Question
Chapter 3, Problem 25P
a)
Summary Introduction
To draw: The PERT diagram.
b)
Summary Introduction
To determine: The critical path and project completion time.
c)
Summary Introduction
To determine: The probability at which the project will take more than 49 time periods to complete.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Janice Eliassen must complete the activities in the following table to fin ish her consulting project. a) Draw the appropriate PERT diagram.b) Find the critical path and project completion time.c) Find the probability that the project will take more than49 time periods to complete.
M2: prepare and update a project management plan, using standard systems of time and resource tracking.
can the answer for above question include a Gantt chart of a construction project please?
Three activities are candidates for crashing on a projectnetwork for a large computer installation (a ll are, of course, critical).Activity details are in the following table: a) What action would you take to reduce the critical path by I day?b) Assuming no other paths become critical, what action would you take to reduce the critical path one additional day?c) What is the total cost of the 2-day reduction?
Chapter 3 Solutions
Principles Of Operations Management
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Task time estimates for the modificat ion of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: a) Draw the project network using AON.b) Identify the critical path.c) What is the expected project completion time?d) Draw a Gantt chart for the project.arrow_forwarda. Draw the precedence diagram b. What is the probability that the project can be completed in 24 days or less? In 21 days or less?arrow_forwardGreenzTech Inc. is planning on installing a new computerised accounting system. For thisproject, they have established the following activities, precedence relationships, and timeestimates in weeks:a. Draw the network diagramb. Calculate the expected time for each activity.c. Calculate the variance of each activityd. Based on the calculation of estimated times, what is the critical path?e. What is the estimated time of the critical path?f. What is the activity variance along the critical path?g. What is the probability of completion of the project within 50 weeks or less?arrow_forward
- A. Create the NETWORK DIAGRAM B. Theprocesses that are included in the critical path are: for example A-B-C-D C.The total number of days to finish the project is within how many days?arrow_forward3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the nodenumbers in circles and draw arrows from node to node, labelling each arrow with theactivity letter and estimated duration. 3.2 Identify all the paths on the network diagram and note how long they are. 3.3 What is the critical path for this project and how long is it? 3.4 What is the shortest possible time needed to complete the project?arrow_forwardConsider the following data for a project to install a new server at the Northland Pines High School: a. Draw the network diagram.b. Calculate the critical path for this project.c. How much slack is in each of the activities G, H, and I?arrow_forward
- The activities described by the following table are given for the Howard Corporation in Kansas: a) Draw the appropriate AON PERT diagram for J.C. Howard's management team.b) Find the critical path.c) What is the project completion time?arrow_forwardA senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Draw the project network. What is the minimum time required to finish the project? State the critical path. Activity Time (week) Immediate Predecessor A. Find client 4 --- B. Write prospectus 2 A C. Obtain approval from client and professor 3 B D. Complete programming 12 C E. Do industry background research 10 --- F. Write final paper 6 D, E G. Write oral report 5 D, Earrow_forwardYour hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed in 18 weeks, before the next Joint Commission survey. Project activity times are listed in the table that is attached as an image. a) Draw the network diagram.b) Identify all project paths. Which path is the critical path and why?c) What is the project completion time and total project costs if only normal times are used? Activityarrow_forward
- Using the below table calculate critical path for the project. Which tasks are on the critical path? Task Predecessor Duration (Weeks) A - 32 B - 11 C - 12 D B,C 16 E A,B 23 F A 23 G D 22 H D 33arrow_forwardAn advertising project manager developed the network diagram shown in Figure 2.10 for a new advertising campaign. In addition, the manager gathered the time information for each activity, as shown in the accompanying table. a. Calculate the expected time and variance for each activity. b. Calculate the activity slacks and determine the critical path, using the expected activity times. c. What is the probability of completing the project within 23 weeks?arrow_forwardA plumber has decided to use the techniques of project management in order to plan a job. He knew all the different activities of the job, their precedence and their average durations. They are shown on the table below. Activity Duration (days) Preceding activities A 3 None B 3 None C 4 A D 8 A E 2 B and C Required: 1. Draw a network diagram representing the sequence of activities and the dependence between them. 2. Determine how long it will take to complete the job by conducting the forward pass 3. By conducting the backward pass, identify the critical path and the non-critical path(s). Note: The work for this task should be produced using Word drawing facilities. The forward and backward passes should be clearly shown on the diagram. The calculations should be shown next to the network diagram.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY