Question
Chapter 3, Problem 28P
Summary Introduction
Case summary
To determine: The activities to be crashed and total crashing cost.
Introduction: In the activity on nodes (AON) project network diagram, the nodes denote activities and the arrows show only the precedence and succession sequence.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
I need a detailed explanation and assistance on how to solve this problem:
The company decided that the project in the previous problem has to be expedited in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting the project reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below.
Activity
Normal
Time
(days)
Expedited
Time
(days)
Normal
Cost
($)
Expedited
Cost
($)
A
32
26
200
500
B
21
20
300
375
C
30
30
200
200
D
45
40
200
800
E
26
20
700
1,360
F
28
24
1,000
1,160
G
20
18
400
550
From this table you can compute the direct cost incurred by expediting an…
1. What’s the maximum amount of time that activity G can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value).
2.What’s the maximum amount of time that activity A can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value)
3. What’s the maximum amount of time that activity H can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value)
1.What’s the maximum amount of time that activity F can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value).
2. What’s the maximum amount of time that activity D can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value).
3.What’s the maximum amount of time that activity C can be delayed without delaying the whole project? (Whole number, no space, no commas, no decimal value).
4. What’s the earliest expected time, in months, to finish the project? (Whole number, no space, no commas, no decimal value).
Chapter 3 Solutions
PRIN.OF OPERATIONS MANAGEMENT-MYOMLAB
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Project crashing is when you shorten the duration of a project by reducing the time of one or more tasks. Crashing is done by increasing the resources to the project, which helps make tasks take less time than what they were planned for. Of course, this also adds to the cost of the overall project. Therefore, the primary objective of project crashing is to shorten the project while also keeping costs at a minimum. What are the different options for crashing an activity when resources are not constrained ?arrow_forwardYou are the project manager of the BTU AVIC project in Bolgatanga. As a result of the ongoing pandemic, you are responsible to ensure the project does not overly delay among other objectives. Required:a. Discuss five strategies for reducing the critical path of the BTU AVIC project.b. Explain five ways you can resolve the problem of resource allocation on the project. c. Using the Four-Stage Process of risk management discuss how risks could be managed on the ongoing BTU AVIC project. Identify three potential categories of team conflicts and how you will resolve such conflictsarrow_forwardThe following criteria is NOT being considered for crashing an activity or the entire project.a) The amount by which an activity is crashed is, in fact, permissible.b) Taken together, the shortened activity durations will enable us tofinish the project by the due date.c) Urgent activities take priority considerations for crashing.d) The total cost of crashing is as small as possible.arrow_forward
- Based on the information below, prepare a comprehensive report that includes the following: Normal completion time and accelerated completion time Steps that can be taken to crash the project to the shortest time at the lowest cost. Hint: Determine each step's cost and the duration of the project at that stage. Your insights on the cost-time trade-off for this project. Your recommended strategy for crashing the project.arrow_forwardIf the company wants to complete the project in 40 weeks,which activities should be crashed? Calculate the additional costincurred to complete the project in 40 weeks.arrow_forwardYou are in charge of a project. Your team has determined that there are 7 activities to be completed. Here are the activities, the time to complete the activity and the immediate predecessor of the activity. Using this data 1) construct a Gantt Chart, 2) determine the time it will take to complete the project, 3) You are monitoring the progress of this project and discover that activity C is in danger of taking longer than planned due to funding issues. What options do you have to get the project back on track? Activity Time Immediate Predecessor A 10 Weeks None B 6 Weeks A C 7 Weeks A D 6 Weeks B E 8 Weeks C F 3 Weeks D G 4 Weeks Farrow_forward
- Project Scope Management includes the processes required to ensure that the project includes all the work required, andonly the work required, to complete the project successfully (Project Management Institute, 2017:129).By referring to the project scope management process, discuss how the case study project scope could have been definedmore efficiently by specifically referring to plan scope management.arrow_forwardYour project to obtain charitable donations is now 30 days into a planned 40-day project. The project is divided into three activities. The first activity is designed to solicit individual donations. It is scheduled to run the first 25 days of the project and to bring in $25,000. Even though we are 30 days into the project, we still see that we have only 90 percent of this activity complete. The second activity relates to company donations and is scheduled to run for 30 days starting on day 5 and extending through day 35. We estimate that, even though we should have 83 percent (25/30) of this activity complete, it is actually only 50 percent complete. This part of the project was scheduled to bring in $150,000 in donations. The final activity is for matching funds. This activity is scheduled to run the last 10 days of the project and has not started. It is scheduled to bring in an additional $50,000. So far, $175,000 has actually been brought in on the project. Calculate the Schedule…arrow_forwardThe company decided that the project in the previous problem had to be expedite in order to optimize (minimize) the project cost. Expediting can be used to trade direct cost for indirect cost, since expediting reduces the indirect cost of the project by a fixed amount per day, while expediting an activity increases its total direct cost. The Accounting Department found that indirect costs amount to $100 per day, while activity direct costs as well as their normal and expedited times are given in the table below. Activity Duration (Days) Expedited Time (Days) Normal Direct Cost ($) Expedited Direct Cost ($) A 32 26 200 500 B 21 20 300 375 C 30 30 200 200 D 45 40 200 800 E 26 20 700 1,360 F 28 24 1,000 1,160 G 20 18 400 550 What is the optimal time to complete the project? What is the optimal project cost?arrow_forward
- You manage a project with 10 activities. Activities A1, A3, A5, and A9 form the critical path.Because you have a large budget for the project, you consider crashing activity A2, which hasthe potential to shorten the time of A2 by three days. What do you think about this opportunity?a. It is a good idea because it will reduce the project duration by three days.b. It is a bad idea because A2 is not on the critical path.arrow_forwardThis exercise tests your ability to come up with a detailed and elaborate Business Case for a project. One of the main responsibilities of an IT Project Manager is writing and defending Project Proposals, that is, justifying the need for the project. You need to explain the organization’s need(s), the current situation, and why your proposed solution will workAssume that you wish to import a 14-seater Public Service Vehicle (PSV) to ply route 14 (Town-Nairobi West-Madaraka) of Nairobi City. You need to compute the Total Cost of Ownership (TCO), that is, the cost of purchasing and maintaining the vehicle including the regulatory requirements. You are expected to take a loan at the prevailing rates and spread it as you wish (based on your assumptions-show the calculations). You then calculate projected income expected from the “Project” (again based on some assumptions which you need to state) and give a realistic position about the viability of getting into this “project”. You earn…arrow_forwardWrite an essay on the following topic: You are a Project Manager at the Department of Public Works in Mpumalanga who has been appointed to oversee the construction of a community hall. You need to explain the following to a community meeting that are being held to roll out this project: 1. Explain to the meeting the difference between a programme, a project and a sub-project. You must also provide them with examples of projects, subprojects and programmes that your department is involved in.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY