Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
12th Edition
ISBN: 9780134855424
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 5, Problem 19P
A paced assembly line has been devised to manufacture calculators, as the following data show:
- What is the maximum hourly output rate from this line? (Hint: The line can go only as fast as its slowest workstation.)
- What cycle time corresponds to this maximum output rate?
- If a worker is at each station and the line operates at this maximum output rate, how much idle time is lost during each 10-hour shift?
- What is the line’s efficiency?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Georgetown Pizza makes its favorite pan pizzas every day with three working shifts around the clock. The current completely cooked pizza-making process has a fixed cost of $24,000, and a variable cost of $2.75 per pizza. The owner is considering a different process that can make pizzas in two ways: completely cooked and selling at $13.98 per unit, or partially cooked with a selling price of $12.98 per unit. This alternate process has a fixed cost of $28,000, but a lower variable cost (because much less energy is used in baking) of $2.25 per pizza.
a. Determine the breakeven quantity between the current pizza-making process and the alternate process.
Georgetown Pizza makes favorite pan pizzas every day with three working shifts around the clock. The current completely cooked pizza making process has a fixed cost of $24,000, and a variable cost of $2.75 per pizza. The owner is considering a different process that can make pizzas in two ways: completely cooked and selling at $13.98 per unit, or partially cooked with a selling price of $12.98 per unit. This alternate process has a fixed cost of $28,000, but a lower variable cost (because much less energy is used in baking) of $2.25 per pizzac. If the owner expects to get $390,000 as a half year profit, how many units of completely cook pizzas, should Georgetown sell a year using the current pizza making process? d. Determine the annual design capacity for Georgetown’s production if the completely cook pizzas can be produced at 120 units per hour.
There is a canteen set up serving food (Breakfast, Lunch, Snacks-tea, and Dinner) to 500 students in a B school. It has a huge well-furnished dining hall and has a serving zone where students queue to pick up their eatables. The Institute director, during his regular Gemba walks in the canteen, has seen a lot of inefficiency in the related operational processes and needs a major improvement.
(a)Provide one relatable and relevant example of five of the eight wastes under Lean systems which are likely to be witnessed in the canteen.
(b)Recommend lean tools & techniques/system solutions to be employed for curbing each of those five wastes with a line on justification.
(c) Suggest three key enablers and measures track the progress on lean in the canteen.
Chapter 5 Solutions
Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)
Ch. 5 - Take a process that you encounter on a daily...Ch. 5 - Prob. 2DQCh. 5 - How could the efficiency of the redesigned process...Ch. 5 - Bill’s Barbershop has two barbers available to...Ch. 5 - Melissa’s Photo Studio offers both individual...Ch. 5 - Figure 5.11 details the process flow for two types...Ch. 5 - Prob. 4PCh. 5 - Super Fun Industries manufactures four top-selling...Ch. 5 - Prob. 6PCh. 5 - Yost-Perry Industries (YPI) manufactures a mix of...
Ch. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - A.J.’s Wildlife Emporium manufactures two unique...Ch. 5 - Cooper River Glass Works (RGW) produces four...Ch. 5 - Quick Stop Pharmacy is a small family-owned,...Ch. 5 - Use the longest work element rule to balance the...Ch. 5 - Johnson Cogs wants to set up a line to serve 60...Ch. 5 - Refer back to Problem 16. Suppose that in addition...Ch. 5 - To meet holiday demand, Penny’s Pie Shop...Ch. 5 - A paced assembly line has been devised to...Ch. 5 - Prob. 20PCh. 5 - Greg Davis, a business major at the University of...Ch. 5 - Prob. 1VCCh. 5 - Which boarding scenario among the different ones...Ch. 5 - How should Southwest evaluate the gate boarding...Ch. 5 - How will Southwest know that the bottleneck had...
Additional Business Textbook Solutions
Find more solutions based on key concepts
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
What is precedent, and how does it affect common law?
Business in Action
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Gordon Miller's job shop has four work areas, A, B, C, and D. Distances in feet between centers of the work areas are: A B C D A − 4 10 8 B − − 5 9 C − − − 9 D − − − − Workpieces moved per week between work areas are: A B C D A − 900 700 600 B − − 400 300 C − − − 600 D − − − − It costs Gordon $3 to move 1 work piece 1 foot. The weekly total material handling cost of the layout =....... $nothing (enter your response as a whole number). The weekly total material handling cost of the layout =....... nothing dollars (enter your response as a whole number).arrow_forwardBalance the assembly line shown below for (a) a shift output of 60 pieces and (b) a shift output of 40 pieces. Assume an 8-hour shift, and use the rule: choose the assignable task with the longest processing time. Compute the line efficiency for each case. Fill in the table below for a shift output of 60 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number. Workstation Tasks Total Time Idle Time 1 2 3 4 Total What is the assembly-line efficiency? Round your answer to one decimal place. % Fill in the table below for a shift output of 40 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number. Workstation Tasks Total Time Idle Time 1 2 3 Total What is the assembly-line efficiency? Round your answer to one decimal place. %arrow_forwardMr. Aris Benn manages an assembly line that produces a piece of equipment that is used to clean floors. The process to produce this piece of equipment consists of 10 steps. Determine what other information is needed in order to balance this assembly line. Also, set up a numerical example of the line balancing problem at hand. Using this example, demonstrate how to balance the line and how to calculate its efficiency.arrow_forward
- Compute the cycle time for Auburn Company given the following data: value add time is 12 hours and non-value add time is 4 hours and 30 minutes. Write your answer up to one decimal place only.arrow_forwardAn assembly line is to be designed for a product whosecompletion requires 21 minutes of work. The factory works400 minutes per day. Can a production line with five workstations make 100 units per day?a) Yes, with exactly 100 minutes to spare.b) No, but four workstations would be sufficient.c) No, it will fall short even with a perfectly balanced line.d) Yes, but the line’s efficiency is very low.e) Cannot be determined from the information given.arrow_forwardgiven information: which step is in bottleneck=30 min for tan leather 60/30=2 briefcases per hr are processed at the bottleneck workstation per hour throughput time of the overall process Throughput = 75 minutes PLEASE answer the following 3 questions: If the manufacturing facility operates 8 hours per day, 250 days a year, what is the annual capacity of this manufacturing process. Assume the company decides to hire additional workers in order to duplicate the bottleneck step identified in part a so that there are 3 of these workstations instead of 1. Redraw the diagram showing the flow of the revised process. Answer parts a through d again based on the new process created in part e?arrow_forward
- The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hourworkweek: e) How much total idle time is present each cycle? f ) What is the efficiency of the assembly line with five stations? With six stations?arrow_forwardNumerous IT companies are staffed by Tip Top Staffing with personnel qualified for certain projects. Lisa Nuevo and Bill Goodman are developing the logical model for Tip Top's billing and records system with the use of DFDs, a data dictionary, and process descriptions. While working on the logical basis of the system, Lisa realized that Tip Top's data forms for job applications may be enhanced. Better forms: a problem with physical implementation? By considering how something will be completed, is Lisa deviating from the work at hand?arrow_forwardA process currently services an average of 50 customers per day. Observations in recent weeks show that its utilization is about 90 percent, allowing for just a 10 percent capacity cushion. If demand is expected to be 75 percent of the current level in five years and management wants to have acapacity cushion of just 5 percent, what capacity requirement should be planned?arrow_forward
- An assembly line is to be designed for a product whose completion requires 21 minutes of work. T he factory works 400 minutes per day. Can a production line with five workstations make !00 units per day? a) Yes, with exactly 100 minutes to spare.b) No, but four workstations would be sufficient.c) No, it will fall short even with a perfectly balanced line.d) Yes, but the line's efficiency is very low.e) Cannot be determined from the information given.arrow_forwardVikiki Furniture, Inc. produces all types of office furniture. The "Executive Secretary" is a sofa-bed that has been designed using ergonomics to provide comfort during long work hours. The sofa-bed sells for $138. There are 580 minutes available during the day, and the average daily demand has been 65 items. There are eight tasks: Task performance time (min) task must follow task listed A 4 -- B 7 -- C 6 A, B D 5 C E 6 D F 7 E G 8 E H 6 F, G Total 49 min What is the Cycle time for this operation?arrow_forwardWhen a variety of processes are active at once, how does the capacity analysis react?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY