a. AOA network diagram:
Explanation of Solution
Draw an Activity on Arrow (AOA) network diagram representing the project given in Table 6.2 of the book. To accomplish the network diagram, follow the following steps:-
1. Put the node numbers 1 to 9 in circles.
2. Find all of the activities that start at node 1. Draw arrows between node 1 and those finish nodes. Put the activity letter and duration estimate on the associated arrow. In this case, Draw an edge from node 1 to 2 and label it as A=2. Label A=2 means activity A has a duration of 2 days.
3. Continue drawing the project network diagram until all activities are included on the diagrams that have dependencies.
4. Label each arrow with the activity letter and estimated time. The below network diagram has 11 arrows corresponding to 11 rows in the table.
- Draw second edge from node 2 to 3 and label it as B=2...
b. All paths on the network diagram:
Explanation of Solution
To identify all the paths on the network diagram, just follow the arrows to identify distinct routes from node 1 to node 9.
To find out length of each path, just add the duration for all activities on that path.
Path No | Route | Length / Total Duration |
c. Critical path for this project
Explanation of Solution
The longest path in the network diagram is the critical path...
d. Shortest possible time needed to complete this project:
Explanation of Solution
The critical path represents the shortest time requir...
Trending nowThis is a popular solution!
Chapter 6 Solutions
Information Technology Project Management
- 1-Draw the network diagram of the activities listed in the table below using Activity on Node. 2-Find the critical path and the duration of the project. 3-Find the values of ES, EC, LS, and LC of the events 4- Find the values of TF and FF for the activitiesarrow_forward. Construct a Gantt chart and network diagram for a project you are or will be involved in. Choose a project of sufficient depth from work, home, or school. Identify the activities to be completed, determine the sequence of the activities, and construct a diagram reflecting the starting times, ending times, durations, and precedence (network diagram only) relationships among all activities. For your network diagram, use the procedure in this chapter to determine time estimates for each activity and calculate the expected time for each activity. Now determine the critical path and the early and late starting and finishing times for each activity. Which activities have slack time?arrow_forwardDraw a network diagram representing the following information: the project starts with three activities—A, B, and C—which can be done concurrently. When A is finished, D can start; when B is finished, F can start; when B and D are finished, E can start. The project is complete when C, E, and F are finished.arrow_forward
- For a particular project, consider following list of Activities, their duration in Days and their Predecessor activities. Activity Days Precedents A 3 - B 15 A C 5 A D 60 A E 6 D F 40 B G 10 C,E H 7 F I 6 G J 12 H,I By using network schedule technique, draw a Network Diagram of above enlisted activities.arrow_forwarddraw a network diagram based on this project plan, clearly showing the Activity ID and Activity duration.arrow_forwardFor the following activities, draw the network diagram and by using forward and backward pass, determine:-1. Project duration.2. Critical path.arrow_forward
- Draw Activity diagram for this scenario When the employee ( customer to us ) encounters an issue he cant solve he goes to tawasol ( the company ticketing system ) and open a ticket for the issue in the correct section and select the issue genre, explain it and add his contact info then the ticket get assigned automatically by the system to the right IT support team, from there the team in head quarter office in Riyadh assign the task to specific member based on geographic location of the issue and the nature of the issue and the competence needed. After that the team member can see it in his/her ticketing system and can assign the status of the process is it active, pending for some reason or resolved . Then the assigned member will contact the customer to further understand the issue and decide if it could be done remotely or physically, if remotely then the assigned member need to contact the network team to allow access for remote applications on that network. Then when the issue is…arrow_forwardhow to draw a project network?arrow_forwardDraw an activity-on-node diagram for the project outlined in the following table. Task Duration (Weeks) Follows A 3 B 7 A C 9 A D 3 C E 11 B, D F 3 E G 2 F H 3 C F I 5 G, Harrow_forward
- A more comprehensive understanding can be achieved by creating a visual representation of the project's map, both with and without the underlying architecture. Given the potential global implications of the outcome.arrow_forwardUnderstanding will be aided by drawing the project's map both with and without its core architecture. Considering the effect of the finished work.arrow_forwardFor both the Spiral and the V Model, provide an example of a project you would manage with each model, briefly describe the nature of the project, and explain why you selected the specific methodology to manage it.arrow_forward
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage LearningPrinciples of Information Systems (MindTap Course...Computer ScienceISBN:9781305971776Author:Ralph Stair, George ReynoldsPublisher:Cengage LearningOperations Research : Applications and AlgorithmsComputer ScienceISBN:9780534380588Author:Wayne L. WinstonPublisher:Brooks Cole