Essentials of Systems Analysis and Design (6th Edition)
6th Edition
ISBN: 9780133546231
Author: Joseph Valacich, Joey George
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Expert Solution & Answer
Chapter 3, Problem 26PE
Explanation of Solution
Deriving Earliest Start Time, Earliest Finish Time and Slack:
Earliest Completion Time:
It is also known as Early Finish and is the amount required to complete the task of the project. The formula for calculating Early Finish is,
Latest Completion Time:
It is also known as Late Finish and is the latest time for the task to be completed. The formula for calculating Late Finish is,
Slack:
It is the amount of time that an activity can be delayed. It is the difference between Latest Finishing Time and Earliest Finishing Time,
Table showing earliest and latest expected time:
Task | Preceding Event |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
For the following activities, draw the network diagram and by using forward and backward pass, determine:-1. Project duration.2. Critical path.
For a particular project, consider following list of Activities, their duration in Days and their Predecessor activities.
Activity
Days
Precedents
A
3
-
B
15
A
C
5
A
D
60
A
E
6
D
F
40
B
G
10
C,E
H
7
F
I
6
G
J
12
H,I
By using network schedule technique, draw a Network Diagram of above enlisted activities.
1. Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated duration.
2. Identify all the paths on the network diagram and note how long they are.
3. What is the critical path for this project and how long is it?
4. What is the shortest possible time needed to complete the project?
Chapter 3 Solutions
Essentials of Systems Analysis and Design (6th Edition)
Ch. 3 - An online or hard-copy repository for all project...Ch. 3 - Prob. 2MCh. 3 - Prob. 3MCh. 3 - Prob. 4MCh. 3 - Prob. 5MCh. 3 - Prob. 6MCh. 3 - Prob. 7MCh. 3 - Prob. 8MCh. 3 - Prob. 9MCh. 3 - The process of dividing the project into...
Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.Similar questions
- Given the following information, draw the project network diagram compute the, early, late, and slake time for each activity. Identify the critical path (CP) ID Optimistic Most likely Pessimistic Predecessor A 2 4 6 None B 10 11 12 A C 5 6 9 A D 2 8 8 A E 5 6 15 B,C F 2 2 2 D G 3 5 7 E,F H 7 7 17 F I 3 6 8 G, Harrow_forwardDraw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated durationarrow_forward1-Draw the network diagram of the activities listed in the table below using Activity on Node. 2-Find the critical path and the duration of the project. 3-Find the values of ES, EC, LS, and LC of the events 4- Find the values of TF and FF for the activitiesarrow_forward
- Draw a network diagram representing the following information: the project starts with three activities—A, B, and C—which can be done concurrently. When A is finished, D can start; when B is finished, F can start; when B and D are finished, E can start. The project is complete when C, E, and F are finished.arrow_forwardConsider the following Project Schedule. i) Identify all the Paths and calculate their duration? ( In your Submission DO NOT submit Network diagram , write down only the paths). ii) Compute the critical paths duration and state the path. Activities Task Name Duration Dependency A Analysis 1wk - B Selection and commissioning hardware 1 day A C Installation of hardware 1 wk B D Detailed analysis of core modules 1.2 wk A E Detailed analysis of supporting modules 2 wks D F Programming of core modules 2 wks D G Programming of supporting modules 3 wks E H Quality assurance of core modules 1wk F I Quality assurance of supporting modules 1 wk G J Core module training 1 day C,H K Development of QA of management report 1 wk E L Development and AQ of management information on system 1 wk E M Development of management information system 1 wk…arrow_forwardActivity Immediate Optimistic Most Likely Pessimistic Predecessor Time (a) Time (m) Time (b) A ____ 2 3 4 B ____ 2 4 6 C A 1 2 3 D B 4 6 9 E C, D 7 8 9 F D 4 7 10 G E 3 4 6 H E, F 7 9 12 a) Construct the project network using…arrow_forward
- 1) Use the List of Activities to develop an AON/CPM/Network Diagram 2) Complete the Critical Path Method (CPM) computations on the diagram developed in Step 1 above to determine the Critical Path, Activity Dates, and Total Float for activities 3) Now using Microsoft Project or Project Libre (if both do not work, use Excel) to develop the Network Diagram for the Sample Project (assume project starts on September 1, 2021) 4) Add Resource Information to your schedule using the Resources Needed table provided for the Sample Project. 5) Perform Resource Leveling on your Project The following documents can be assembled into a single PDF file and uploaded: Scan the network diagram with the calculations (see step 1 and step 2 above) Print the Gantt Chart from Mircosoft Project or Project Libre (after adding resources in step 4 but without performing Resource Leveling) Print the Gantt Chart from Mircosoft Project or Project Libre (after performing Resource Leveling listed in Step 5 above)…arrow_forwardQ- a) What is PERT and CPM in project management show the difference between them b) Consider the following engineering project. 1-What is the critical path 2- Compute the ES, EC, LS, LC and the slack time, and display all the values in a table. Activity Immediate Time (week) predecessor Activity A A A, B D B E A, C, D 8 3- Suppose that activity C has been completed within 5 weeks, what is the effect on the project completion time? 65arrow_forward. Construct a Gantt chart and network diagram for a project you are or will be involved in. Choose a project of sufficient depth from work, home, or school. Identify the activities to be completed, determine the sequence of the activities, and construct a diagram reflecting the starting times, ending times, durations, and precedence (network diagram only) relationships among all activities. For your network diagram, use the procedure in this chapter to determine time estimates for each activity and calculate the expected time for each activity. Now determine the critical path and the early and late starting and finishing times for each activity. Which activities have slack time?arrow_forward
- Using an application of your choice: Draw a network diagram for this project, clearly showing the Activity ID and Activity durationarrow_forwardDraw a neat network diagram and find the critical path for the given activity table for software development. Activity Description Predecessor Duration A Analysis None 2 B Development None 6 C Testing None 4 D Documentation A 3 E Training C 5 F Implementation A 4 G Maintenance B, D, E 2 a) Draw a neat network diagram and find LS,LF,ES,EF and mark appropriate Activity on Node. b) Find the completion time of the project. c) Find critical path. (calculation of ES, EF, LS, LF)arrow_forwardQ1. An engineering project is being planned using Project Network Techniques, and the precedence diagram attached as Figure 1a has been prepared to show the sequence of logic. The duration of each activity is shown in the standard position, quoted in weeks. Lags with durations also given in weeks are shown applied to two dependencies. (a) Complete the precedence diagram (Figure 1a) by adding the full analysis of start and finish times (early and late), and total float in the appropriate places. (b) Indicate the critical path on the diagram. A-1 B-5 C-4 D-1 E-5 F-8arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningOperations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks Cole
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole