Textbook Question
Chapter 3, Problem 22P
Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger Tides (starring Johnny Depp), identified 16 activities to be completed before the release of the film.
a) How many weeks in advance of the film release should Four Squares have started its marketing campaign? What is the critical path? The tasks (in time units of weeks) are as follows:
b) What is the probability of completing the marketing campaign in the time (in weeks) noted in pan a?
c) If activities I and J were not necessary, what impact would this have on the critical path and the number of weeks needed to complete the marketing campaign?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A Social Project manager is faced with a project with the following activities:
Activity-ID Description Duration
1-2 Social Work Team to live in Village 5 Weeks
1-3 Social Research Team to do survey 12 Weeks
3-4 Analyse results of survey 5 Weeks
2-4 Establish Mother & Child Health Program 14 Weeks
3-5 Establish Rural Credit Programme 15 Weeks
4-5 carry out Immunisation of under Fives 4 Weeks
Draw the arrow diagram, using the helpful numbering of the activities, which suggests the…
A toy manufacturing company is in the process of designing and subsequently launching a new toy. The process consists of seven activities with predecessor activity relationships and activity time estimates as follows:
Activity
Description
Predecessor activity
Duration
(Weeks)
A
Design prototype
-
2
B
Build prototype
A
3
C
Order parts
B
2
D
Prepare for production
B
4
E
Prepare for marketing
B
5
F
Assembly and testing
C, D
2
G
Launch
E, F
1
a. Draw the critical path diagram
b. Determine the early start, early finish, late start, and late finish times
c. Show critical path and determine its duration
d. Determine the slack for each activity
Four Squares Productions, a firm hired to coordinate the release of the movie Pirates oft he Caribbean: Dead Men Tell No Tales (starring Johnny Depp), identified 16 activities to becompleted before the release of the film. a) How many weeks in advance of the film release should Four Squares have started its marketing campaign? What is the critical path? The tasks (in time units of weeks) are asfollows:b) What is the probability of completing the marketing campaign in the time (in weeks) noted in part a?c) If activities I and J were not necessary, what impact would this have on the critical path and the number of weeks needed to complete the marketing campaign?
Chapter 3 Solutions
Principles Of Operations Management
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______arrow_forwardFour Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger Tides (starring Johnny Depp), identified 16 activities to be completed before the release of the film. The appropriate data are shown in the following table: Time (weeks) Immediate Time (weeks) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 1.0 2.0 4.0 — I 10.5 13.0 14.0 C B 2.0 3.5 6.0 — J 2.0 4.0 6.0 C C 10.0 12.0 14.0 — K 2.0 4.0 6.0 D D 4.0 5.0 7.0 — L 3.0 5.0 7.0 E E 2.0 4.0…arrow_forwardThe activities described by the following table are given for the Howard Corporation in Kansas: a) Draw the appropriate AON PERT diagram for J.C. Howard's management team.b) Find the critical path.c) What is the project completion time?arrow_forward
- An architect has been awarded a contract to prepare plans for an urban renewal project. The job consists of the following activities and their estimated value. Draw a critical path arrow diagram for this project, indicate the critical path and calculate the total slack and free slack for each activity. Job Description Predecessor Expected time in days A Prepare preliminary sketches NA 2 B Outline specifications NA 1 C Prepare drawings A 3 D Write specifications A B 2 E Run prints C D 1 F Have specifications printed B D 3 G Assemble bid package E F 1arrow_forwardTo complete the rotor assembly for an experimental spacecraft, Gilbert has laid out nine major activities involved. These activities have been labelled A to I in the table below, which also shows their estimated completion times (in weeks) and their immediate predecessors. EVENTS AND ACTIVITIES FOR ROTOR ASSEMBLY ACTIVITIES TIMES (IN WEEKS) PRECEDING EVENT A M B A 1 2 3 - B 2 3 4 A C 4 5 6 A D 8 9 10 A E 2 5 8 B F 4 5 6 B, C G 1 2 3 F, D H 1 3 5 E, F I 2 4 6 H, G Key: A is optimist time, M is the most likely time and B is the pessimistic time. a) Calculate the expected time for each activity b) Draw a Gantt Chart from the same information above c) State the critical path and the maximum number of weeks the project will take to be completed. d) Discuss the pros and cons of using the Gantt chart as a planning and scheduling tool?arrow_forwardReliable Garage is completing production of the J2000 kit car. The following data are available for the project:a. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?arrow_forward
- Reliable Garage is completing production of the J2000 kit car. The following data are available for the project:a. Draw the network diagram for the project. b. Determine the project’s critical path and duration. c. What is the slack for each activity?arrow_forwardTask time estimates for the modificat ion of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: a) Draw the project network using AON.b) Identify the critical path.c) What is the expected project completion time?d) Draw a Gantt chart for the project.arrow_forwardMake a list of the tasks that is necessary for Management Trainee Officer job in private banks. Develop a table showing each task, its duration, and preceding event(s). Develop a Network diagram for these tasks. Highlight the critical path on your Network diagram and find out slack of all activities.arrow_forward
- Farihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.arrow_forwardBased on the table above, draw a complete Activity-in-the-Box network diagram using the ID's to represent each activity.arrow_forwardTask time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Time (in hours) Immediate Predecessor(s) A 5.0 - B 6.5 - C 5.0 A D 5.0 B, C E 4.0 B, C F 7.5 D G 4.0 E, F This exercise contains only parts d, b, and c. d) Using the line drawing tool five times, draw a Gantt chart for activities C through G of the project based on the early times. Carefully follow the instructions above, and only draw the required objects. b) The critical path activities for the leadership training program development project are c) The expected project completion time for the leadership training program development project = hours (round your response to one decimal place).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY