EBK OPERATIONS MANAGEMENT
11th Edition
ISBN: 8220103630726
Author: RENDER
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 3, Problem 22P
Rich Cole Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Cole requires 14 different activities. Cole’s managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table.
- a. What is the probability of being done in 53 days?
- b. What date results in a 99% probability of completion?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Rich Cole Control Devices, Inc., producescustom-built relay devices for auto makers. The most recentproject undertaken by Cole requires 14 different activities.Cole’s managers would like to determine the total projectcompletion time (in days) and those activities that lie alongthe critical path. The appropriate data are shown in the fol-lowing table.a) What is the probability of being done in 53 days?b) What date results in a 99% probability of completion?
PERT-CPMYu and Mi Company is planning to computerize its accounting system. Its IT consultant has determined thefollowing activities required to complete this project together with the time estimates and precedence relationships.
a. Determine the expected project completion time and the variance.b. What is the project’s critical path?c. Determine the probability that the project will be completed in 40 weeks or less.
a. Determine the expected activity completion times.
b. Identify the critical path.
*Please answer letter A and B above.
Note: to = optimistic, tm = most likely, and te = expected time.
Chapter 3 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - What would a project manager have to do to crash...Ch. 3 - Describe how expected activity times and variances...
Ch. 3 - Define earliest start, earliest Finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - What are dummy activities? Why are they used in...Ch. 3 - What are the three time estimates used with PERT?Ch. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - 3.2 Robert Day has decided to run for a seat as...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - 3.5 Using AOA, diagram the network described below...Ch. 3 - Stephen Hall is developing a program in supply...Ch. 3 - Task time estimates for the modification of an...Ch. 3 - 3.8 The City Commission of Nashville has decided...Ch. 3 - Refer to the table in Problem 3.8. a. Draw the AON...Ch. 3 - The activities needed to build a prototype laser...Ch. 3 - Dave Fletcher (see Problem 3.10) was able to...Ch. 3 - The activities described by the following table...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The following is a table of activities associated...Ch. 3 - Assume that the activities in Problem 3.15 have...Ch. 3 - Bill Fennema, president of Fennema Hospitality,...Ch. 3 - What is the minimum cost of crashing the following...Ch. 3 - Three activities are candidates for crashing on a...Ch. 3 - Development of Version 2.0 of a particular...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Rich Cole Control Devices, Inc., produces...Ch. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Using PERT, Adam Munson was able to determine that...Ch. 3 - Clark Products makes pizza ovens for commercial...Ch. 3 - The Tesla 6 is a new custom-designed sports car....Ch. 3 - TABLE 3.6 Southwestern University Project 1....Ch. 3 - TABLE 3.6 Southwestern University Project 2 What...Ch. 3 - TABLE 3.6 Southwestern University Project 3. If it...Ch. 3 - Project Management at Arnold Palmer Hospital Video...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - The equivalent of a new kindergarten class is born...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...Ch. 3 - At the Hard Rock Cafe, like many organizations,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Coleman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: Time (days) a m 3 7 1 2 6 4 Immediate b Predecessor(s) Activity Activity A B C D E F G a) The expected completion time of the project = 10 9 3 6 11 8 17 7 3 3 5 1 7 8 A A B, C D D H I J K L M N Time (days) a 5 1 3 6 3 1 6 m 5 5 6 8 4 Immediate b Predecessor(s) 6 10 7 11 6 3 3 8 11 E, F G, H I J K L, M days (round your response to two decimal places).arrow_forwardDevelopment of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Activity Time (weeks) Time (weeks) A B с D E F G 4 2 3 8 6 3 4 3 1 3 4 3 2 2 a) Based on the given information regarding the activities for the project, the project length = Normal Cost $2,000 $2,300 $600 $2,300 $900 $3,200 $1,500 weeks. Total Cost with Crashing Immediate Predecessor(s) $2,650 $2,900 $600 $2,600 $1,200 $4,400 $1,900 A B C D, Earrow_forwardThe following represents a project that should be scheduled using CPM: ACTIVITY A B C D E F G H IMMEDIATE PREDECESSORS A A B C, D D, E F,G b. What is the critical path? ⒸA-D-G-H OB-E-G-H ⒸA-C-F-H A-D-F-H Probability TIMES (DAYS) b Project completion time a 1 1 2 1 1 3 1 2 m 2 2 2 8 2 4 3 3 6 9 11 9 3 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 11 11 X Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.arrow_forward
- Earned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: No Type Cumulative Budgeted Cost (CBC) 2 Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) 1 3 TOTAL RM i. ii. iii. iv. 64,000 68,000 54,000 100,000 Percentage 64.0 Cost performance Index (CPI) [hint: CEV/CAC] Cost variance (VC) [hint: CEV-CAC] 68.0 54.0 a) Based on question 2(a), calculate and elaborate the various of indicators of cost performance for this project based on the respective below: 100.0 Forecasted cost of completion (FCAC) with action taken [hint: TBC/CPI] Forecasted cost of completion (FCAC) without any action taken [hint: CAC + [TBC-CEV]arrow_forwardA solved PERT problem is detailed in the table below. The expected time and variance values and the critical activities are given in the table below. Answer the following questions by filling the blanks (WRITE YOUR ANSWERS TO 2 DECIMAL PLACES. DO NOT ROUND UP OR DOWN): a. The expected project completion time for this problem is and the standard deviation is . b. There is a 0.95 probability that the project will be completed by weeks. Activity Expected time Variance Critical? A 10 0.36 Yes B 7 0.11 No C 7 0.25 No D 3 0.48 Yes E 5 1.60 Yes F 7 0.69 No G 2 3.69 Yesarrow_forwardColeman Rich Control Devices, Inc., produces custom-built relay devices for auto makers. The most recent project undertaken by Rich requires 14 different activities. Rich's managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table: Activity A B с D E F G a) The expected completion time of the project = a 4 1 6 5 1 2 1 Time (days) m 6 2 6 8 9 3 7 b 7 3 6 11 18 6 8 Immediate Predecessor(s) A A B, C D D Activity a H 4 I 1 J 2 K 8 2 1 6 M N days (round your response to two decimal places). Time (days) = m 4 6 5 9 4 2 8 b 6 8 7 11 6 3 10 Immediate Predecessor(s) E, F G, H K L, M The activities that represent the project's critical path are b) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in 53 days or less = decimal places). c) Using the standard normal table, the…arrow_forward
- Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Normal Crash Activity Time (weeks) Time (weeks) A B 3 1 3 4 3 2 2 a) Based on the given information regarding the activities for the project, the project length с D E F G 2 8 6 Normal Cost $2,100 $2,300 $500 $2,400 $900 $3,400 $1,600 weeks Total Cost with Crashing Immediate Predecessor(s) $2,700 $3,000 $500 $2,700 $1,350 $4,900 $2,200 С D, Earrow_forward11. Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 4. Part 2 a) The probability that the project will be completed in 20 months = ______ (round your response to four decimal places)arrow_forwardBy using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B Barrow_forward
- Develop a project network. Determine the expected project completion time. What is the probability that the project completion time will be completed? With in 2 weeks earlier than the expected project completion time? With in 1.5 week more than the expected project completion time ?arrow_forwardRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______arrow_forwardColeman Rich Control Devices, I nc., producescustom-built relay devices for auto makers. The most recent projectundertaken by Rich requires 14 different activities. Rich's managerswould like to determine the total project completion time(in days) and those activities that lie along the critical path. Theappropriate data are shown in the following table.a) What is the probability of being done in 53 days?b) What date results in a 99% probability of completion?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY