Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated duration
1. Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labelling each arrow with the activity letter and estimated duration.
2. Identify all the paths on the network diagram and note how long they are.
3. What is the critical path for this project and how long is it?
4. What is the shortest possible time needed to complete the project?
Using an application of your choice: Draw a network diagram for this project, clearly showing the Activity ID and Activity duration
Chapter 6 Solutions
Information Technology Project Management
Knowledge Booster
Similar questions
- 1-Draw the network diagram of the activities listed in the table below using Activity on Node. 2-Find the critical path and the duration of the project. 3-Find the values of ES, EC, LS, and LC of the events 4- Find the values of TF and FF for the activitiesarrow_forwardFor a particular project, consider following list of Activities, their duration in Days and their Predecessor activities. Activity Days Precedents A 3 - B 15 A C 5 A D 60 A E 6 D F 40 B G 10 C,E H 7 F I 6 G J 12 H,I By using network schedule technique, draw a Network Diagram of above enlisted activities.arrow_forwardDraw a network diagram representing the following information: the project starts with three activities—A, B, and C—which can be done concurrently. When A is finished, D can start; when B is finished, F can start; when B and D are finished, E can start. The project is complete when C, E, and F are finished.arrow_forward
- Consider Table 6-2. All duration estimates or estimated times are in days, and the network proceeds from Node 1 to Node 9. (Note that you can easily change this table to create multiple exercises.arrow_forwardFor the following activities, draw the network diagram and by using forward and backward pass, determine:-1. Project duration.2. Critical path.arrow_forward. Construct a Gantt chart and network diagram for a project you are or will be involved in. Choose a project of sufficient depth from work, home, or school. Identify the activities to be completed, determine the sequence of the activities, and construct a diagram reflecting the starting times, ending times, durations, and precedence (network diagram only) relationships among all activities. For your network diagram, use the procedure in this chapter to determine time estimates for each activity and calculate the expected time for each activity. Now determine the critical path and the early and late starting and finishing times for each activity. Which activities have slack time?arrow_forward
- Having an example to look at makes it much easier to understand a concept. If you want to do a network analysis, you have four different approaches from which to choose?arrow_forwardhow to draw a project network?arrow_forwardSTART ITEM A ACTIVITIES B C D E F G END ITEM H Prepare your own Network Diagram in order to reach the end item. Explain how you reach Item H in a paragraph form.arrow_forward
- Draw Activity diagram for this scenario When the employee ( customer to us ) encounters an issue he cant solve he goes to tawasol ( the company ticketing system ) and open a ticket for the issue in the correct section and select the issue genre, explain it and add his contact info then the ticket get assigned automatically by the system to the right IT support team, from there the team in head quarter office in Riyadh assign the task to specific member based on geographic location of the issue and the nature of the issue and the competence needed. After that the team member can see it in his/her ticketing system and can assign the status of the process is it active, pending for some reason or resolved . Then the assigned member will contact the customer to further understand the issue and decide if it could be done remotely or physically, if remotely then the assigned member need to contact the network team to allow access for remote applications on that network. Then when the issue is…arrow_forwarddraw a network diagram based on this project plan, clearly showing the Activity ID and Activity duration.arrow_forwardA more comprehensive understanding can be achieved by creating a visual representation of the project's map, both with and without the underlying architecture. Given the potential global implications of the outcome.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning