Essentials of Systems Analysis and Design (6th Edition)
Essentials of Systems Analysis and Design (6th Edition)
6th Edition
ISBN: 9780133546231
Author: Joseph Valacich, Joey George
Publisher: PEARSON
bartleby

Concept explainers

Expert Solution & Answer
Book Icon
Chapter 3, Problem 26PE

Explanation of Solution

Deriving Earliest Start Time, Earliest Finish Time and Slack:

Earliest Completion Time:

It is also known as Early Finish and is the amount required to complete the task of the project. The formula for calculating Early Finish is,

  EF = ES + Duration

Latest Completion Time:

It is also known as Late Finish and is the latest time for the task to be completed. The formula for calculating Late Finish is,

   LF = LS + Duration

Slack:

It is the amount of time that an activity can be delayed. It is the difference between Latest Finishing Time and Earliest Finishing Time,

  Slack = Latest Expected Time – Earliest Expected Time

Table showing earliest and latest expected time:

TaskPreceding Event

Blurred answer
Students have asked these similar questions
For the following activities, draw the network diagram and by using forward and backward pass, determine:-1. Project duration.2. Critical path.
For a particular project, consider following list of Activities, their duration in Days and their Predecessor activities.   Activity Days Precedents A 3 - B 15 A C 5 A D 60 A E 6 D F 40 B G 10 C,E H 7 F I 6 G J 12 H,I By using network schedule technique, draw a Network Diagram of above enlisted activities.
1. Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated duration. 2. Identify all the paths on the network diagram and note how long they are. 3. What is the critical path for this project and how long is it? 4. What is the shortest possible time needed to complete the project?

Chapter 3 Solutions

Essentials of Systems Analysis and Design (6th Edition)

Ch. 3 - Prob. 11MCh. 3 - A graphical representation of a project that shows...Ch. 3 - Prob. 13MCh. 3 - Prob. 14MCh. 3 - A systems analyst with a diverse set of...Ch. 3 - The second phase of the project management...Ch. 3 - Prob. 17MCh. 3 - Prob. 18MCh. 3 - Prob. 19MCh. 3 - Prob. 20MCh. 3 - Prob. 1RQCh. 3 - Prob. 2RQCh. 3 - Prob. 3RQCh. 3 - Prob. 4RQCh. 3 - Prob. 5RQCh. 3 - Prob. 6RQCh. 3 - Prob. 7RQCh. 3 - Prob. 8RQCh. 3 - Prob. 9RQCh. 3 - Describe the steps involved in making a network...Ch. 3 - In which phase of the systems development life...Ch. 3 - What are some reasons why one activity may have to...Ch. 3 - Which of the four phases of the project management...Ch. 3 - What are some sources of risk in a systems...Ch. 3 - Search the Web for recent reviews of project...Ch. 3 - Prob. 16PECh. 3 - Prob. 17PECh. 3 - Prob. 18PECh. 3 - Prob. 19PECh. 3 - Construct a Gantt chart for the project defined in...Ch. 3 - Look again at the activities outlined in Problem...Ch. 3 - Prob. 25PECh. 3 - Prob. 26PECh. 3 - Prob. 27PECh. 3 - Prob. 29PECh. 3 - Prob. 30PECh. 3 - Prob. 31PECh. 3 - Prob. 32PECh. 3 - Prob. 33DQCh. 3 - Do you agree that breaking projects down into...Ch. 3 - Microsoft Project is powerful but expensive....Ch. 3 - When completing a project, some tasks are...Ch. 3 - a. While eating lunch one day, Juanita asked Chris...Ch. 3 - What qualities might Jim possess that would make...Ch. 3 - Prob. 41CQCh. 3 - Prob. 42CQCh. 3 - What should Jim do next to complete the project...Ch. 3 - Prob. 44CQ
Knowledge Booster
Background pattern image
Computer Science
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole