The work breakdown structure (WBS) for building a house (levels 1 and 2) is shown below:
- a. Add two level-3 activities to each of the level-2 activities to provide more detail to the WBS.
- b. Select one of your level-3 activities and add two level-4 activities below it.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
The work breakdown structure (WBS) for building a house (levels 1 and 2) is shown below: a) Add two level-3 activities to each of the level-2 activities to provide more detail to the WBS. b) Select one of your level-3 activities and add two level-4 activities below it.
The work breakdown structure (WBS) for building a house (levels I and 2) is shown below: a) Add two level-3 activities to each of the level-2 activities to provide more detail to the WBS.b) Select one of your level-3 activities and add two level-4 activities below it.
The work breakdown structure (WBS) for build-ing a house (levels 1 and 2) is shown below: a) Add two level-3 activities to each of the level-2 activities toprovide more detail to the WBS.b) Select one of your level-3 activities and add two level-4activities below it.
Chapter 3 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - 3.2 Robert Day has decided to run for a seat as...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Stephen Hall is developing a program in supply...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - Bill Fennema, president of Fennema Hospitality,...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - The Tesla 6 is a new custom-designed sports car....Ch. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Develop a Work Breakdown Structure (WBS) for the following case study by using Top-down Approach. You are hired as a project manager to develop the Campus Management System (CMS) of a famous educational complex. CMS is designed to promote automated university administration and provides a medium for teachers, staff and administration to work in harmony. CMS has a complete role based access where in various resources are made available depending upon the role assigned. The Student module includes students to add, modify and view features designed to ease registration. The Academic Management module deals with academic history of the students and it allows determining student's expertise level through his obtained grades. The Fee Management module keeps track of fees paid and dues and allows printing of fee voucher. The Course Management module allows maintaining different courses, the respective instructors and session details. The Alerts and Notification module is email based alerts…arrow_forwardJames Lawson has decided to run for a seat as Congressman from the House of Representatives, District 34, in Florida. He views his 8-month campaign for office as a majorproject and wishes to create a work breakdown structure (WBS) to help control the detailed scheduling. So far, he has developed the following pieces of the WBS: Help Lawson by providing details where the blank lines appear. Are there any other major (Jevel-2) activities to create? If so, add an ID no. 1.6 and insert them.arrow_forwardFor this assignment you must pick 4 processes – one from each of the knowledge areas listed below. For each process, write a paragraph (or two) that describes the process, explains the key benefit of using the process, and describes a garden in my backyard that would benefit from using the process. Knowledge Areas: • Integration Management • Scope Management • Time Management • Cost Management In lieu of an individual process, you may also choose a group of closely related processes (e.g., define activities and sequence activities). In this case, you must describe both processes and both key benefits, but you can describe a single hypothetical project situation. Keep in mind that a group of related processes only counts as one process for the purposes of this assignmentarrow_forward
- Can we identify a specific area of difficulty being tackled by the workflow management tool?arrow_forwardYou are alone at home and have to prepare a bread sandwich for yourself. The following preparation activities and time taken are given in the table below: Task Description Predecessor Time (Minutes) A Purchase of bread - 20 B Take cheese and apply on bread A 5 C Get onions from freezer A 1 D Fry onions with pepper B,C 6 E Purchase sauce for bread - 15 F Toast bread B,C 4 G Assemble bread and fried onions F 2 H Arrange in plat G 1 Determine: a. While purchasing sauce, you met a friend and spoke to him for 6 minutes. Did this cause any delay in the preparation?arrow_forwardTwo techniques for reducing rework expenses should be provided. Consider the need of progressive delivery across both tactics.arrow_forward
- Power Builders Inc. is planning for an upcoming job with a large client. They have listed the specific activities and steps to be performed, and estimated the time to complete each activity. The activities involved in the job are listed below: Activity Description of Activity Preceding Activity Estimated Time Required (in weeks) A B C D E F G H I J K Planning Meeting Obtain Permit Inspect Damage Begin Repair Work Order Additional Materials Apply for Waiver Obtain Waiver Complete Electrical Work Build Interior Partitions Onsite Testing Meet With Client -- A B A D E C, F D H G, I J 5 2 5 4 2 4 2 5 5 2 2 REQUIRED: Prepare a Gantt Chart from the facts in this time budget.arrow_forwardKiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…arrow_forwardDescribe different ways to develop a WBS (Work Breakdown Structure) and explain why it is often so difficult to do.Describe different ways to develop a WBS (Work Breakdown Structure) and explain why it is often so difficult to do.arrow_forward
- The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: A- Time B- Code Description (hrs) Immediate Predecessor(s) C- A Find location; determine resource requirements 25 None Requisition of lumber and sand Dig and grade Saw lumber into appropriate sizes 55 A D- C 100 A E- 30 В E Position lumber in correct locations 20 D, C F- F Nail lumber together 10 E G- Put sand in and under the equipment Put dirt around the equipment G 25 F H F H- Put grass all over the garden, landscape, paint 35 G, H Refer to the legend for the activity that corresponds to each code. Using the line drawing tool, draw a Gantt chart for activities E through I of the project. 20 40 60 80 100 120 140 160 180 200 220arrow_forwardKiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40teddy bears per hour on its assembly line. The following information will assist in answering thequestions that follow: Task Information for Kiko Teddy Bear Work Element Task Description ImmediatePredecessor Task Time (inseconds)A Cut teddy bear pattern None 90B Sew teddy bear cloth A 75C Stuff teddy bear B 50D Glue on eyes C 20E Glue on nose C…arrow_forwardA Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY