Chapter 4.S, Problem 22P
Summary Introduction
To determine: The most cost-effective option.
Introduction:
Mean time between failures (MTBF):
The mean time between failures is a term which denotes the time that is elapsed between the first failure of a product and the second failure of a product. It is calculated during the normal system operation.
Mean time to repair (MTTR):
The mean time to repair is the time incurred for a device to fail and also the time elapsed to repair the device. The repair is carried out after the failure of the device.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A designer estimates that she can (a) increase the average time between failures of a part by 5 percent at a cost of $450, or (b) reduce the average repair time by 10 percent at a cost of $200. Which option would be more cost-effective? Currently, the average time between failures is 100 hours andthe average repair time is 4 hours.
Even after taking all appropriate steps to produce a high integrity system, some remaining faults will remain. How would you ensure system safety and reliability in practical approaches?
What is the overall reliability that bank loans willbe processed accurately if each of the 5 clerks shown in thechart has the reliability shown?
Hint: The three paths are done in parallel, followed by anadditional independent step.
Chapter 4 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 4.2 - Prob. 1.1RQCh. 4.2 - Prob. 1.2RQCh. 4.5 - Prob. 1.1RQCh. 4.5 - Prob. 1.2RQCh. 4.7 - Prob. 1.1RQCh. 4.7 - Prob. 1.2RQCh. 4.7 - Prob. 1.3RQCh. 4.8 - Prob. 1.1RQCh. 4.8 - Prob. 1.2RQCh. 4.11 - THE CHALLENGES OF MANAGING SERVICES Services can...
Ch. 4.11 - THE CHALLENGES OF MANAGING SERVICES Services can...Ch. 4.S - Prob. 1DRQCh. 4.S - Prob. 2DRQCh. 4.S - Prob. 3DRQCh. 4.S - Consider the following system: Determine the...Ch. 4.S - A product is composed of four parts. In order for...Ch. 4.S - A system consists of three identical components....Ch. 4.S - A product engineer has developed the following...Ch. 4.S - The guidance system of a ship is controlled by a...Ch. 4.S - One of the industrial robots designed by a leading...Ch. 4.S - A production line has three machines A, B, and C,...Ch. 4.S - Prob. 8PCh. 4.S - A Web server has five major components that must...Ch. 4.S - Repeat Problem 9 under the condition that one of...Ch. 4.S - Hoping to increase the chances of reaching a...Ch. 4.S - An electronic chess game has a useful life that is...Ch. 4.S - A manufacturer of programmable calculators is...Ch. 4.S - Lucky Lumen light bulbs have an expected life that...Ch. 4.S - Prob. 15PCh. 4.S - Prob. 16PCh. 4.S - Determine the availability for each of these...Ch. 4.S - Prob. 20PCh. 4.S - A manager must decide between two machines. The...Ch. 4.S - Prob. 22PCh. 4.S - Auto batteries have an average life of 2.7 years....Ch. 4 - Prob. 1DRQCh. 4 - Prob. 2DRQCh. 4 - Prob. 3DRQCh. 4 - Prob. 4DRQCh. 4 - Prob. 5DRQCh. 4 - Prob. 6DRQCh. 4 - Prob. 7DRQCh. 4 - Prob. 8DRQCh. 4 - a. What is meant by the term life cycle? b. Why...Ch. 4 - Prob. 10DRQCh. 4 - Prob. 11DRQCh. 4 - Prob. 12DRQCh. 4 - Prob. 13DRQCh. 4 - Explain what quality function development is and...Ch. 4 - Prob. 15DRQCh. 4 - Prob. 16DRQCh. 4 - Prob. 17DRQCh. 4 - Prob. 18DRQCh. 4 - Prob. 19DRQCh. 4 - Describe some of the trade-off that are...Ch. 4 - Prob. 2TSCh. 4 - Prob. 3TSCh. 4 - Prob. 1CTECh. 4 - Prob. 2CTECh. 4 - Prob. 3CTECh. 4 - Prob. 4CTECh. 4 - Prob. 5CTECh. 4 - Give two examples of unethical conduct involving...Ch. 4 - Prob. 1PCh. 4 - Prob. 2PCh. 4 - Prepare a service blueprint for each of these...Ch. 4 - Prepare a service blueprint for each of these post...Ch. 4 - Prob. 5PCh. 4 - Prob. 6PCh. 4 - Prob. 7PCh. 4 - Prepare a table similar to that shown in Problem...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- MagTech assembles tape players from four major compo-nents arranged as follows:The components can be purchased from three differentvendors, who have supplied the following reliability data:a. If MagTech has decided to use only one vendor tosupply all four components, which vendor should beselected?b. Would your decision change if all the components wereassembled in series?arrow_forwardIn the context of system reliability, explain the difference between Mean Time Between Failures (MTBF) and Mean Time To Recovery (MTTR). How do these metrics impact system design?arrow_forwardWhat distinguishes six Sigma from traditional continuous improvement?arrow_forward
- R1 R2 R3 x y graph For the parallel production process shown above, R1=0.92, R2=0.88, R3=0.98. For the given parallel production process, the reliability = % (enter your response as a percentage rounded to two decimal places).arrow_forwardElizabeth Irwin's design team has proposed the following system with component reliabilities as indicated: R2=0.88 R1=0.92 R4=0.92 R3=0.88 The overall reliability of the proposed system = % (enter your response as a percentage rounded to two decimal places). Hint: The system functions if either R2 or R3 work.arrow_forwardAs VP for operations at Méndez-Piñero Engineering, you must decide which product design, A or B, has the higher reli-ability. B is designed with backup units for components R3 and R4 . What is the reliability of each design? PX 0.99 0.95 0.998 0.995Product Design AR1 R2 R3 R4 0.99 0.95 0.985 0.990.95 0.99arrow_forward
- A furnace thermostat has a constant failure rate of one failure per 25 months and a mean time to repair of four hours., Please answer last 3 subparts a) What is the thermostate reliablity after 12 months? After 24 months? After 36 months? b) What is the availablity? c) Should a design team try to streamline the repair process to reduce the MTTR? Explain. Does the location of the furnace matter? d.) Given a reliability target of 99 % ,what combination of mu,µ,and time ,t ,values will suffice? You must do at least two different combinations of µ and tarrow_forwardExplain carefully how redundancy improves product reliability?arrow_forwardA manager states that her process is really working well. Out of 1,500 parts, 1,477 were produced free of a particular defect and passed inspection. Based upon Six Sigma theory, how would you rate this performance, other things being equal? (Answer in Appendix D)arrow_forward
- Examine the systems given below. Which system is morereliable, a or b? c or d? Now calculate the reliability of eachsystem. Were your perceptions correct?If it costs $1000 for each 90% reliable component, $1500for each 93% component, $2000 for each 95% reliablecomponent, and $10,000 to replace a failed system, whichsystem would you choose, a or b? c or d?arrow_forward***Not an assignment*** As a Senior Manager of the Customer Service Department in Joyah Airlines (JOL). you are been instructed by CEO, Dato' Dony Bernadi, to execute an intensive plan mprove the Quality and Reliability of service to JOL's customers. Prepare a thorough plan on how you going to apply the concept of QRM towards excellent Quality and Reliability services to the customersarrow_forwardDavid Hall, chief of the maintenance departmentat Mechanical Dynamics, has presented you with the following failure curve. What does it suggest?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY