Expert Solution & Answer
Chapter 3, Problem 25PE
Explanation of Solution
Network Diagram:
The network diagram showing critical path is:
Explanation:
- In a network diagram, activities are represented in circles and arrows represent the flow of activities.
- In the above network diagram, there are 7 activities which are A, B, C, D, E, F and G...
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Your task for this assignment is to create a network diagram for two projects. The activity, immediate predecessor and duration are given. You are to layout-long-hand or using some software-a network diagram for each project. For each diagram conduct a forward and backward pass, calculate the slack, and identify the critical path. When noting your early start, early finish, late start, late finish and slack, please use the format provided."
Project 1
Your task for this assignment is to create a network diagram for two projects. The activity,
immediate predecessor and duration are given. You are to layout-long-hand or using some
software-a network diagram for each project. For each diagram conduct a forward and
backward pass, calculate the slack, and identify the critical path. When noting your early start,
early finish, late start, late finish and slack, please use the format provided.
Project 1
Activity
Immediate Predecessor
Duration
A
none
3
В
A
4
none
6
D
none
2
D
5
F
В, С, Е
2
Project 2
Activity
Immediate Predecessor
Duration
A
none
6
B
none
3
A
9
B
E
в
4
D
2
G
E
8.
*Note: please use this format.
Early
Start
Duration Early
Finish
Activity
Float
Late
Start
Late
Finish
Draw Activity diagram for this scenario
When the employee ( customer to us ) encounters an issue he cant solve he goes to tawasol ( the company ticketing system ) and open a ticket for the issue in the correct section and select the issue genre, explain it and add his contact info then the ticket get assigned automatically by the system to the right IT support team, from there the team in head quarter office in Riyadh assign the task to specific member based on geographic location of the issue and the nature of the issue and the competence needed. After that the team member can see it in his/her ticketing system and can assign the status of the process is it active, pending for some reason or resolved . Then the assigned member will contact the customer to further understand the issue and decide if it could be done remotely or physically, if remotely then the assigned member need to contact the network team to allow access for remote applications on that network. Then when the issue is…
Chapter 3 Solutions
EBK ESSENTIALS OF SYSTEMS ANALYSIS AND
Ch. 3 - An online or hard-copy repository for all project...Ch. 3 - Prob. 2MCh. 3 - Prob. 3MCh. 3 - Prob. 4MCh. 3 - Prob. 5MCh. 3 - Prob. 6MCh. 3 - Prob. 7MCh. 3 - Prob. 8MCh. 3 - Prob. 9MCh. 3 - The process of dividing the project into...
Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- List the task regions in the Spiral model.arrow_forwardAs a project manager of a Software project, you have received given data about the different type of Issues identified in the project: – Issue 1 – 85 occurrences; Issue 2 – 125 occurrences; Issue 3 – 28 occurrences; Issue 4 – 395 occurrences; Issue 5 – 185 occurrences; Issue 6 – 128 occurrences; Issue 7 – 85 occurrences; Issue 8 – 169 occurrences; Issue 9 – 148 occurrences; Issue 10 – 209 occurrences. Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.arrow_forwardMake a SDLC Gantt Chart with 10 phases and add as much sub-tasks in them as you can. (of any duration)arrow_forward
- You are asked to do some requirement development. Suppose you are asked to develop a booking system for a public library system Define a possible scope for the system using the following steps. First list a wide range of things that the system could do. Then narrow down the scope by selecting the most important features that you would implement in the first release of the system. Finally, give a precise problem statement for the system. Identify stakeholders of the system. Then select one important stakeholder and design a list of questions for interviewing that stakeholder. Give functional requirements and quality requirements of the system. Create a list of use cases and describe two of them in detail using the method discussed in class (two-column method). Then draw use cases diagram to describe the system Using UML. Indicate extension, generalization and inclusion, if there are any.arrow_forwardAs a senior studying IT at CTU, your supervisor has requested that you present a plan for consideration and approval. Produce a research proposal of about 1600 words on a topic that interests you, paying special attention to the following: Five sections make up a research paper: the introduction (1), the methods (II), the issue statement (II), the goals (III), the significance (IV), and the literature review (V).arrow_forwardin the textbook. All duration estimates or hes are in days, and the network proceeds from Node 1 to Node 9 Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, 1. labeling each arrow with the activity letter and estimated time. Draw an PDM network diagram representing the project. Determine the early start,early finish,late start and late finish date for every activity and mark them at the four corners of each activity. 2. 3. Identify all of the paths on the network diagram and note how long they are, using Figure 6-8 as a guide for how to represent each path. What is the critical path for this project and how long is it? What is the shortest possible time needed to camnl 4. 5. Formation Technology Project anagement, Sevantiarrow_forward
- A company developing a management system for its client, decides to apply the concept of SDLC approach using Iterative model. Your work is to develop a Work Breakdown Structure (WBS) for this project identifying the various task(s) to be done using a diagram/organogram showing assigned tasks and duration of tasks.arrow_forwardCreate a HACCP flow diagram for canned pasta. Your diagram must start with the receipt of raw ingredients, and end with transport of the finished product to the grocery store. It can be helpful to label each box with a code ornumber so it can be easily referred to in subsequent analysis. It can also be helpful toshow areas of the facility that different processes are taking place.arrow_forwardTask 1 2 3 Duration 2 3 1 4 Make critical path and network diagram, show the float time activity of each task. 4 5 2arrow_forward
- (a) Draw a network diagram for the timeline chart in Figure Q3. (b) Determine all paths based on the answer in Q3(a)arrow_forwarda) A network diagram is an important scheduling tool that graphically portrays the logical relationship and sequencing of activities and events on a project. Task Immediately Preceding Activity A B с D A E B F B G C H D I G J F, H, I Based on the information in the table above, draw an Activity-on-Arrow network diagram to depict the logical relationships among the activities of the project. b) One of the logical rules on a network diagram states that "No two activities may share the same 'head' and 'tail' events". Explain why this is the case and STATE any TWO implications for the project if this rule is disregarded.arrow_forwardNetwork diagram is a boxes and links represent task dependencies True Falsearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning