from Madrid. It was even named after Don Quixote, the deluded Castilian gentleman of Cervantes’s famous novel before wiser heads renamed it simply “Central”. Although launched by local private investors, the project has been fully supported by the regional government of Castilla La Mancha and was financed by Caja Castilla La Mancha (CCM), the regional savings bank, or caja. A huge Don Quixote-themed attraction was…arrow_forwardSPANISH AIRPORT Inside the abandoned Spanish airport that cost £1billion to build An airport in Spain has been abandoned for years The Ciudad Real Airport opened in 2008, only for it to close three years later. The Ciudad Real Airport hoped to be an alternative to Madrid Airport. The airport, which was meant to handle overflow from Madrid’s Barajas airport, cost some €1.1 billion to build, including a large amount of public funding for infrastructure. The site is next to a town of just 72,000 people on the sparsely populated Castilian plain and lies more than 140 miles from Madrid. It was even named after Don Quixote, the deluded Castilian gentleman of Cervantes’s famous novel before wiser heads renamed it simply “Central”. Although launched by local private investors, the project has been fully supported by the regional government of Castilla La Mancha and was financed by Caja Castilla La Mancha (CCM), the regional savings bank, or caja. A huge Don Quixote-themed attraction was…arrow_forward
- *(e) Draw manually the appropriate network diagram (using PDM) and then find (and also provide as a table) for each of the activities by d: early start (ES), early finish (EF), late start (LS), late finish (LF) and total floats and total slacks and provide them in a table form. Answer:arrow_forward4 demand trends of a shopping mall in new york? the points should be positive so the investor is interested to investarrow_forwardNamibia: Walvis Bay Port is now a regional logistic hubThe new container terminal at the Namibian Port of Walvis Bay, built between 2014 and 2019, gives thecountry a high-end port facility. The terminal, commissioned in August 2019, is now fully operational,according to a report by the African Development Bank published on 3 September 2020. The port is expandedon 40 hectares of reclaimed land, costing nearly $300 million. The works included the dredging of over 3.9million cubic metres of sand, used partly for reclamation, construction of a 600-metre quay wall, laying304,000 square metres of paved surface, and the construction of a workshop and administrative buildings.It also entailed the installation of four ship-to-shore (STS) cranes, the construction of a one-kilometre road,the laying of 2.3 km of rail lines, and the installation of service networks. The facility's electricity supply wasalso successfully upgraded, the report noted. The expansion increased the terminal's capacity…arrow_forward
- Namibia: Walvis Bay Port is now a regional logistic hubThe new container terminal at the Namibian Port of Walvis Bay, built between 2014 and 2019, gives thecountry a high-end port facility. The terminal, commissioned in August 2019, is now fully operational,according to a report by the African Development Bank published on 3 September 2020. The port is expandedon 40 hectares of reclaimed land, costing nearly $300 million. The works included the dredging of over 3.9million cubic metres of sand, used partly for reclamation, construction of a 600-metre quay wall, laying304,000 square metres of paved surface, and the construction of a workshop and administrative buildings.It also entailed the installation of four ship-to-shore (STS) cranes, the construction of a one-kilometre road,the laying of 2.3 km of rail lines, and the installation of service networks. The facility's electricity supply wasalso successfully upgraded, the report noted. The expansion increased the terminal's capacity…arrow_forwardSouth Hampton University is preparing its budget for the upcoming academic year. This is a specialised private university that charges fees for all degree courses. Currently, 30,000 students are enrolled on campus. However, the university is forecasting a 5 per cent growth in student numbers in the coming year, despite an increase in fees to $3,000 per subject. The following additional information has been gathered from an examination of university records and conversations with university managers: South Hampton is planning to award scholarships to 200 students, which will cover their fees. The average class has 80 students, and the typical student takes 4 subjects per semester. South Hampton operates 2 semesters per year. The average academic staff salary is $120,000 per annum including on-costs. South Hampton’s academic staff are evaluated on the basis of teaching, research, administration and professional/community service. Each of the academic staff teaches the equivalent…arrow_forwardWhy does a feasibility study need so much time and effort?arrow_forward
- *(e) Draw manually the appropriate network diagram (using PDM) and then find (and also provide as a table) for each of the activities by d: early start (ES), early finish (EF), late start (LS), late finish (LF) and total floats and total slacks and provide them in a table form.arrow_forwardA competitor of Kozar International, Inc. has begun marketing a new instant-developing film project. Kozar has had a similar product under study in its R&D department but has not yet been able to begin production. Because of the competitor's action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are shown in the following columns. Immediate Optimistic Most Probable Pessimistic Activity Predecessor(s) Time Time Time A — 3.5 5 6.5 B A 1.5 3 4.5 C A 2 4 6 D B, C 3.5 4.5 8.5 E B 1 3 5 F C, D 7.5 8.5 12.5 G E, F 6 8 10 Compute expected times and variances for each activity. Round your answers for the expected times to nearest whole number and for the variances to two decimal places. Activity Mean Variance A B C D E F G…arrow_forwardDepartment of Health getting the highest executive budget this 2021 National Budget because of this COVID-19 pandemic. - What are the projects and programs that needed to be implement? Are these revenue expenditures or capital expenditures?- Is it for long term or by phase implementation?- Where are the locations of the projects? Urban areas or rural areas?- How long do you see the department getting the lion's share? Justify the forecast.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.