Snyder Snacks makes potato chips, corn chips, and cheese puffs using three different production lines within the same manufacturing plant. Currently, Snyder uses a single plantwide overhead rate to allocate its $3,311,500 of annual manufacturing overhead. Of this amount, $2,070,000 is associated with the potato chip line, $763,000 is associated with the corn chip line, and $478,500 is associated with the cheese puff line. Snyder’s plant is currently running a total of 17,900 machine hours: 11,500 in the potato chip line, 3,500 in the corn chip line, and 2,900 in the cheese puff line. Snyder considers machine hours to be the cost driver of
- 1. What is Snyder’s plantwide overhead rate?
- 2. Calculate the departmental overhead rates for Snyder’s three production lines. Round all answers to the nearest cent.
- 3. Which products have been overcosted by the plantwide rate? Which products have been undercosted by the plantwide rate?
Trending nowThis is a popular solution!
Chapter 4 Solutions
Managerial Accounting - With Helios Access
- Bordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On average, the first unit of a new design takes 600 hours. Direct labor is paid 25 per hour. Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, cumulative total time in hours, and the time for the last unit. Show results by row for each of units one through eight. (Round answers to two significant digits.)arrow_forwardMANAGEMENT ACCOUNTING & CONTROL STANDARD COSTS AND VARIANCE ANALYSIS LEARNING ACTIVITY 1 Torres Company has established standard costs for the cabinet department, in which one size of MX cabinet is made. The standard costs of producing one of these MX cabinets are shown below: Standard Cost Card – MX Cabinet Direct Material: Lumber 50 board ft at P 4 200 Direct Labor: 8 hours at P 10 80 Overhead Costs: Variable – 8 hrs at P5 40 Fixed – 8 hrs at P3 24 Total Standard Unit Cost 344 During June 2018, 500 of these cabinets were produced. The cost of operations during the month are shown below. There is no work in process at the beginning and end of the month. Direct material purchased: 30,000 bf at P4.10 123,000 Direct materials used: 24,000 board ft Direct labor: 4,200 hrs at P9.50 39,900 Overhead Costs : Variable Costs 22,000 Fixed Costs 11,000…arrow_forwardprofile-image Student question Time to preview question: 00 : 08 : 51 The Epsilon Co. have a building, which houses three production department, Alpha, Beta and Gamma, and one service department Delta. The service department, Delta is wholly involved in working for the three production departments and it is estimated that department Alpa uses 50%, department Beta uses 30% and department Gamma uses 20% of the services of department Delta. The budgeted overhead for the four departments for a period were: REQUIRED: a. Apportion the costs to the departments on the most equitable bases and calculate the overhead absorption rate, based on labour hours, for all the production department.arrow_forward
- The following information is provided to you: Time taken to produce first 8 shock pads 640 hours Time taken to produce first 16 shock pads 1200 hours Calculate the learning curve The following information is provided to you: Direct labour needed to make first machine. 1000 hoursLearning curve. 80%Direct labour cost. R300 per hourDirect materials cost. R180000 per machine Fixed cost for machines at each cumulative production R800000 Calculate the total direct hours required to manufacture four (4) machines. ( Indicate both average time per unit as well as cumulative time per unit for all theunits) Calculate the total costs to manufacture 4 machinesarrow_forwardLearnCo LearnCo manufactures and sells one product, an abacus for classroom use, with two models, the Basic model and the Deluxe model. The company began operations on January 1, 20Y1, and is planning for 20Y2, its second year of operations, by preparing budgets from its master budget. The company is trying to decide how many units to manufacture, how much it might spend on direct materials and direct labor, and what their factory overhead expenses might be. In addition, the company is interested in budgeting for selling and administrative costs, and in creating a budgeted income statement showing a prediction of net income for 20Y2. You have been asked to assist the controller of LearnCo in preparing the 20Y2 budgets. Sales Budget The sales budget often uses the prior year’s sales as a starting point, and then sales quantities are revised for various factors such as planned advertising and promotion, projected pricing changes, and expected industry and general economic conditions.…arrow_forwardLearnCo manufactures and sells one product, an abacus for classroom use, with two models, the Basic model and the Deluxe model. The company began operations on January 1, 20Y1, and is planning for 20Y2, its second year of operations, by preparing budgets from its master budget. The company is trying to decide how many units to manufacture, how much it might spend on direct materials and direct labor, and what their factory overhead expenses might be. In addition, the company is interested in budgeting for selling and administrative costs, and in creating a budgeted income statement showing a prediction of net income for 20Y2. You have been asked to assist the controller of LearnCo in preparing the 20Y2 budgets. The sales budget often uses the prior year’s sales as a starting point, and then sales quantities are revised for various factors such as planned advertising and promotion, projected pricing changes, and expected industry and general economic conditions. LearnCo has…arrow_forward
- Harriman Industries manufactures engines for the aerospace industry. It has completed manufacturing the first unit of the new ZX-9 engine design. Management believes that the 1,000 labor hours required to complete this unit are reasonable and is prepared to go forward with the manufacture of additional units. An 80 percent cumulative average-time learning curve model for direct labor hours is assumed to be valid. Data on costs are as follows: Required: 1. Set up a table with columns for cumulative number of units, cumulative average time per unit in hours, and the cumulative total time in hours. Complete the table for 1, 2, 4, 8, 16, and 32 units. (Round hours to one significant digit.) 2. What are the total variable costs of producing 1, 2, 4, 8, 16, and 32 units? What is the variable cost per unit for 1, 2, 4, 8, 16, and 32 units?arrow_forwardThe Vest School of Vocational Technology has organized the school training programs into three departments. Each department provides training in a different area as follows: nursing assistant, dental hygiene, and office technology. The school's owner, Candice Vest, wants to know how much it cost to operate each of the three departments. To accumulate the total cost for each department, the accountant has identified several indirect costs that must be allocated to each. These costs are $10,080 of telephone expense, $2,016 of supplies expense, $720,000 of office rent, $144,000 of janitorial services, and $150,000 of salary paid to the dean of students. To provide a reasonably accurate allocation of costs, the accountant has identified several possible cost drivers. These drivers and their association with each department follow. Cost Driver Department 1 Department 2 Department 3 Number of telephone 28 16 19 Number of faculty members 20 16 12 Square footage of office space 28,000 16,800…arrow_forwardSharon Glessing, controller for Janson Company, has noticed that the company faces a 80 percent learning rate for its specialty design line. In planning the cost of the latest design, Sharon assumed that the first set of units would take 1,100 direct labor hours. She decided to use this information in budgeting for the cost of the total project, which would involve the manufacture of 16 sets. Direct labor is paid $40 per hour. 1. Complete the table below showing results by row for total production of: one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) (Round Cumulative Total Time answers to the nearest whole number.) 2. What is the total labor cost if Janson Company makes eight sets? Sixteen sets? (Use the rounded answers in the subsequent computations). 3. Using the logarithmic function, complete the table below showing results by row for each of unit sets one through eight. (Round hour answers to two significant digits.)…arrow_forward
- Question Content Area A local picnic table manufacturer has budgeted these overhead costs: Purchasing $70,000 Handling Materials 34,580 Machine Setups 72,000 Inspections 30,600 Utilities 27,000 They are considering adapting ABC costing and have estimated the cost drivers for each pool as shown: Cost Driver Activity Orders 700 Material Moves 1,330 Machine Setups 16,000 Number of Inspections 6,000 Square Feet 180,000 Recent success has yielded an order for 1,000 tables. Assume direct labor costs per hour of $20. Activity Order, Units 1,000 Direct Materials 112,600 Machine Hours 15,300 Direct Labor Hours 5,200 Number of Purchase Orders 70 Number of Material Moves 750 Number of Machine Setups 100 Number of Inspections 450 Number of Square Feet Occupied 8,000 Determine how much the job would cost given the following activities: Do not round intermediate computations and round final answers to nearest whole number. Cost Assigned…arrow_forwardThe Document Creation Center (DCC) for Arlington Corp. provides photocopying and document services for three departments in the Minneapolis office. The following budget has been prepared for the year. Available capacity 8,100,000 pages Budgeted usage: Software Development 1,700,000 pages Training 3,100,000 pages Management 2,500,000 pages Cost equation $285,000 + $0.02 per page If DCC uses a dual-rate for allocating its costs based on usage, how much cost will be allocated to the Software Development Department? Multiple Choice $116,740. $100,370. $45,630. $162,000.arrow_forwardJoseph Fox, controller of Thorpe Company, has been in charge of a project to install an activity-based cost management system. This new system is designed to support the companys efforts to become more competitive. For the past six weeks, he and the project committee members have been identifying and defining activities, associating workers with activities, and assessing the time and resources consumed by individual activities. Now, he and the project committee are focusing on three additional implementation issues: (1) identifying activity drivers, (2) assessing value content, and (3) identifying cost drivers (root causes). Joseph has assigned a committee member the responsibilities of assessing the value content of five activities, choosing a suitable activity driver for each activity, and identifying the possible root causes of the activities. Following are the five activities with possible activity drivers: The committee member ran a regression analysis for each potential activity driver, using the method of least squares to estimate the variable and fixed cost components. In all five cases, costs were highly correlated with the potential drivers. Thus, all drivers appeared to be good candidates for assigning costs to products. The company plans to reward production managers for reducing product costs. Required: 1. What is the difference between an activity driver and a cost driver? In answering the question, describe the purpose of each type of driver. 2. For each activity, assess the value content and classify each activity as value-added or non-value-added (justify the classification). Identify some possible root causes of each activity, and describe how this knowledge can be used to improve activity performance. For purposes of discussion, assume that the value-added activities are not performed with perfect efficiency. 3. Describe the behavior that each activity driver will encourage, and evaluate the suitability of that behavior for the companys objective of becoming more competitive.arrow_forward