Textbook Question
Chapter 3, Problem 2CS
TABLE 3.6 Southwestern University Project
2 What is the probability of finishing in 270 days?
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations.
Activity
Predecessor
Duration in Weeks
A
-
5
B
-
3
C
A, B
8
D
C
3
E
-
4
F
E
10
G
F
8
H
E
18
I
D
20
J
D, G, I
7
K
I
5
L
H
10
6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation:
the first pic:
First: Draw the precedence diagram.
Second: Using the notation given identify the duration of the project: you can type it.
Third: identify the critical part and explain the critical path.
Fourth: Explain your answer. This can be done by describing the process and the observations done once the answer has been found.
6B. Draw the project’s Gantt chart
First: The…
2. Given the data, answer the questions below.
Activity
Normal Time
Normal Cost
Crashed Time
Crashed Cost
(weeks)
(Pesos)
(weeks)
(Pesos)
1-2
12
30,000
7
50,000
2-3
8
20,000
35,000
2-4
4
40,000
3
70,000
3-4
4-5
4
5,000
1
11,000
4-6
12
500,000
9.
710,000
5-6
4
5,000
1
11,000
6-7
4
150,000
220,000
750,000
1,107,000
a. Suppose the project needs to be completed within 30 weeks, how much extra cost
will be incurred to finish the project by this time? Which activity/ies must be crushed?
b. If the project duration is reduced down to the minimum time possible, what is the total
number of crashed weeks? How much extra cost will this require?
Draw project network
Chapter 3 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - 3.2 Robert Day has decided to run for a seat as...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Stephen Hall is developing a program in supply...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - Bill Fennema, president of Fennema Hospitality,...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - The Tesla 6 is a new custom-designed sports car....Ch. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Determine the expected activity completion times, tearrow_forwardProblem 9-14 (Algorithmic) Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion date requested by the owner. The Davison project manager prepared the following project network: B F H Start C G Finish D E Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows: Activity Optimistic Most Probable Pessimistic A 4 9 14 B 5 7 3 4 D 8 11 14 7 17arrow_forwardQuestions 1. Develop the network for planning and construction of the new hospital at Arnold Palmer.2. What is the critical path, and how long is the project expected to take?3. Why is the construction of this 11-story building any more complex than the construction ofan equivalent office building?arrow_forward
- project developmental approach used in elliott bay sea wall rebuilding project and 3 reasons why it was usedarrow_forwardWhat is an Aggregate Project plan?arrow_forward• Q3: Draw the network diagram and determine the critical path for the following project: Activity Time estimate (Weeks) 1-2 1-3 6. 1-4 3 2-5 3-6 7 3-7 10 4 -7 4 5-8 2 6-8 7-9 6. 8-9 4arrow_forward
- Q1. Table 1 shows the activities involving a grant related project at national level that recommended for second year students of the Faculty of Defense Engineering, Universiti Pertahanan Malaysia. (a) Construct a project network diagram for Table 1 using the Arrow-On-Nodes (AON) method with all related calculations on the activities of Early Start (ES), Early Finish (EF), Late Start (LS), Late Finish (LF), and Slack (SL). (b) Determine the total completion time and the critical path of the project network diagram. (c) Discuss the impacts on the project completion, if the activity E is delayed. Table 1: Activity Time Estimates and Dependencies Immediate ID Activity Description Time (days) Predecessor(s) A Planning Determine the theme, select supervisor, select team Designing the product 75 None В Design 150 Planning Simulation and product analysis Procurement Purchasing raw materials and standard components Cutting, welding and manufacturing Fitting and components assembly Product…arrow_forwardCASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forwardCASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forward
- CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forwardCASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forwardCASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY