Chapter 3, Problem 9P
a)
Summary Introduction
To develop:An AON network diagram with the given the various activities, their precedence and succession relationships, activity times and so on.
Introduction: In the activity on nodes (AON) project network diagram, the nodes denote activities and the arrows show only the precedence and succession sequence.
b)
Summary Introduction
To determine: The critical path.
c)
Summary Introduction
To determine: The total expected time.
d)
Summary Introduction
To draw: The Gantt chart for the project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Considering the Project Details;
1.Construct the Project Network Diagram
2.Find the Expected Duration and Standard Deviation and Variance of each Activity
3.Find the Critical path and Expected Project Completion Time
Given the project activity table below: (check images)
a) Draw a project network from the table
b)
What activity(s) is a burst activity?
What activity(s) is a merge activity?
3. What is the length of the project?
4. What is the critical path?
c) Make the Gantt chart
d) Build the project network using expected activity times based on the new table below (I WROTE "2nd CHART" on it)
e) What would be the expected length of the project?
f) What would be the project standard deviation?
g) Using a z-table (one can be found here: https://statisticsbyjim.com/hypothesis-testing/z-table/ ), what is the probability that the project can be completed in 28 weeks?
Paul Silver, owner of Sculptures International, just initiated a new art project. The following data are available for the project:
a. Draw the network diagram for the project.b. Determine the project’s critical path and duration.c. What is the slack for each activity?
Chapter 3 Solutions
Pearson Etext For Principles Of Operations Management: Sustainability And Supply Chain Management -- Access Card (11th Edition)
Ch. 3 - Ethical Dilemma Two examples of massively...Ch. 3 - Give an example of a situation in which project...Ch. 3 - Explain the purpose of project organization.Ch. 3 - What are the three phases involved in the...Ch. 3 - What are some of the questions that can be...Ch. 3 - Define work breakdown structure. How is it used?Ch. 3 - What is the use of Gantt charts in project...Ch. 3 - What is the difference between an...Ch. 3 - What is the significance of the critical path?Ch. 3 - what would a project manager have to do to crash...
Ch. 3 - Prob. 10DQCh. 3 - Define earliest start, earliest finish, latest...Ch. 3 - Students are sometimes confused by the concept of...Ch. 3 - Prob. 13DQCh. 3 - Prob. 14DQCh. 3 - Would a project manager ever consider crashing a...Ch. 3 - How is the variance of the total project computed...Ch. 3 - Describe the meaning of slack, and discuss how it...Ch. 3 - How can we determine the probability that a...Ch. 3 - Name some of the widely used project management...Ch. 3 - What is the difference between the waterfall...Ch. 3 - The work breakdown structure (WBS) for building a...Ch. 3 - James Lawson has decided to run for a seat as...Ch. 3 - Prob. 3PCh. 3 - Refer to the table in Problem 3.3. a) Draw the AON...Ch. 3 - Draw the activity-on-node (AON) project network...Ch. 3 - Given the activities whose sequence is described...Ch. 3 - Prob. 7PCh. 3 - Roger Ginde is developing a program in supply...Ch. 3 - Prob. 9PCh. 3 - The activities described by the following table...Ch. 3 - Prob. 11PCh. 3 - The activities needed to build a prototype laser...Ch. 3 - Prob. 13PCh. 3 - Dave Fletcher (sec Problem 3.12) was able to...Ch. 3 - Ross Hopkins, president of Hopkins Hospitality,...Ch. 3 - A renovation of the gift shop at Orlando Amway...Ch. 3 - Kelle Carpet and Trim installs carpet in...Ch. 3 - The estimated times and immediate predecessors for...Ch. 3 - Prob. 21PCh. 3 - Four Squares Productions, a firm hired to...Ch. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 25PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 30PCh. 3 - Development of Version 2.0 of a particular...Ch. 3 - Prob. 32PCh. 3 - Prob. 33PCh. 3 - Prob. 1.1VCCh. 3 - Prob. 1.2VCCh. 3 - Project Management at Arnold Palmer Hospital The...Ch. 3 - Prob. 1.4VCCh. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...Ch. 3 - Managing Hard Rocks Rockfest At the Hard Rock...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Task time estimates for the modificat ion of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: a) Draw the project network using AON.b) Identify the critical path.c) What is the expected project completion time?d) Draw a Gantt chart for the project.arrow_forwardYour hospital has applied for certification as a level 1 stroke center. It is critical that the following project is completed in 18 weeks, before the next Joint Commission survey. Project activity times are listed in the table that is attached as an image. a) Draw the network diagram.b) Identify all project paths. Which path is the critical path and why?c) What is the project completion time and total project costs if only normal times are used? Activityarrow_forwardConsider the following data for a project to install a new server at the Northland Pines High School: a. Draw the network diagram.b. Calculate the critical path for this project.c. How much slack is in each of the activities G, H, and I?arrow_forward
- Create a Network Diagram and Critical Path using the Data. Determine the minimum project duration. The duration of each activity is in days.arrow_forward1. CREATE THE NETWORK DIAGRAM USING AON 2. DETERMINE THE NETWORK PATHS 3. DETERMINE THE CRITICAL PATH AND ITS DURATION 4. CREATE A GANTT CHART STARTING JANUARY 1, 2021. NO DAY-OFFS 5. WHEN WILL THE PROJECT BE COMPLETED?arrow_forwardExercise 8: Given the following network, refer to the pic please (a) What is the critical path? (b) How long will it take to complete this project? (c) Can activity B be delayed without delaying the completion of the project? If so, how many days?arrow_forward
- An advertising project manager developed the network diagram shown in Figure 2.10 for a new advertising campaign. In addition, the manager gathered the time information for each activity, as shown in the accompanying table. a. Calculate the expected time and variance for each activity. b. Calculate the activity slacks and determine the critical path, using the expected activity times. c. What is the probability of completing the project within 23 weeks?arrow_forwarda. Draw a project network. b. What is the critical path? c. What is the normal project cost? d. What is the total cost of the project if you need to crash it by 1 week?arrow_forwardJanice Eliassen must complete the activities in the following table to fin ish her consulting project. a) Draw the appropriate PERT diagram.b) Find the critical path and project completion time.c) Find the probability that the project will take more than49 time periods to complete.arrow_forward
- The fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in Chicago, their durations, and what activities each must precede: a) Draw an AOA diagram of the project, including activity durations.b) Define the critical path, listing all critical activities in chronological order.c) What is the project completion time (in weeks)?d) What is the slack (in weeks) associated with any and all noncritical paths through the project?arrow_forwardYou are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calcu-late the free slack and total slack for all noncritical activities.ID Description Predecessor Time (days)A Systems design None 2 B Subsystem A design A 1C Subsystem B design A 1D Subsystem C design A 1E Program A B 2F Program B C 2G Program C D 2H Subsystem A test E 1I Subsystem B test F 1J Subsystem C test G 1K Integration H, I, J 3L Integration test K 1arrow_forwarda) Determine the expected completion time and variance for each activity. b) Determine the total project completion time and the critical path for the project. c) Determine ES, EF, LS, LF, and slack for each activity. d) What is the probability that Kelle Carpet and Trim will finish the project in 40 days or less?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY