Principles Of Operations Management
11th Edition
ISBN: 9780135173930
Author: RENDER, Barry, HEIZER, Jay, Munson, Chuck
Publisher: Pearson,
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 16DQ
How is the variance of the total project computed in PERT?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
How is the variance of the total project computed inPERT?
Define Time–Cost Models and Project Crashing?
Considering the Project Details;
1.Construct the Project Network Diagram
2.Find the Expected Duration and Standard Deviation and Variance of each Activity
3.Find the Critical path and Expected Project Completion Time
Chapter 3 Solutions
Principles Of Operations Management
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The expected time and variances for the major activities of an R&D project are depicted in the following PERT chart. Determine the probability that the project completion time will be: A. Less than 50 weeks B. More than 50 weeksarrow_forward- Draw the project network diagram. - What completion date would you recommend?arrow_forwardWhat is the importance of variance analysis to project managers? Give 2 examples.arrow_forward
- Given the following table, construct a network diagram, either AOA or AON. Times are in days.a. Determine the expected duration of the project.b. Compute the probability that the project will take at least 18 days.Path Activity Time EstimatesA 4-5-6Top B 7-8-10C 3-5-9D 7-8-11Bottom E 2-3-4F 1-4-6arrow_forwardDetermine the probability that the project will take less than 42 weeks.arrow_forwarda) Determine the expected completion time and variance for each activity. b) Determine the total project completion time and the critical path for the project. c) Determine ES, EF, LS, LF, and slack for each activity. d) What is the probability that Kelle Carpet and Trim will finish the project in 40 days or less?arrow_forward
- What are the primary components of process planning in project management, and how do they contribute to the successful execution of a project?arrow_forward2) Following is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded By Regular Crash Regular Crash A -- 6 days 2 day $2000 $3800 B -- 12 6 2000 10000 C A 4 2 1000 4000 D B, C 10 6 3400 4600 E D 8 6 2800 3900 F E 6 2 5000 7600 G B, C 18 8 16000 19600 H F, G 6 4 2000 4000 (a) Construct a network including the Early and Late Start and Finish times. (b) Identify the normal Critical Path(s) and the normal expected completion time (c) Can the project be crashed to last 18 days? Which activities should be crashed and at what additional cost?arrow_forward(2) Following is a table listing the project activities, sequencing requirements and other relevant information: Expected Time Direct Cost Activity Preceded By Regular Crash Regular Crash A -- 6 days 2 days $2000 $3800 B -- 12 6 2000 10000 C A 4 2 1000 4000 D B,C 10 6 3400 4600 E D 8 6 2800 3900 F E 6 2 5000 7600 G B, C 18 8 16000 19600 H F, G 6 4 2000 4000 Construct a network including the early and late start and finish times. Identify the normal critical path (s) and the normal expected completion time. Can the project be crushed to last 18 days? Which activities should be crushed and what additional cost?arrow_forward
- PERT-CPMYu and Mi Company is planning to computerize its accounting system. Its IT consultant has determined thefollowing activities required to complete this project together with the time estimates and precedence relationships. a. Determine the expected project completion time and the variance.b. What is the project’s critical path?c. Determine the probability that the project will be completed in 40 weeks or less.arrow_forward1. CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL PATH AND ITS DURATION 4. CREATE A GANTT CHART STARTING JANUARY 1, 2021. NO DAY-OFFS 5. WHEN WILL THE PROJECT BE COMPLETED?arrow_forwardThe following six activities constitute an overall bar chart portrayal of 4-month project. Two months after the start of construction, Activities A, C, D half of E, and one-fourth of B were completed, for a cost of $10,500. Evaluate the status of the project. Using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead of or behind schedule.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY