Finding optimal solution:
IRS can rent computers for one, two or three months at a rent of $100, $180, $250 respectively. The excel Solver is used to minimize total expenditure. Follow the given below steps,
Step 1:
Enter the required data in Excel worksheet. Create columns of month 1, month 2 and month 3 and computers in hand. Column C, D, E are initially blank.
For column F, enter Formula
Enter formula
The excel worksheet is given below,
Step 2:
Select Excel Options. Go to Add-Ins. Click on manage to get a list of available Add-Ins. Add Solver-Add In from the options.
Step 3:
Select
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Chapter 4 Solutions
Student Suite Cd-rom For Winston's Operations Research: Applications And Algorithms
- Rounding the solution of a linear programming problem to the nearest integer values provides a(n): a. integer solution that is optimal. b. integer solution that may be neither feasible nor optimal. c. feasible solution that is not necessarily optimal. d. infeasible solution.arrow_forwardSolve the following:arrow_forwardI need the solution parrow_forward
- The following table belongs to the optimal solition nit of a Lineer Programming Problem. Obtain the formulation of the initial problem. XI x2 ke -Jig 38 X₁ Xu O 1 O 19 41 14 23 38 xu O O 1 VI 38 A 38 AL A2 (1-38M) (2-19M) 38 19 -3 38 5 L 응급 31 19 19 solution 7' 2 5arrow_forwardQuestion 14 of 20: Set the best anas 14 Use Gauss-Jordan elimination to solve the following linear system: -3x+4y=-6 5x-y=10 OA (2.0) 08.2-5 OCHED ⒸD. (22) Mark for revine (Will be highlighted on the review page) s Gutxarrow_forwardA construction company has four large bulldozers located at four different garages. The bulldozers are to be moved to four different construction sites. The distances in miles between the bulldozers and the construction sites are given below. Bulldozer/ A B C D Site Students 1 90 75 75 80 solve it 2 35 85 55 65 yourself 3 125 95 90 105 4 45 110 95 115 How should the bulldozers be moved to the construction sites in order to minimize the total distance traveled?arrow_forward
- Operations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks Cole
![Text book image](https://www.bartleby.com/isbn_cover_images/9780534380588/9780534380588_smallCoverImage.gif)